CPM network, 12 activities (A=8 to L=3)

Short answer

Draw the activity-on-arrow network with dummies, then do forward pass for EST/EFT and backward pass for LST/LFT. Floats: TF=LST-EST, FF=min successor EST minus EFT, IntF=TF-FF, IndF=max(0, min succ EST minus max pred LFT minus D). Project duration is 19 time units; critical path B-D-F-L.

A project has the following schedule. Construct the network diagram and compute EST, EFT, LST, LFT, TF, FF, IF and interfering floats for each activity and find the critical path.

ActivityTimePredecessor
A8None
B2None
C1A
D9B
E4B
F5C, D
G6E
H3E
I3G, H
J5H
K2I, J
L3E, F

IF is taken as independent float.

Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.

Network diagram (activity-on-arrow)

Each activity is an arrow with its duration in brackets (time units). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.

(1) --A(8)--> (2)
(1) --B(2)--> (3)
(2) --C(1)--> (4)
(3) --D(9)--> (4)
(3) --E(4)--> (5)
(4) --F(5)--> (7)
(5) --H(3)--> (6)
(5) - - dummy - -> (7)
(5) --G(6)--> (8)
(6) - - dummy - -> (8)
(6) --J(5)--> (9)
(7) --L(3)--> (10)
(8) --I(3)--> (9)
(9) --K(2)--> (10)

The network has 10 events and 2 dummy activities. Start event is (1) and the end event is (10).

Forward pass (EST and EFT)

Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.

  • A: EST = 0; EFT = 0 + 8 = 8
  • B: EST = 0; EFT = 0 + 2 = 2
  • D: EST = EFT of B = 2; EFT = 2 + 9 = 11
  • E: EST = EFT of B = 2; EFT = 2 + 4 = 6
  • G: EST = EFT of E = 6; EFT = 6 + 6 = 12
  • H: EST = EFT of E = 6; EFT = 6 + 3 = 9
  • C: EST = EFT of A = 8; EFT = 8 + 1 = 9
  • J: EST = EFT of H = 9; EFT = 9 + 5 = 14
  • F: EST = max(C:9, D:11) = 11; EFT = 11 + 5 = 16
  • I: EST = max(G:12, H:9) = 12; EFT = 12 + 3 = 15
  • K: EST = max(I:15, J:14) = 15; EFT = 15 + 2 = 17
  • L: EST = max(E:6, F:16) = 16; EFT = 16 + 3 = 19

Project duration = largest EFT = 19 time units.

Backward pass (LFT and LST)

Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.

  • L: LFT = project duration = 19; LST = 19 - 3 = 16
  • K: LFT = project duration = 19; LST = 19 - 2 = 17
  • I: LFT = LST of K = 17; LST = 17 - 3 = 14
  • F: LFT = LST of L = 16; LST = 16 - 5 = 11
  • J: LFT = LST of K = 17; LST = 17 - 5 = 12
  • C: LFT = LST of F = 11; LST = 11 - 1 = 10
  • H: LFT = min(I:14, J:12) = 12; LST = 12 - 3 = 9
  • G: LFT = LST of I = 14; LST = 14 - 6 = 8
  • E: LFT = min(G:8, H:9, L:16) = 8; LST = 8 - 4 = 4
  • D: LFT = LST of F = 11; LST = 11 - 9 = 2
  • B: LFT = min(D:2, E:4) = 2; LST = 2 - 2 = 0
  • A: LFT = LST of C = 10; LST = 10 - 8 = 2

Floats

  • Total float TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT
  • Free float FF=min⁡(EST of successors)−EFTFF = \min(\text{EST of successors}) - EFT
  • Interfering float IntF=TF−FFIntF = TF - FF
  • Independent float IndF=max⁡(0, min⁡(EST of successors)−max⁡(LFT of predecessors)−D)IndF = \max\left(0,\ \min(\text{EST of successors}) - \max(\text{LFT of predecessors}) - D\right)

Result table

ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A8082102020
B202020000
C18910112200
D92112110000
E426482020
F5111611160000
G66128142020
H3699123030
I3121514172020
J591412173120
K2151717192200
L3161916190000

Event times (TE from the forward pass, TL from the backward pass):

EventTE (earliest)TL (latest)Slack
1000
28102
3220
411110
5682
69123
716160
812142
915172
1019190

Critical path and project duration

  • Critical activities (TF = 0): B, D, F, L
  • Critical path: B - D - F - L (= 2+9+5+3 = 19 time units)

Answer: project duration = 19 time units; critical path = B - D - F - L