- 2076 Asoj · 16 marks
CPM network, 9 activities with successors
Short answer
With the AOA network drawn, forward and backward passes give all event/activity times and floats. Project duration is 13 days. Critical path is A-D-G-I (5+3+3+2 days). Total float shows which activities are critical and how long non-critical ones may slip without delaying the project.
Draw network diagram. Compute EST, EFT, LST, LFT, TF, FF, interfering float and independent float. Write down the significance of calculating total float in network analysis.
| Activity | Duration (day) | Predecessor | Successor |
|---|---|---|---|
| A | 5 | - | B, C, D |
| B | 4 | A | E |
| C | 2 | A | F, H |
| D | 3 | A | G |
| E | 2 | B | H |
| F | 1 | C | I |
| G | 3 | D | I |
| H | 1 | C, E | - |
| I | 2 | F, G | - |
Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.
Network diagram (activity-on-arrow)
Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.
(1) --A(5)--> (2)
(2) --B(4)--> (3)
(2) --C(2)--> (4)
(2) --D(3)--> (5)
(3) --E(2)--> (6)
(4) - - dummy - -> (6)
(4) --F(1)--> (7)
(5) --G(3)--> (7)
(6) --H(1)--> (8)
(7) --I(2)--> (8)
The network has 8 events and 1 dummy activity. Start event is (1) and the end event is (8).
Forward pass (EST and EFT)
Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.
- A: EST = 0; EFT = 0 + 5 = 5
- B: EST = EFT of A = 5; EFT = 5 + 4 = 9
- C: EST = EFT of A = 5; EFT = 5 + 2 = 7
- D: EST = EFT of A = 5; EFT = 5 + 3 = 8
- F: EST = EFT of C = 7; EFT = 7 + 1 = 8
- G: EST = EFT of D = 8; EFT = 8 + 3 = 11
- E: EST = EFT of B = 9; EFT = 9 + 2 = 11
- H: EST = max(C:7, E:11) = 11; EFT = 11 + 1 = 12
- I: EST = max(F:8, G:11) = 11; EFT = 11 + 2 = 13
Project duration = largest EFT = 13 days.
Backward pass (LFT and LST)
Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.
- I: LFT = project duration = 13; LST = 13 - 2 = 11
- H: LFT = project duration = 13; LST = 13 - 1 = 12
- E: LFT = LST of H = 12; LST = 12 - 2 = 10
- G: LFT = LST of I = 11; LST = 11 - 3 = 8
- F: LFT = LST of I = 11; LST = 11 - 1 = 10
- D: LFT = LST of G = 8; LST = 8 - 3 = 5
- C: LFT = min(F:10, H:12) = 10; LST = 10 - 2 = 8
- B: LFT = LST of E = 10; LST = 10 - 4 = 6
- A: LFT = min(B:6, C:8, D:5) = 5; LST = 5 - 5 = 0
Floats
- Total float
- Free float
- Interfering float
- Independent float
Result table
| Activity | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F |
|---|---|---|---|---|---|---|---|---|---|
| A | 5 | 0 | 5 | 0 | 5 | 0 | 0 | 0 | 0 |
| B | 4 | 5 | 9 | 6 | 10 | 1 | 0 | 1 | 0 |
| C | 2 | 5 | 7 | 8 | 10 | 3 | 0 | 3 | 0 |
| D | 3 | 5 | 8 | 5 | 8 | 0 | 0 | 0 | 0 |
| E | 2 | 9 | 11 | 10 | 12 | 1 | 0 | 1 | 0 |
| F | 1 | 7 | 8 | 10 | 11 | 3 | 3 | 0 | 0 |
| G | 3 | 8 | 11 | 8 | 11 | 0 | 0 | 0 | 0 |
| H | 1 | 11 | 12 | 12 | 13 | 1 | 1 | 0 | 0 |
| I | 2 | 11 | 13 | 11 | 13 | 0 | 0 | 0 | 0 |
Event times (TE from the forward pass, TL from the backward pass):
| Event | TE (earliest) | TL (latest) | Slack |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 5 | 5 | 0 |
| 3 | 9 | 10 | 1 |
| 4 | 7 | 10 | 3 |
| 5 | 8 | 8 | 0 |
| 6 | 11 | 12 | 1 |
| 7 | 11 | 11 | 0 |
| 8 | 13 | 13 | 0 |
Critical path and project duration
- Critical activities (TF = 0): A, D, G, I
- Critical path: A - D - G - I (= 5+3+3+2 = 13 days)
Answer: project duration = 13 days; critical path = A - D - G - I
Significance of total float
- Activities with TF = 0 are critical; they decide the project duration, so they get the closest control and priority in resources.
- TF tells how long a non-critical activity may be delayed without delaying the project, which helps to decide its start date.
- It is used to level and smooth resources, shifting activities inside their float to cut peaks.
- It shows which activities can release men and machines to the critical activities when the project must be speeded up.
- It is the cushion against delay; when TF becomes negative the project is behind schedule and corrective action is needed.
- Float is shared along a path, so using it on one activity reduces the float of the others on the same path.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM network, 10 activities with successors · Project Engineering, chapter 3
- CPM network, 9 activities with successors · Project Engineering, chapter 3 · asked 2×
- CPM network, 10 activities (A=4 to J=9) · Project Engineering, chapter 3
- CPM network, 12 activities (A=10 to L=8) · Project Engineering, chapter 3
- CPM network, 10 activities (A=10 to J=4) · Project Engineering, chapter 3
- CPM network, 9 activities (A=3 to I=1) · Project Engineering, chapter 3 · asked 5×
- CPM schedule, critical path and float · Industrial Engineering and Management, chapter 3
- TCTO numerical: seven activities, Rs 225/day · Construction Management, chapter 2