- 2079 Baisakh · 12 marks
CPM network, 10 activities (A=10 to J=4)
Short answer
AOA network without dummies; forward/backward pass yields 42 days. Critical path A-B-E-I-J with critical activities A, B, E, I, J; all activity times and floats computed, with zero total float on critical activities.
Draw the network diagram and compute EST, EFT, LST, LFT, TF, FF, IF and interfering floats of each activity of a project having the precedence relationship given below. The time durations are in days.
| Activity | Duration (days) | Predecessor |
|---|---|---|
| A | 10 | - |
| B | 12 | A |
| C | 8 | A |
| D | 6 | A |
| E | 10 | B |
| F | 8 | D |
| G | 4 | C |
| H | 10 | G |
| I | 6 | E |
| J | 4 | F, H, I |
Here IF is taken as the independent float; interfering float = TF - FF.
Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.
Network diagram (activity-on-arrow)
Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.
(1) --A(10)--> (2)
(2) --B(12)--> (3)
(2) --C(8)--> (4)
(2) --D(6)--> (5)
(3) --E(10)--> (6)
(4) --G(4)--> (7)
(5) --F(8)--> (8)
(6) --I(6)--> (8)
(7) --H(10)--> (8)
(8) --J(4)--> (9)
The network has 9 events and 0 dummy activities. Start event is (1) and the end event is (9).
Forward pass (EST and EFT)
Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.
- A: EST = 0; EFT = 0 + 10 = 10
- B: EST = EFT of A = 10; EFT = 10 + 12 = 22
- C: EST = EFT of A = 10; EFT = 10 + 8 = 18
- D: EST = EFT of A = 10; EFT = 10 + 6 = 16
- F: EST = EFT of D = 16; EFT = 16 + 8 = 24
- G: EST = EFT of C = 18; EFT = 18 + 4 = 22
- E: EST = EFT of B = 22; EFT = 22 + 10 = 32
- H: EST = EFT of G = 22; EFT = 22 + 10 = 32
- I: EST = EFT of E = 32; EFT = 32 + 6 = 38
- J: EST = max(F:24, H:32, I:38) = 38; EFT = 38 + 4 = 42
Project duration = largest EFT = 42 days.
Backward pass (LFT and LST)
Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.
- J: LFT = project duration = 42; LST = 42 - 4 = 38
- I: LFT = LST of J = 38; LST = 38 - 6 = 32
- H: LFT = LST of J = 38; LST = 38 - 10 = 28
- E: LFT = LST of I = 32; LST = 32 - 10 = 22
- G: LFT = LST of H = 28; LST = 28 - 4 = 24
- F: LFT = LST of J = 38; LST = 38 - 8 = 30
- D: LFT = LST of F = 30; LST = 30 - 6 = 24
- C: LFT = LST of G = 24; LST = 24 - 8 = 16
- B: LFT = LST of E = 22; LST = 22 - 12 = 10
- A: LFT = min(B:10, C:16, D:24) = 10; LST = 10 - 10 = 0
Floats
- Total float
- Free float
- Interfering float
- Independent float
Result table
| Activity | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F |
|---|---|---|---|---|---|---|---|---|---|
| A | 10 | 0 | 10 | 0 | 10 | 0 | 0 | 0 | 0 |
| B | 12 | 10 | 22 | 10 | 22 | 0 | 0 | 0 | 0 |
| C | 8 | 10 | 18 | 16 | 24 | 6 | 0 | 6 | 0 |
| D | 6 | 10 | 16 | 24 | 30 | 14 | 0 | 14 | 0 |
| E | 10 | 22 | 32 | 22 | 32 | 0 | 0 | 0 | 0 |
| F | 8 | 16 | 24 | 30 | 38 | 14 | 14 | 0 | 0 |
| G | 4 | 18 | 22 | 24 | 28 | 6 | 0 | 6 | 0 |
| H | 10 | 22 | 32 | 28 | 38 | 6 | 6 | 0 | 0 |
| I | 6 | 32 | 38 | 32 | 38 | 0 | 0 | 0 | 0 |
| J | 4 | 38 | 42 | 38 | 42 | 0 | 0 | 0 | 0 |
Event times (TE from the forward pass, TL from the backward pass):
| Event | TE (earliest) | TL (latest) | Slack |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 10 | 10 | 0 |
| 3 | 22 | 22 | 0 |
| 4 | 18 | 24 | 6 |
| 5 | 16 | 30 | 14 |
| 6 | 32 | 32 | 0 |
| 7 | 22 | 28 | 6 |
| 8 | 38 | 38 | 0 |
| 9 | 42 | 42 | 0 |
Critical path and project duration
- Critical activities (TF = 0): A, B, E, I, J
- Critical path: A - B - E - I - J (= 10+12+10+6+4 = 42 days)
Answer: project duration = 42 days; critical path = A - B - E - I - J
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM network, 12 activities (A=10 to L=8) · Project Engineering, chapter 3
- CPM network, 10 activities (A=4 to J=9) · Project Engineering, chapter 3
- CPM network, 12 activities (A=8 to L=3) · Project Engineering, chapter 3
- CPM network, 10 activities (A=5 to J=5) · Project Engineering, chapter 3
- CPM precedence diagram, 9 activities · Project Engineering, chapter 3
- CPM network, 10 activities with successors · Project Engineering, chapter 3