CPM network, 9 activities with successors

Short answer

With the AOA network drawn, forward and backward passes give all event/activity times and floats. Project duration is 13 days. Critical path is A-D-G-I (5+3+3+2 days). Total float shows which activities are critical and how long non-critical ones may slip without delaying the project.

Draw network diagram. Compute EST, EFT, LST, LFT, TF, FF, interfering float and independent float. Write down the significance of calculating total float in network analysis.

ActivityDuration (day)PredecessorSuccessor
A5-B, C, D
B4AE
C2AF, H
D3AG
E2BH
F1CI
G3DI
H1C, E-
I2F, G-

Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.

Network diagram (activity-on-arrow)

Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.

(1) --A(5)--> (2)
(2) --B(4)--> (3)
(2) --C(2)--> (4)
(2) --D(3)--> (5)
(3) --E(2)--> (6)
(4) - - dummy - -> (6)
(4) --F(1)--> (7)
(5) --G(3)--> (7)
(6) --H(1)--> (8)
(7) --I(2)--> (8)

The network has 8 events and 1 dummy activity. Start event is (1) and the end event is (8).

Forward pass (EST and EFT)

Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.

  • A: EST = 0; EFT = 0 + 5 = 5
  • B: EST = EFT of A = 5; EFT = 5 + 4 = 9
  • C: EST = EFT of A = 5; EFT = 5 + 2 = 7
  • D: EST = EFT of A = 5; EFT = 5 + 3 = 8
  • F: EST = EFT of C = 7; EFT = 7 + 1 = 8
  • G: EST = EFT of D = 8; EFT = 8 + 3 = 11
  • E: EST = EFT of B = 9; EFT = 9 + 2 = 11
  • H: EST = max(C:7, E:11) = 11; EFT = 11 + 1 = 12
  • I: EST = max(F:8, G:11) = 11; EFT = 11 + 2 = 13

Project duration = largest EFT = 13 days.

Backward pass (LFT and LST)

Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.

  • I: LFT = project duration = 13; LST = 13 - 2 = 11
  • H: LFT = project duration = 13; LST = 13 - 1 = 12
  • E: LFT = LST of H = 12; LST = 12 - 2 = 10
  • G: LFT = LST of I = 11; LST = 11 - 3 = 8
  • F: LFT = LST of I = 11; LST = 11 - 1 = 10
  • D: LFT = LST of G = 8; LST = 8 - 3 = 5
  • C: LFT = min(F:10, H:12) = 10; LST = 10 - 2 = 8
  • B: LFT = LST of E = 10; LST = 10 - 4 = 6
  • A: LFT = min(B:6, C:8, D:5) = 5; LST = 5 - 5 = 0

Floats

  • Total float TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT
  • Free float FF=min⁡(EST of successors)−EFTFF = \min(\text{EST of successors}) - EFT
  • Interfering float IntF=TF−FFIntF = TF - FF
  • Independent float IndF=max⁡(0, min⁡(EST of successors)−max⁡(LFT of predecessors)−D)IndF = \max\left(0,\ \min(\text{EST of successors}) - \max(\text{LFT of predecessors}) - D\right)

Result table

ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A505050000
B4596101010
C2578103030
D358580000
E291110121010
F17810113300
G38118110000
H1111212131100
I2111311130000

Event times (TE from the forward pass, TL from the backward pass):

EventTE (earliest)TL (latest)Slack
1000
2550
39101
47103
5880
611121
711110
813130

Critical path and project duration

  • Critical activities (TF = 0): A, D, G, I
  • Critical path: A - D - G - I (= 5+3+3+2 = 13 days)

Answer: project duration = 13 days; critical path = A - D - G - I

Significance of total float

  • Activities with TF = 0 are critical; they decide the project duration, so they get the closest control and priority in resources.
  • TF tells how long a non-critical activity may be delayed without delaying the project, which helps to decide its start date.
  • It is used to level and smooth resources, shifting activities inside their float to cut peaks.
  • It shows which activities can release men and machines to the critical activities when the project must be speeded up.
  • It is the cushion against delay; when TF becomes negative the project is behind schedule and corrective action is needed.
  • Float is shared along a path, so using it on one activity reduces the float of the others on the same path.

✓ Answer checked by Claude Opus 5.5 (high effort)