- 2074 Asoj · 16 marks
CPM network, 10 activities with successors
Short answer
Total float is maximum delay to an activity without delaying project completion; free float is delay without delaying earliest start of any successor; independent float is delay using latest predecessors and earliest successors without affecting others. CPM analysis gives project duration 14 days. Critical path is A-D-G-I-J.
Define total float, free float and independent float. Draw a CPM network and find EST, EFT, LST, LFT, TF, FF, IntF and IndF. Show the critical path also.
| Activity | Successor | Duration (days) |
|---|---|---|
| A | B, C, D | 2 |
| B | E | 3 |
| C | F, H, I | 4 |
| D | G | 5 |
| E | H | 4 |
| F | J | 3 |
| G | I | 2 |
| H | J | 1 |
| I | J | 2 |
| J | - | 3 |
Definitions
- Total float (TF): the time by which an activity can be delayed without delaying the project completion. .
- Free float (FF): the time by which an activity can be delayed without delaying the earliest start of any following activity. .
- Independent float (IndF): the time available to an activity when its predecessors finish at their latest and its successors start at their earliest; using it affects no other activity. .
- Interfering float (the part of the total float that is shared with the following activities).
Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.
Network diagram (activity-on-arrow)
Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.
(1) --A(2)--> (2)
(2) --B(3)--> (3)
(2) --C(4)--> (4)
(2) --D(5)--> (5)
(3) --E(4)--> (6)
(4) - - dummy - -> (6)
(4) - - dummy - -> (7)
(4) --F(3)--> (8)
(5) --G(2)--> (7)
(6) --H(1)--> (8)
(7) --I(2)--> (8)
(8) --J(3)--> (9)
The network has 9 events and 2 dummy activities. Start event is (1) and the end event is (9).
Forward pass (EST and EFT)
Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.
- A: EST = 0; EFT = 0 + 2 = 2
- B: EST = EFT of A = 2; EFT = 2 + 3 = 5
- C: EST = EFT of A = 2; EFT = 2 + 4 = 6
- D: EST = EFT of A = 2; EFT = 2 + 5 = 7
- E: EST = EFT of B = 5; EFT = 5 + 4 = 9
- F: EST = EFT of C = 6; EFT = 6 + 3 = 9
- G: EST = EFT of D = 7; EFT = 7 + 2 = 9
- H: EST = max(C:6, E:9) = 9; EFT = 9 + 1 = 10
- I: EST = max(C:6, G:9) = 9; EFT = 9 + 2 = 11
- J: EST = max(F:9, H:10, I:11) = 11; EFT = 11 + 3 = 14
Project duration = largest EFT = 14 days.
Backward pass (LFT and LST)
Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.
- J: LFT = project duration = 14; LST = 14 - 3 = 11
- I: LFT = LST of J = 11; LST = 11 - 2 = 9
- H: LFT = LST of J = 11; LST = 11 - 1 = 10
- G: LFT = LST of I = 9; LST = 9 - 2 = 7
- F: LFT = LST of J = 11; LST = 11 - 3 = 8
- E: LFT = LST of H = 10; LST = 10 - 4 = 6
- D: LFT = LST of G = 7; LST = 7 - 5 = 2
- C: LFT = min(F:8, H:10, I:9) = 8; LST = 8 - 4 = 4
- B: LFT = LST of E = 6; LST = 6 - 3 = 3
- A: LFT = min(B:3, C:4, D:2) = 2; LST = 2 - 2 = 0
Floats
- Total float
- Free float
- Interfering float
- Independent float
Result table
| Activity | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F |
|---|---|---|---|---|---|---|---|---|---|
| A | 2 | 0 | 2 | 0 | 2 | 0 | 0 | 0 | 0 |
| B | 3 | 2 | 5 | 3 | 6 | 1 | 0 | 1 | 0 |
| C | 4 | 2 | 6 | 4 | 8 | 2 | 0 | 2 | 0 |
| D | 5 | 2 | 7 | 2 | 7 | 0 | 0 | 0 | 0 |
| E | 4 | 5 | 9 | 6 | 10 | 1 | 0 | 1 | 0 |
| F | 3 | 6 | 9 | 8 | 11 | 2 | 2 | 0 | 0 |
| G | 2 | 7 | 9 | 7 | 9 | 0 | 0 | 0 | 0 |
| H | 1 | 9 | 10 | 10 | 11 | 1 | 1 | 0 | 0 |
| I | 2 | 9 | 11 | 9 | 11 | 0 | 0 | 0 | 0 |
| J | 3 | 11 | 14 | 11 | 14 | 0 | 0 | 0 | 0 |
Event times (TE from the forward pass, TL from the backward pass):
| Event | TE (earliest) | TL (latest) | Slack |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 2 | 2 | 0 |
| 3 | 5 | 6 | 1 |
| 4 | 6 | 8 | 2 |
| 5 | 7 | 7 | 0 |
| 6 | 9 | 10 | 1 |
| 7 | 9 | 9 | 0 |
| 8 | 11 | 11 | 0 |
| 9 | 14 | 14 | 0 |
Critical path and project duration
- Critical activities (TF = 0): A, D, G, I, J
- Critical path: A - D - G - I - J (= 2+5+2+2+3 = 14 days)
Answer: project duration = 14 days; critical path = A - D - G - I - J
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM network, 9 activities with successors · Project Engineering, chapter 3
- CPM network, 10 activities (A=4 to J=9) · Project Engineering, chapter 3
- CPM network, 9 activities with successors · Project Engineering, chapter 3 · asked 2×
- CPM network, 12 activities (A=10 to L=8) · Project Engineering, chapter 3
- CPM network, 10 activities (A=5 to J=5) · Project Engineering, chapter 3
- CPM network, 13 activities (A to M) · Project Engineering, chapter 3 · asked 5×
- CPM schedule, critical path and float · Industrial Engineering and Management, chapter 3
- TCTO numerical: crashing critical path, Rs 30/day · Construction Management, chapter 2