- 2067 Asar (old course) · 4+12 marks
CPM network, 12 activities (A=10 to L=8)
Short answer
Forward pass computes EST/EFT from start to end; backward pass computes LFT/LST from end to start. Duration 48 days; critical path A-D-G-K-L. EST/EFT/LST/LFT/TF/FF: A 0,10,0,10,0,0; B 0,9,2,11,2,0; C 10,17,26,33,16,13; D 10,19,10,19,0,0; E 9,17,11,19,2,2; F 9,14,25,30,16,16; G 19,30,19,30,0,0; H 30,36,33,39,3,0; I 36,45,39,48,3,3; J 30,42,36,48,6,6; K 30,40,30,40,0,0; L 40,48,40,48,0,0.
Define forward and backward pass in the network analysis. Draw the network diagram and compute EST, EFT, LST, LFT, TF, FF, IF and interfering floats for each activity of the project having the precedence relationship shown below. Also find out the critical path.
| Activity | Duration (days) | Predecessor |
|---|---|---|
| A | 10 | - |
| B | 9 | - |
| C | 7 | A |
| D | 9 | A |
| E | 8 | B |
| F | 5 | B |
| G | 11 | D, E |
| H | 6 | C, G |
| I | 9 | H |
| J | 12 | G |
| K | 10 | G, F |
| L | 8 | K |
Forward pass and backward pass
- Forward pass: the calculation from the start event to the end event to find EST and EFT of each activity ( = largest EFT of the predecessors, ). The largest EFT is the project duration.
- Backward pass: the calculation from the end event back to the start event to find LFT and LST ( = smallest LST of the successors, ), taking the project duration as LFT of the last activity.
Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.
Network diagram (activity-on-arrow)
Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.
(1) --A(10)--> (2)
(1) --B(9)--> (3)
(2) --D(9)--> (4)
(2) --C(7)--> (6)
(3) --E(8)--> (4)
(3) --F(5)--> (7)
(4) --G(11)--> (5)
(5) - - dummy - -> (6)
(5) - - dummy - -> (7)
(5) --J(12)--> (10)
(6) --H(6)--> (8)
(7) --K(10)--> (9)
(8) --I(9)--> (10)
(9) --L(8)--> (10)
The network has 10 events and 2 dummy activities. Start event is (1) and the end event is (10).
Forward pass (EST and EFT)
Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.
- A: EST = 0; EFT = 0 + 10 = 10
- B: EST = 0; EFT = 0 + 9 = 9
- E: EST = EFT of B = 9; EFT = 9 + 8 = 17
- F: EST = EFT of B = 9; EFT = 9 + 5 = 14
- C: EST = EFT of A = 10; EFT = 10 + 7 = 17
- D: EST = EFT of A = 10; EFT = 10 + 9 = 19
- G: EST = max(D:19, E:17) = 19; EFT = 19 + 11 = 30
- H: EST = max(C:17, G:30) = 30; EFT = 30 + 6 = 36
- J: EST = EFT of G = 30; EFT = 30 + 12 = 42
- K: EST = max(G:30, F:14) = 30; EFT = 30 + 10 = 40
- I: EST = EFT of H = 36; EFT = 36 + 9 = 45
- L: EST = EFT of K = 40; EFT = 40 + 8 = 48
Project duration = largest EFT = 48 days.
Backward pass (LFT and LST)
Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.
- L: LFT = project duration = 48; LST = 48 - 8 = 40
- I: LFT = project duration = 48; LST = 48 - 9 = 39
- K: LFT = LST of L = 40; LST = 40 - 10 = 30
- J: LFT = project duration = 48; LST = 48 - 12 = 36
- H: LFT = LST of I = 39; LST = 39 - 6 = 33
- G: LFT = min(H:33, J:36, K:30) = 30; LST = 30 - 11 = 19
- D: LFT = LST of G = 19; LST = 19 - 9 = 10
- C: LFT = LST of H = 33; LST = 33 - 7 = 26
- F: LFT = LST of K = 30; LST = 30 - 5 = 25
- E: LFT = LST of G = 19; LST = 19 - 8 = 11
- B: LFT = min(E:11, F:25) = 11; LST = 11 - 9 = 2
- A: LFT = min(C:26, D:10) = 10; LST = 10 - 10 = 0
Floats
- Total float
- Free float
- Interfering float
- Independent float
Result table
| Activity | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F |
|---|---|---|---|---|---|---|---|---|---|
| A | 10 | 0 | 10 | 0 | 10 | 0 | 0 | 0 | 0 |
| B | 9 | 0 | 9 | 2 | 11 | 2 | 0 | 2 | 0 |
| C | 7 | 10 | 17 | 26 | 33 | 16 | 13 | 3 | 13 |
| D | 9 | 10 | 19 | 10 | 19 | 0 | 0 | 0 | 0 |
| E | 8 | 9 | 17 | 11 | 19 | 2 | 2 | 0 | 0 |
| F | 5 | 9 | 14 | 25 | 30 | 16 | 16 | 0 | 14 |
| G | 11 | 19 | 30 | 19 | 30 | 0 | 0 | 0 | 0 |
| H | 6 | 30 | 36 | 33 | 39 | 3 | 0 | 3 | 0 |
| I | 9 | 36 | 45 | 39 | 48 | 3 | 3 | 0 | 0 |
| J | 12 | 30 | 42 | 36 | 48 | 6 | 6 | 0 | 6 |
| K | 10 | 30 | 40 | 30 | 40 | 0 | 0 | 0 | 0 |
| L | 8 | 40 | 48 | 40 | 48 | 0 | 0 | 0 | 0 |
Event times (TE from the forward pass, TL from the backward pass):
| Event | TE (earliest) | TL (latest) | Slack |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 10 | 10 | 0 |
| 3 | 9 | 11 | 2 |
| 4 | 19 | 19 | 0 |
| 5 | 30 | 30 | 0 |
| 6 | 30 | 33 | 3 |
| 7 | 30 | 30 | 0 |
| 8 | 36 | 39 | 3 |
| 9 | 40 | 40 | 0 |
| 10 | 48 | 48 | 0 |
Critical path and project duration
- Critical activities (TF = 0): A, D, G, K, L
- Critical path: A - D - G - K - L (= 10+9+11+10+8 = 48 days)
Answer: project duration = 48 days; critical path = A - D - G - K - L
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM network, 10 activities (A=10 to J=4) · Project Engineering, chapter 3
- CPM network, 12 activities (A=8 to L=3) · Project Engineering, chapter 3
- CPM network, 10 activities (A=4 to J=9) · Project Engineering, chapter 3
- CPM precedence diagram, 9 activities · Project Engineering, chapter 3
- CPM network, building project (A to K) · Project Engineering, chapter 3
- CPM network, 10 activities with successors · Project Engineering, chapter 3