CPM network, 13 activities (A to M)
Short answer
Forward/backward pass gives project duration 25 days. Critical activities with zero total float: A, D, F, G, I, J, L. Critical paths: A-F-I-L and D-G-J-L (each 25 days).
Draw the CPM network diagram and compute EST, EFT, LST, LFT, TF, FF, Int.F and Ind.F from the information given below. Also compute the project duration and mark the critical path.
| Activity | Duration (days) | Predecessor |
|---|---|---|
| A | 9 | - |
| B | 8 | - |
| C | 7 | - |
| D | 9 | - |
| E | 5 | A |
| F | 4 | A |
| G | 3 | D |
| H | 6 | D |
| I | 7 | B, F |
| J | 8 | C, G |
| K | 4 | B, E, F |
| L | 5 | I, J |
| M | 3 | C, G, H |
Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.
Network diagram (activity-on-arrow)
Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.
(1) --A(9)--> (2)
(1) --D(9)--> (3)
(1) --B(8)--> (4)
(1) --C(7)--> (5)
(2) --F(4)--> (4)
(2) --E(5)--> (6)
(3) --G(3)--> (5)
(3) --H(6)--> (8)
(4) - - dummy - -> (6)
(4) --I(7)--> (7)
(5) --J(8)--> (7)
(5) - - dummy - -> (8)
(6) --K(4)--> (9)
(7) --L(5)--> (9)
(8) --M(3)--> (9)
The network has 9 events and 2 dummy activities. Start event is (1) and the end event is (9).
Forward pass (EST and EFT)
Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.
- A: EST = 0; EFT = 0 + 9 = 9
- B: EST = 0; EFT = 0 + 8 = 8
- C: EST = 0; EFT = 0 + 7 = 7
- D: EST = 0; EFT = 0 + 9 = 9
- E: EST = EFT of A = 9; EFT = 9 + 5 = 14
- F: EST = EFT of A = 9; EFT = 9 + 4 = 13
- G: EST = EFT of D = 9; EFT = 9 + 3 = 12
- H: EST = EFT of D = 9; EFT = 9 + 6 = 15
- J: EST = max(C:7, G:12) = 12; EFT = 12 + 8 = 20
- I: EST = max(B:8, F:13) = 13; EFT = 13 + 7 = 20
- K: EST = max(B:8, E:14, F:13) = 14; EFT = 14 + 4 = 18
- M: EST = max(C:7, G:12, H:15) = 15; EFT = 15 + 3 = 18
- L: EST = max(I:20, J:20) = 20; EFT = 20 + 5 = 25
Project duration = largest EFT = 25 days.
Backward pass (LFT and LST)
Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.
- L: LFT = project duration = 25; LST = 25 - 5 = 20
- M: LFT = project duration = 25; LST = 25 - 3 = 22
- K: LFT = project duration = 25; LST = 25 - 4 = 21
- I: LFT = LST of L = 20; LST = 20 - 7 = 13
- J: LFT = LST of L = 20; LST = 20 - 8 = 12
- H: LFT = LST of M = 22; LST = 22 - 6 = 16
- G: LFT = min(J:12, M:22) = 12; LST = 12 - 3 = 9
- F: LFT = min(I:13, K:21) = 13; LST = 13 - 4 = 9
- E: LFT = LST of K = 21; LST = 21 - 5 = 16
- D: LFT = min(G:9, H:16) = 9; LST = 9 - 9 = 0
- C: LFT = min(J:12, M:22) = 12; LST = 12 - 7 = 5
- B: LFT = min(I:13, K:21) = 13; LST = 13 - 8 = 5
- A: LFT = min(E:16, F:9) = 9; LST = 9 - 9 = 0
Floats
- Total float
- Free float
- Interfering float
- Independent float
Result table
| Activity | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F |
|---|---|---|---|---|---|---|---|---|---|
| A | 9 | 0 | 9 | 0 | 9 | 0 | 0 | 0 | 0 |
| B | 8 | 0 | 8 | 5 | 13 | 5 | 5 | 0 | 5 |
| C | 7 | 0 | 7 | 5 | 12 | 5 | 5 | 0 | 5 |
| D | 9 | 0 | 9 | 0 | 9 | 0 | 0 | 0 | 0 |
| E | 5 | 9 | 14 | 16 | 21 | 7 | 0 | 7 | 0 |
| F | 4 | 9 | 13 | 9 | 13 | 0 | 0 | 0 | 0 |
| G | 3 | 9 | 12 | 9 | 12 | 0 | 0 | 0 | 0 |
| H | 6 | 9 | 15 | 16 | 22 | 7 | 0 | 7 | 0 |
| I | 7 | 13 | 20 | 13 | 20 | 0 | 0 | 0 | 0 |
| J | 8 | 12 | 20 | 12 | 20 | 0 | 0 | 0 | 0 |
| K | 4 | 14 | 18 | 21 | 25 | 7 | 7 | 0 | 0 |
| L | 5 | 20 | 25 | 20 | 25 | 0 | 0 | 0 | 0 |
| M | 3 | 15 | 18 | 22 | 25 | 7 | 7 | 0 | 0 |
Event times (TE from the forward pass, TL from the backward pass):
| Event | TE (earliest) | TL (latest) | Slack |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 9 | 9 | 0 |
| 3 | 9 | 9 | 0 |
| 4 | 13 | 13 | 0 |
| 5 | 12 | 12 | 0 |
| 6 | 14 | 21 | 7 |
| 7 | 20 | 20 | 0 |
| 8 | 15 | 22 | 7 |
| 9 | 25 | 25 | 0 |
Critical path and project duration
- Critical activities (TF = 0): A, D, F, G, I, J, L
- Critical path: A - F - I - L (= 9+4+7+5 = 25 days)
- Critical path: D - G - J - L (= 9+3+8+5 = 25 days)
- There are two critical paths of the same length, so a delay on either one delays the project.
Answer: project duration = 25 days; critical paths = A - F - I - L and D - G - J - L
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM network, 13 activities (A=2 to M=7) · Project Engineering, chapter 3 · asked 5×
- CPM network, 9 activities (A=3 to I=1) · Project Engineering, chapter 3 · asked 5×
- CPM network, 9 activities (A=5 to I=2) · Project Engineering, chapter 3 · asked 5×
- CPM network, road project (days) · Project Engineering, chapter 3
- CPM network, 12 activities (A=10 to L=8) · Project Engineering, chapter 3
- CPM network, 10 activities (A=4 to J=9) · Project Engineering, chapter 3
- CPM network, 10 activities with successors · Project Engineering, chapter 3
- CPM network, 10 activities (A=10 to J=4) · Project Engineering, chapter 3
- CPM network, building project (A to K) · Project Engineering, chapter 3
- CPM schedule, critical path and float · Industrial Engineering and Management, chapter 3