Short answer

Total float is maximum delay to an activity without delaying project completion; free float is delay without delaying earliest start of any successor; independent float is delay using latest predecessors and earliest successors without affecting others. CPM analysis gives project duration 14 days. Critical path is A-D-G-I-J.

Define total float, free float and independent float. Draw a CPM network and find EST, EFT, LST, LFT, TF, FF, IntF and IndF. Show the critical path also.

ActivitySuccessorDuration (days)
AB, C, D2
BE3
CF, H, I4
DG5
EH4
FJ3
GI2
HJ1
IJ2
J-3

Definitions

  • Total float (TF): the time by which an activity can be delayed without delaying the project completion. TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT.
  • Free float (FF): the time by which an activity can be delayed without delaying the earliest start of any following activity. FF=min⁡(EST of successors)−EFTFF = \min(EST\ \text{of successors}) - EFT.
  • Independent float (IndF): the time available to an activity when its predecessors finish at their latest and its successors start at their earliest; using it affects no other activity. IndF=max⁡(0, min⁡(ESTsucc)−max⁡(LFTpred)−D)IndF = \max(0,\ \min(EST_{succ}) - \max(LFT_{pred}) - D).
  • Interfering float =TF−FF= TF - FF (the part of the total float that is shared with the following activities).

Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.

Network diagram (activity-on-arrow)

Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.

(1) --A(2)--> (2)
(2) --B(3)--> (3)
(2) --C(4)--> (4)
(2) --D(5)--> (5)
(3) --E(4)--> (6)
(4) - - dummy - -> (6)
(4) - - dummy - -> (7)
(4) --F(3)--> (8)
(5) --G(2)--> (7)
(6) --H(1)--> (8)
(7) --I(2)--> (8)
(8) --J(3)--> (9)

The network has 9 events and 2 dummy activities. Start event is (1) and the end event is (9).

Forward pass (EST and EFT)

Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.

  • A: EST = 0; EFT = 0 + 2 = 2
  • B: EST = EFT of A = 2; EFT = 2 + 3 = 5
  • C: EST = EFT of A = 2; EFT = 2 + 4 = 6
  • D: EST = EFT of A = 2; EFT = 2 + 5 = 7
  • E: EST = EFT of B = 5; EFT = 5 + 4 = 9
  • F: EST = EFT of C = 6; EFT = 6 + 3 = 9
  • G: EST = EFT of D = 7; EFT = 7 + 2 = 9
  • H: EST = max(C:6, E:9) = 9; EFT = 9 + 1 = 10
  • I: EST = max(C:6, G:9) = 9; EFT = 9 + 2 = 11
  • J: EST = max(F:9, H:10, I:11) = 11; EFT = 11 + 3 = 14

Project duration = largest EFT = 14 days.

Backward pass (LFT and LST)

Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.

  • J: LFT = project duration = 14; LST = 14 - 3 = 11
  • I: LFT = LST of J = 11; LST = 11 - 2 = 9
  • H: LFT = LST of J = 11; LST = 11 - 1 = 10
  • G: LFT = LST of I = 9; LST = 9 - 2 = 7
  • F: LFT = LST of J = 11; LST = 11 - 3 = 8
  • E: LFT = LST of H = 10; LST = 10 - 4 = 6
  • D: LFT = LST of G = 7; LST = 7 - 5 = 2
  • C: LFT = min(F:8, H:10, I:9) = 8; LST = 8 - 4 = 4
  • B: LFT = LST of E = 6; LST = 6 - 3 = 3
  • A: LFT = min(B:3, C:4, D:2) = 2; LST = 2 - 2 = 0

Floats

  • Total float TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT
  • Free float FF=min⁡(EST of successors)−EFTFF = \min(\text{EST of successors}) - EFT
  • Interfering float IntF=TF−FFIntF = TF - FF
  • Independent float IndF=max⁡(0, min⁡(EST of successors)−max⁡(LFT of predecessors)−D)IndF = \max\left(0,\ \min(\text{EST of successors}) - \max(\text{LFT of predecessors}) - D\right)

Result table

ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A202020000
B325361010
C426482020
D527270000
E4596101010
F3698112200
G279790000
H191010111100
I29119110000
J3111411140000

Event times (TE from the forward pass, TL from the backward pass):

EventTE (earliest)TL (latest)Slack
1000
2220
3561
4682
5770
69101
7990
811110
914140

Critical path and project duration

  • Critical activities (TF = 0): A, D, G, I, J
  • Critical path: A - D - G - I - J (= 2+5+2+2+3 = 14 days)

Answer: project duration = 14 days; critical path = A - D - G - I - J