Draw the CPM network diagram (or precedence diagram) from the following activity relationships. Compute the total minimum project time of completion, critical activities and ES, EF, LS, LF, TF, FF, IntF and IndF. Also mark the critical path in the network diagram.

ActivityDurationPredecessorSuccessor
A3-B, C, D
B5AE
C5AE, F
D6AG
E2B, CG
F3CG
G4D, E, FI
H2DI
I6G, H-

Total minimum project time, critical activities, the eight CPM values (ES, EF, LS, LF, TF, FF, IntF, IndF) and the critical path are found below.

Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.

Network diagram (activity-on-arrow)

Each activity is an arrow with its duration in brackets (time units). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only. Double arrows (==>) mark the critical path.

(1) ==A(3)==> (2)
(2) ==C(5)==> (3)
(2) --B(5)--> (4)
(2) --D(6)--> (5)
(3) - - dummy - -> (4)
(3) ==F(3)==> (6)
(4) --E(2)--> (6)
(5) - - dummy - -> (6)
(5) --H(2)--> (7)
(6) ==G(4)==> (7)
(7) ==I(6)==> (8)

The network has 8 events and 2 dummy activities. The dummy 3-4 makes E depend on both B and C; the dummy 5-6 makes G depend on D while H follows D alone. The start event is (1) and the end event is (8).

Critical path on the network: (1) - A - (2) - C - (3) - F - (6) - G - (7) - I - (8).

Forward pass (EST and EFT)

Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.

  • A: EST = 0; EFT = 0 + 3 = 3
  • B: EST = EFT of A = 3; EFT = 3 + 5 = 8
  • C: EST = EFT of A = 3; EFT = 3 + 5 = 8
  • D: EST = EFT of A = 3; EFT = 3 + 6 = 9
  • E: EST = max(B:8, C:8) = 8; EFT = 8 + 2 = 10
  • F: EST = EFT of C = 8; EFT = 8 + 3 = 11
  • H: EST = EFT of D = 9; EFT = 9 + 2 = 11
  • G: EST = max(D:9, E:10, F:11) = 11; EFT = 11 + 4 = 15
  • I: EST = max(G:15, H:11) = 15; EFT = 15 + 6 = 21

Project duration = largest EFT = 21 time units.

Backward pass (LFT and LST)

Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.

  • I: LFT = project duration = 21; LST = 21 - 6 = 15
  • G: LFT = LST of I = 15; LST = 15 - 4 = 11
  • H: LFT = LST of I = 15; LST = 15 - 2 = 13
  • F: LFT = LST of G = 11; LST = 11 - 3 = 8
  • E: LFT = LST of G = 11; LST = 11 - 2 = 9
  • D: LFT = min(G:11, H:13) = 11; LST = 11 - 6 = 5
  • C: LFT = min(E:9, F:8) = 8; LST = 8 - 5 = 3
  • B: LFT = LST of E = 9; LST = 9 - 5 = 4
  • A: LFT = min(B:4, C:3, D:5) = 3; LST = 3 - 3 = 0

Floats

  • Total float TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT
  • Free float FF=min⁡(EST of successors)−EFTFF = \min(\text{EST of successors}) - EFT
  • Interfering float IntF=TF−FFIntF = TF - FF
  • Independent float IndF=max⁡(0, min⁡(EST of successors)−max⁡(LFT of predecessors)−D)IndF = \max\left(0,\ \min(\text{EST of successors}) - \max(\text{LFT of predecessors}) - D\right)

Result table

ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A303030000
B538491010
C538380000
D6395112020
E28109111100
F38118110000
G4111511150000
H291113154402
I6152115210000

Event times (TE from the forward pass, TL from the backward pass):

EventTE (earliest)TL (latest)Slack
1000
2330
3880
4891
59112
611110
715150
821210

Critical path and project duration

  • Critical activities (TF = 0): A, C, F, G, I
  • Critical path: A - C - F - G - I (= 3+5+3+4+6 = 21 time units)

Answer: total minimum project time = 21 time units; critical path = A - C - F - G - I