CPM network, 10 activities (A=10 to J=4)

Short answer

AOA network without dummies; forward/backward pass yields 42 days. Critical path A-B-E-I-J with critical activities A, B, E, I, J; all activity times and floats computed, with zero total float on critical activities.

Draw the network diagram and compute EST, EFT, LST, LFT, TF, FF, IF and interfering floats of each activity of a project having the precedence relationship given below. The time durations are in days.

ActivityDuration (days)Predecessor
A10-
B12A
C8A
D6A
E10B
F8D
G4C
H10G
I6E
J4F, H, I

Here IF is taken as the independent float; interfering float = TF - FF.

Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.

Network diagram (activity-on-arrow)

Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.

(1) --A(10)--> (2)
(2) --B(12)--> (3)
(2) --C(8)--> (4)
(2) --D(6)--> (5)
(3) --E(10)--> (6)
(4) --G(4)--> (7)
(5) --F(8)--> (8)
(6) --I(6)--> (8)
(7) --H(10)--> (8)
(8) --J(4)--> (9)

The network has 9 events and 0 dummy activities. Start event is (1) and the end event is (9).

Forward pass (EST and EFT)

Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.

  • A: EST = 0; EFT = 0 + 10 = 10
  • B: EST = EFT of A = 10; EFT = 10 + 12 = 22
  • C: EST = EFT of A = 10; EFT = 10 + 8 = 18
  • D: EST = EFT of A = 10; EFT = 10 + 6 = 16
  • F: EST = EFT of D = 16; EFT = 16 + 8 = 24
  • G: EST = EFT of C = 18; EFT = 18 + 4 = 22
  • E: EST = EFT of B = 22; EFT = 22 + 10 = 32
  • H: EST = EFT of G = 22; EFT = 22 + 10 = 32
  • I: EST = EFT of E = 32; EFT = 32 + 6 = 38
  • J: EST = max(F:24, H:32, I:38) = 38; EFT = 38 + 4 = 42

Project duration = largest EFT = 42 days.

Backward pass (LFT and LST)

Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.

  • J: LFT = project duration = 42; LST = 42 - 4 = 38
  • I: LFT = LST of J = 38; LST = 38 - 6 = 32
  • H: LFT = LST of J = 38; LST = 38 - 10 = 28
  • E: LFT = LST of I = 32; LST = 32 - 10 = 22
  • G: LFT = LST of H = 28; LST = 28 - 4 = 24
  • F: LFT = LST of J = 38; LST = 38 - 8 = 30
  • D: LFT = LST of F = 30; LST = 30 - 6 = 24
  • C: LFT = LST of G = 24; LST = 24 - 8 = 16
  • B: LFT = LST of E = 22; LST = 22 - 12 = 10
  • A: LFT = min(B:10, C:16, D:24) = 10; LST = 10 - 10 = 0

Floats

  • Total float TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT
  • Free float FF=min⁡(EST of successors)−EFTFF = \min(\text{EST of successors}) - EFT
  • Interfering float IntF=TF−FFIntF = TF - FF
  • Independent float IndF=max⁡(0, min⁡(EST of successors)−max⁡(LFT of predecessors)−D)IndF = \max\left(0,\ \min(\text{EST of successors}) - \max(\text{LFT of predecessors}) - D\right)

Result table

ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A100100100000
B12102210220000
C8101816246060
D610162430140140
E10223222320000
F816243038141400
G4182224286060
H10223228386600
I6323832380000
J4384238420000

Event times (TE from the forward pass, TL from the backward pass):

EventTE (earliest)TL (latest)Slack
1000
210100
322220
418246
5163014
632320
722286
838380
942420

Critical path and project duration

  • Critical activities (TF = 0): A, B, E, I, J
  • Critical path: A - B - E - I - J (= 10+12+10+6+4 = 42 days)

Answer: project duration = 42 days; critical path = A - B - E - I - J