- 2070 Asar · 16 marks
CPM network, 10 activities (A=4 to J=9)
Short answer
Duration 35 days; critical path B-C-F-G-I-J. EST/EFT/LST/LFT/TF/FF: A 0,4,3,7,3,0; B 0,7,0,7,0,0; C 7,11,7,11,0,0; D 7,10,10,13,3,2; E 4,6,10,12,6,6; F 11,12,11,12,0,0; G 12,18,12,18,0,0; H 12,17,13,18,1,1; I 18,26,18,26,0,0; J 26,35,26,35,0,0.
Construct the CPM network for a project with the following activities. Find: (i) critical path, (ii) project completion time, (iii) EST, EFT, LST, LFT, total float, free float (FF), independent float (IdF) and interfering float (If).
| Activity | Days | Predecessor |
|---|---|---|
| A | 4 | - |
| B | 7 | - |
| C | 4 | A, B |
| D | 3 | B |
| E | 2 | A |
| F | 1 | C |
| G | 6 | E, F |
| H | 5 | D, F |
| I | 8 | G, H |
| J | 9 | I |
Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.
Network diagram (activity-on-arrow)
Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.
(1) --A(4)--> (2)
(1) --B(7)--> (3)
(2) - - dummy - -> (4)
(2) --E(2)--> (8)
(3) - - dummy - -> (4)
(3) --D(3)--> (7)
(4) --C(4)--> (5)
(5) --F(1)--> (6)
(6) - - dummy - -> (7)
(6) - - dummy - -> (8)
(7) --H(5)--> (9)
(8) --G(6)--> (9)
(9) --I(8)--> (10)
(10) --J(9)--> (11)
The network has 11 events and 4 dummy activities. Start event is (1) and the end event is (11).
Forward pass (EST and EFT)
Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.
- A: EST = 0; EFT = 0 + 4 = 4
- B: EST = 0; EFT = 0 + 7 = 7
- E: EST = EFT of A = 4; EFT = 4 + 2 = 6
- C: EST = max(A:4, B:7) = 7; EFT = 7 + 4 = 11
- D: EST = EFT of B = 7; EFT = 7 + 3 = 10
- F: EST = EFT of C = 11; EFT = 11 + 1 = 12
- G: EST = max(E:6, F:12) = 12; EFT = 12 + 6 = 18
- H: EST = max(D:10, F:12) = 12; EFT = 12 + 5 = 17
- I: EST = max(G:18, H:17) = 18; EFT = 18 + 8 = 26
- J: EST = EFT of I = 26; EFT = 26 + 9 = 35
Project duration = largest EFT = 35 days.
Backward pass (LFT and LST)
Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.
- J: LFT = project duration = 35; LST = 35 - 9 = 26
- I: LFT = LST of J = 26; LST = 26 - 8 = 18
- H: LFT = LST of I = 18; LST = 18 - 5 = 13
- G: LFT = LST of I = 18; LST = 18 - 6 = 12
- F: LFT = min(G:12, H:13) = 12; LST = 12 - 1 = 11
- D: LFT = LST of H = 13; LST = 13 - 3 = 10
- C: LFT = LST of F = 11; LST = 11 - 4 = 7
- E: LFT = LST of G = 12; LST = 12 - 2 = 10
- B: LFT = min(C:7, D:10) = 7; LST = 7 - 7 = 0
- A: LFT = min(C:7, E:10) = 7; LST = 7 - 4 = 3
Floats
- Total float
- Free float
- Interfering float
- Independent float
Result table
| Activity | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F |
|---|---|---|---|---|---|---|---|---|---|
| A | 4 | 0 | 4 | 3 | 7 | 3 | 0 | 3 | 0 |
| B | 7 | 0 | 7 | 0 | 7 | 0 | 0 | 0 | 0 |
| C | 4 | 7 | 11 | 7 | 11 | 0 | 0 | 0 | 0 |
| D | 3 | 7 | 10 | 10 | 13 | 3 | 2 | 1 | 2 |
| E | 2 | 4 | 6 | 10 | 12 | 6 | 6 | 0 | 3 |
| F | 1 | 11 | 12 | 11 | 12 | 0 | 0 | 0 | 0 |
| G | 6 | 12 | 18 | 12 | 18 | 0 | 0 | 0 | 0 |
| H | 5 | 12 | 17 | 13 | 18 | 1 | 1 | 0 | 0 |
| I | 8 | 18 | 26 | 18 | 26 | 0 | 0 | 0 | 0 |
| J | 9 | 26 | 35 | 26 | 35 | 0 | 0 | 0 | 0 |
Event times (TE from the forward pass, TL from the backward pass):
| Event | TE (earliest) | TL (latest) | Slack |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 4 | 7 | 3 |
| 3 | 7 | 7 | 0 |
| 4 | 7 | 7 | 0 |
| 5 | 11 | 11 | 0 |
| 6 | 12 | 12 | 0 |
| 7 | 12 | 13 | 1 |
| 8 | 12 | 12 | 0 |
| 9 | 18 | 18 | 0 |
| 10 | 26 | 26 | 0 |
| 11 | 35 | 35 | 0 |
Critical path and project duration
- Critical activities (TF = 0): B, C, F, G, I, J
- Critical path: B - C - F - G - I - J (= 7+4+1+6+8+9 = 35 days)
Answer: project duration = 35 days; critical path = B - C - F - G - I - J
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM network, 10 activities with successors · Project Engineering, chapter 3
- CPM network, building project (A to K) · Project Engineering, chapter 3
- CPM network, 12 activities (A=10 to L=8) · Project Engineering, chapter 3
- CPM network, 12 activities (A=8 to L=3) · Project Engineering, chapter 3
- CPM network, 10 activities (A=10 to J=4) · Project Engineering, chapter 3
- CPM network, 9 activities with successors · Project Engineering, chapter 3
- CPM schedule, critical path and float · Industrial Engineering and Management, chapter 3
- Relaxation time and mean free path · Electrical Engineering Material, chapter 2 · asked 4×
- PERT expected time and completion probability · Industrial Engineering and Management, chapter 3
- Free space path loss: 6 GHz, 10,500 km · Propagation and Antenna, chapter 5