CPM network, 10 activities (A=4 to J=9)

Short answer

Duration 35 days; critical path B-C-F-G-I-J. EST/EFT/LST/LFT/TF/FF: A 0,4,3,7,3,0; B 0,7,0,7,0,0; C 7,11,7,11,0,0; D 7,10,10,13,3,2; E 4,6,10,12,6,6; F 11,12,11,12,0,0; G 12,18,12,18,0,0; H 12,17,13,18,1,1; I 18,26,18,26,0,0; J 26,35,26,35,0,0.

Construct the CPM network for a project with the following activities. Find: (i) critical path, (ii) project completion time, (iii) EST, EFT, LST, LFT, total float, free float (FF), independent float (IdF) and interfering float (If).

ActivityDaysPredecessor
A4-
B7-
C4A, B
D3B
E2A
F1C
G6E, F
H5D, F
I8G, H
J9I

Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.

Network diagram (activity-on-arrow)

Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.

(1) --A(4)--> (2)
(1) --B(7)--> (3)
(2) - - dummy - -> (4)
(2) --E(2)--> (8)
(3) - - dummy - -> (4)
(3) --D(3)--> (7)
(4) --C(4)--> (5)
(5) --F(1)--> (6)
(6) - - dummy - -> (7)
(6) - - dummy - -> (8)
(7) --H(5)--> (9)
(8) --G(6)--> (9)
(9) --I(8)--> (10)
(10) --J(9)--> (11)

The network has 11 events and 4 dummy activities. Start event is (1) and the end event is (11).

Forward pass (EST and EFT)

Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.

  • A: EST = 0; EFT = 0 + 4 = 4
  • B: EST = 0; EFT = 0 + 7 = 7
  • E: EST = EFT of A = 4; EFT = 4 + 2 = 6
  • C: EST = max(A:4, B:7) = 7; EFT = 7 + 4 = 11
  • D: EST = EFT of B = 7; EFT = 7 + 3 = 10
  • F: EST = EFT of C = 11; EFT = 11 + 1 = 12
  • G: EST = max(E:6, F:12) = 12; EFT = 12 + 6 = 18
  • H: EST = max(D:10, F:12) = 12; EFT = 12 + 5 = 17
  • I: EST = max(G:18, H:17) = 18; EFT = 18 + 8 = 26
  • J: EST = EFT of I = 26; EFT = 26 + 9 = 35

Project duration = largest EFT = 35 days.

Backward pass (LFT and LST)

Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.

  • J: LFT = project duration = 35; LST = 35 - 9 = 26
  • I: LFT = LST of J = 26; LST = 26 - 8 = 18
  • H: LFT = LST of I = 18; LST = 18 - 5 = 13
  • G: LFT = LST of I = 18; LST = 18 - 6 = 12
  • F: LFT = min(G:12, H:13) = 12; LST = 12 - 1 = 11
  • D: LFT = LST of H = 13; LST = 13 - 3 = 10
  • C: LFT = LST of F = 11; LST = 11 - 4 = 7
  • E: LFT = LST of G = 12; LST = 12 - 2 = 10
  • B: LFT = min(C:7, D:10) = 7; LST = 7 - 7 = 0
  • A: LFT = min(C:7, E:10) = 7; LST = 7 - 4 = 3

Floats

  • Total float TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT
  • Free float FF=min⁡(EST of successors)−EFTFF = \min(\text{EST of successors}) - EFT
  • Interfering float IntF=TF−FFIntF = TF - FF
  • Independent float IndF=max⁡(0, min⁡(EST of successors)−max⁡(LFT of predecessors)−D)IndF = \max\left(0,\ \min(\text{EST of successors}) - \max(\text{LFT of predecessors}) - D\right)

Result table

ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A404373030
B707070000
C47117110000
D371010133212
E24610126603
F1111211120000
G6121812180000
H5121713181100
I8182618260000
J9263526350000

Event times (TE from the forward pass, TL from the backward pass):

EventTE (earliest)TL (latest)Slack
1000
2473
3770
4770
511110
612120
712131
812120
918180
1026260
1135350

Critical path and project duration

  • Critical activities (TF = 0): B, C, F, G, I, J
  • Critical path: B - C - F - G - I - J (= 7+4+1+6+8+9 = 35 days)

Answer: project duration = 35 days; critical path = B - C - F - G - I - J