- 2079 Bhadra · 12 marks
CPM network, road project (days)
Short answer
Using AOA network with dummies, forward/backward pass gives project duration 19 days. Critical path A-D-G-J with critical activities A, D, G, J; all floats (TF, FF, Int.F, Ind.F) are tabulated, with zero total float on critical activities.
Draw a network diagram for a road project having information as in the table. Find out ES, EF, LS, LF, TF, FF, Int F, Ind F and then analyse the situation of the project stating the critical path, project completion time and critical activities.
| Activity | Duration (days) | Predecessor |
|---|---|---|
| A | 6 | - |
| B | 4 | - |
| C | 5 | - |
| D | 2 | A, B |
| E | 4 | C, D |
| F | 2 | D |
| G | 5 | D |
| H | 8 | D |
| I | 5 | G |
| J | 6 | E, G |
Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.
Network diagram (activity-on-arrow)
Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.
(1) --B(4)--> (2)
(1) --A(6)--> (3)
(1) --C(5)--> (7)
(2) - - dummy - -> (3)
(3) --D(2)--> (4)
(4) --G(5)--> (5)
(4) --H(8)--> (6)
(4) - - dummy - -> (7)
(4) --F(2)--> (9)
(5) - - dummy - -> (8)
(5) --I(5)--> (9)
(6) - - dummy - -> (9)
(7) --E(4)--> (8)
(8) --J(6)--> (9)
The network has 9 events and 4 dummy activities. Start event is (1) and the end event is (9).
Forward pass (EST and EFT)
Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.
- A: EST = 0; EFT = 0 + 6 = 6
- B: EST = 0; EFT = 0 + 4 = 4
- C: EST = 0; EFT = 0 + 5 = 5
- D: EST = max(A:6, B:4) = 6; EFT = 6 + 2 = 8
- E: EST = max(C:5, D:8) = 8; EFT = 8 + 4 = 12
- F: EST = EFT of D = 8; EFT = 8 + 2 = 10
- G: EST = EFT of D = 8; EFT = 8 + 5 = 13
- H: EST = EFT of D = 8; EFT = 8 + 8 = 16
- I: EST = EFT of G = 13; EFT = 13 + 5 = 18
- J: EST = max(E:12, G:13) = 13; EFT = 13 + 6 = 19
Project duration = largest EFT = 19 days.
Backward pass (LFT and LST)
Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.
- J: LFT = project duration = 19; LST = 19 - 6 = 13
- I: LFT = project duration = 19; LST = 19 - 5 = 14
- H: LFT = project duration = 19; LST = 19 - 8 = 11
- G: LFT = min(I:14, J:13) = 13; LST = 13 - 5 = 8
- F: LFT = project duration = 19; LST = 19 - 2 = 17
- E: LFT = LST of J = 13; LST = 13 - 4 = 9
- D: LFT = min(E:9, F:17, G:8, H:11) = 8; LST = 8 - 2 = 6
- C: LFT = LST of E = 9; LST = 9 - 5 = 4
- B: LFT = LST of D = 6; LST = 6 - 4 = 2
- A: LFT = LST of D = 6; LST = 6 - 6 = 0
Floats
- Total float
- Free float
- Interfering float
- Independent float
Result table
| Activity | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F |
|---|---|---|---|---|---|---|---|---|---|
| A | 6 | 0 | 6 | 0 | 6 | 0 | 0 | 0 | 0 |
| B | 4 | 0 | 4 | 2 | 6 | 2 | 2 | 0 | 2 |
| C | 5 | 0 | 5 | 4 | 9 | 4 | 3 | 1 | 3 |
| D | 2 | 6 | 8 | 6 | 8 | 0 | 0 | 0 | 0 |
| E | 4 | 8 | 12 | 9 | 13 | 1 | 1 | 0 | 0 |
| F | 2 | 8 | 10 | 17 | 19 | 9 | 9 | 0 | 9 |
| G | 5 | 8 | 13 | 8 | 13 | 0 | 0 | 0 | 0 |
| H | 8 | 8 | 16 | 11 | 19 | 3 | 3 | 0 | 3 |
| I | 5 | 13 | 18 | 14 | 19 | 1 | 1 | 0 | 1 |
| J | 6 | 13 | 19 | 13 | 19 | 0 | 0 | 0 | 0 |
Event times (TE from the forward pass, TL from the backward pass):
| Event | TE (earliest) | TL (latest) | Slack |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 4 | 6 | 2 |
| 3 | 6 | 6 | 0 |
| 4 | 8 | 8 | 0 |
| 5 | 13 | 13 | 0 |
| 6 | 16 | 19 | 3 |
| 7 | 8 | 9 | 1 |
| 8 | 13 | 13 | 0 |
| 9 | 19 | 19 | 0 |
Critical path and project duration
- Critical activities (TF = 0): A, D, G, J
- Critical path: A - D - G - J (= 6+2+5+6 = 19 days)
Answer: project duration = 19 days; critical path = A - D - G - J
Analysis of the project situation
- Project completion time = 19 days.
- Critical path = A - D - G - J (6 + 2 + 5 + 6 = 19 days); critical activities = A, D, G and J (zero float). A delay in any of them delays the road project by the same number of days.
- Non-critical activities: B, C, E, F, H and I. E and I have only 1 day of float, so they are near-critical and must be watched; F (9 days) and H (3 days) have the most float.
- Management should give priority in resources and supervision to the critical activities, and use the float of F, H, B and C to level labour and equipment.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM network, hydropower project (months) · Project Engineering, chapter 3
- CPM network, 12 activities (A=1 to L=4) · Project Engineering, chapter 3 · asked 2×
- CPM precedence diagram, 9 activities · Project Engineering, chapter 3
- CPM network, 13 activities (A to M) · Project Engineering, chapter 3 · asked 5×
- CPM network, 13 activities (A=2 to M=7) · Project Engineering, chapter 3 · asked 5×
- CPM network, 9 activities (A=3 to I=1) · Project Engineering, chapter 3 · asked 5×
- CPM schedule, critical path and float · Industrial Engineering and Management, chapter 3
- TCTO numerical: crashing critical path, Rs 30/day · Construction Management, chapter 2