- Asked 5/26
- 2082 Bhadra · 14 marks
- 2074 Chaitra · 12 marks
CPM network, 9 activities (A=3 to I=1)
Short answer
Forward and backward pass on activity-on-arrow network yields project duration 19 weeks. Critical path: A-C-E-G-I.
Draw the CPM network diagram and compute EST, EFT, LST, LFT, TF, FF, Int.F and Ind.F from the information given below. Also compute the project duration and mark the critical path.
| Activity | Duration (week) | Predecessor |
|---|---|---|
| A | 3 | - |
| B | 2 | - |
| C | 0 | A |
| D | 4 | A |
| E | 7 | B, C |
| F | 5 | B, C |
| G | 8 | D, E |
| H | 6 | F |
| I | 1 | G, H |
Network diagram (activity on arrow)
Events are numbered 1 to 7. Activity C has zero duration, so event 3 is reached when both A (via C) and B finish. Event times (EST = LST) are: 1: 0, 2: 3, 3: 3, 4: 10, 6: 18, 7: 19; event 5 has EST 8 and LST 12.
+------D4-------+
| v
(1)-A3->(2)-C0->(3)-E7->(4)-G8->(6)-I1->(7)
| ^ | ^
+-----B2-------+ +-F5->(5)-H6---+
Event 4 follows D and E, event 6 follows G and H, and event 7 is the end.
Forward pass (EST, EFT)
= largest of predecessors; .
Backward pass (LFT, LST)
= smallest of successors; . Project duration weeks.
Floats
; ; ; .
| Act | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F | Critical |
|---|---|---|---|---|---|---|---|---|---|---|
| A | 3 | 0 | 3 | 0 | 3 | 0 | 0 | 0 | 0 | Yes |
| B | 2 | 0 | 2 | 1 | 3 | 1 | 1 | 0 | 1 | No |
| C | 0 | 3 | 3 | 3 | 3 | 0 | 0 | 0 | 0 | Yes |
| D | 4 | 3 | 7 | 6 | 10 | 3 | 3 | 0 | 3 | No |
| E | 7 | 3 | 10 | 3 | 10 | 0 | 0 | 0 | 0 | Yes |
| F | 5 | 3 | 8 | 7 | 12 | 4 | 0 | 4 | 0 | No |
| G | 8 | 10 | 18 | 10 | 18 | 0 | 0 | 0 | 0 | Yes |
| H | 6 | 8 | 14 | 12 | 18 | 4 | 4 | 0 | 0 | No |
| I | 1 | 18 | 19 | 18 | 19 | 0 | 0 | 0 | 0 | Yes |
Sample check, activity F: ; ; ; ; ; ; .
Answer: Project duration = 19 weeks. Critical path: A - C - E - G - I ().
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM network, 9 activities (A=5 to I=2) · Project Engineering, chapter 3 · asked 5×
- CPM network, 13 activities (A to M) · Project Engineering, chapter 3 · asked 5×
- CPM network, 13 activities (A=2 to M=7) · Project Engineering, chapter 3 · asked 5×
- CPM network, 12 activities (A=10 to L=8) · Project Engineering, chapter 3
- CPM network, 12 activities (A=8 to L=3) · Project Engineering, chapter 3
- CPM network, 10 activities (A=4 to J=9) · Project Engineering, chapter 3
- CPM network, 10 activities with successors · Project Engineering, chapter 3
- CPM network, 10 activities (A=10 to J=4) · Project Engineering, chapter 3
- CPM network, building project (A to K) · Project Engineering, chapter 3
- CPM schedule, critical path and float · Industrial Engineering and Management, chapter 3