CPM network, 13 activities (A to M)

Short answer

Forward/backward pass gives project duration 25 days. Critical activities with zero total float: A, D, F, G, I, J, L. Critical paths: A-F-I-L and D-G-J-L (each 25 days).

Draw the CPM network diagram and compute EST, EFT, LST, LFT, TF, FF, Int.F and Ind.F from the information given below. Also compute the project duration and mark the critical path.

ActivityDuration (days)Predecessor
A9-
B8-
C7-
D9-
E5A
F4A
G3D
H6D
I7B, F
J8C, G
K4B, E, F
L5I, J
M3C, G, H

Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.

Network diagram (activity-on-arrow)

Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.

(1) --A(9)--> (2)
(1) --D(9)--> (3)
(1) --B(8)--> (4)
(1) --C(7)--> (5)
(2) --F(4)--> (4)
(2) --E(5)--> (6)
(3) --G(3)--> (5)
(3) --H(6)--> (8)
(4) - - dummy - -> (6)
(4) --I(7)--> (7)
(5) --J(8)--> (7)
(5) - - dummy - -> (8)
(6) --K(4)--> (9)
(7) --L(5)--> (9)
(8) --M(3)--> (9)

The network has 9 events and 2 dummy activities. Start event is (1) and the end event is (9).

Forward pass (EST and EFT)

Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.

  • A: EST = 0; EFT = 0 + 9 = 9
  • B: EST = 0; EFT = 0 + 8 = 8
  • C: EST = 0; EFT = 0 + 7 = 7
  • D: EST = 0; EFT = 0 + 9 = 9
  • E: EST = EFT of A = 9; EFT = 9 + 5 = 14
  • F: EST = EFT of A = 9; EFT = 9 + 4 = 13
  • G: EST = EFT of D = 9; EFT = 9 + 3 = 12
  • H: EST = EFT of D = 9; EFT = 9 + 6 = 15
  • J: EST = max(C:7, G:12) = 12; EFT = 12 + 8 = 20
  • I: EST = max(B:8, F:13) = 13; EFT = 13 + 7 = 20
  • K: EST = max(B:8, E:14, F:13) = 14; EFT = 14 + 4 = 18
  • M: EST = max(C:7, G:12, H:15) = 15; EFT = 15 + 3 = 18
  • L: EST = max(I:20, J:20) = 20; EFT = 20 + 5 = 25

Project duration = largest EFT = 25 days.

Backward pass (LFT and LST)

Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.

  • L: LFT = project duration = 25; LST = 25 - 5 = 20
  • M: LFT = project duration = 25; LST = 25 - 3 = 22
  • K: LFT = project duration = 25; LST = 25 - 4 = 21
  • I: LFT = LST of L = 20; LST = 20 - 7 = 13
  • J: LFT = LST of L = 20; LST = 20 - 8 = 12
  • H: LFT = LST of M = 22; LST = 22 - 6 = 16
  • G: LFT = min(J:12, M:22) = 12; LST = 12 - 3 = 9
  • F: LFT = min(I:13, K:21) = 13; LST = 13 - 4 = 9
  • E: LFT = LST of K = 21; LST = 21 - 5 = 16
  • D: LFT = min(G:9, H:16) = 9; LST = 9 - 9 = 0
  • C: LFT = min(J:12, M:22) = 12; LST = 12 - 7 = 5
  • B: LFT = min(I:13, K:21) = 13; LST = 13 - 8 = 5
  • A: LFT = min(E:16, F:9) = 9; LST = 9 - 9 = 0

Floats

  • Total float TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT
  • Free float FF=min⁡(EST of successors)−EFTFF = \min(\text{EST of successors}) - EFT
  • Interfering float IntF=TF−FFIntF = TF - FF
  • Independent float IndF=max⁡(0, min⁡(EST of successors)−max⁡(LFT of predecessors)−D)IndF = \max\left(0,\ \min(\text{EST of successors}) - \max(\text{LFT of predecessors}) - D\right)

Result table

ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A909090000
B8085135505
C7075125505
D909090000
E591416217070
F49139130000
G39129120000
H691516227070
I7132013200000
J8122012200000
K4141821257700
L5202520250000
M3151822257700

Event times (TE from the forward pass, TL from the backward pass):

EventTE (earliest)TL (latest)Slack
1000
2990
3990
413130
512120
614217
720200
815227
925250

Critical path and project duration

  • Critical activities (TF = 0): A, D, F, G, I, J, L
  • Critical path: A - F - I - L (= 9+4+7+5 = 25 days)
  • Critical path: D - G - J - L (= 9+3+8+5 = 25 days)
  • There are two critical paths of the same length, so a delay on either one delays the project.

Answer: project duration = 25 days; critical paths = A - F - I - L and D - G - J - L

✓ Answer checked by Claude Opus 5.5 (high effort)