CPM network, road project (days)

Short answer

Using AOA network with dummies, forward/backward pass gives project duration 19 days. Critical path A-D-G-J with critical activities A, D, G, J; all floats (TF, FF, Int.F, Ind.F) are tabulated, with zero total float on critical activities.

Draw a network diagram for a road project having information as in the table. Find out ES, EF, LS, LF, TF, FF, Int F, Ind F and then analyse the situation of the project stating the critical path, project completion time and critical activities.

ActivityDuration (days)Predecessor
A6-
B4-
C5-
D2A, B
E4C, D
F2D
G5D
H8D
I5G
J6E, G

Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.

Network diagram (activity-on-arrow)

Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.

(1) --B(4)--> (2)
(1) --A(6)--> (3)
(1) --C(5)--> (7)
(2) - - dummy - -> (3)
(3) --D(2)--> (4)
(4) --G(5)--> (5)
(4) --H(8)--> (6)
(4) - - dummy - -> (7)
(4) --F(2)--> (9)
(5) - - dummy - -> (8)
(5) --I(5)--> (9)
(6) - - dummy - -> (9)
(7) --E(4)--> (8)
(8) --J(6)--> (9)

The network has 9 events and 4 dummy activities. Start event is (1) and the end event is (9).

Forward pass (EST and EFT)

Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.

  • A: EST = 0; EFT = 0 + 6 = 6
  • B: EST = 0; EFT = 0 + 4 = 4
  • C: EST = 0; EFT = 0 + 5 = 5
  • D: EST = max(A:6, B:4) = 6; EFT = 6 + 2 = 8
  • E: EST = max(C:5, D:8) = 8; EFT = 8 + 4 = 12
  • F: EST = EFT of D = 8; EFT = 8 + 2 = 10
  • G: EST = EFT of D = 8; EFT = 8 + 5 = 13
  • H: EST = EFT of D = 8; EFT = 8 + 8 = 16
  • I: EST = EFT of G = 13; EFT = 13 + 5 = 18
  • J: EST = max(E:12, G:13) = 13; EFT = 13 + 6 = 19

Project duration = largest EFT = 19 days.

Backward pass (LFT and LST)

Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.

  • J: LFT = project duration = 19; LST = 19 - 6 = 13
  • I: LFT = project duration = 19; LST = 19 - 5 = 14
  • H: LFT = project duration = 19; LST = 19 - 8 = 11
  • G: LFT = min(I:14, J:13) = 13; LST = 13 - 5 = 8
  • F: LFT = project duration = 19; LST = 19 - 2 = 17
  • E: LFT = LST of J = 13; LST = 13 - 4 = 9
  • D: LFT = min(E:9, F:17, G:8, H:11) = 8; LST = 8 - 2 = 6
  • C: LFT = LST of E = 9; LST = 9 - 5 = 4
  • B: LFT = LST of D = 6; LST = 6 - 4 = 2
  • A: LFT = LST of D = 6; LST = 6 - 6 = 0

Floats

  • Total float TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT
  • Free float FF=min⁡(EST of successors)−EFTFF = \min(\text{EST of successors}) - EFT
  • Interfering float IntF=TF−FFIntF = TF - FF
  • Independent float IndF=max⁡(0, min⁡(EST of successors)−max⁡(LFT of predecessors)−D)IndF = \max\left(0,\ \min(\text{EST of successors}) - \max(\text{LFT of predecessors}) - D\right)

Result table

ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A606060000
B404262202
C505494313
D268680000
E48129131100
F281017199909
G58138130000
H881611193303
I5131814191101
J6131913190000

Event times (TE from the forward pass, TL from the backward pass):

EventTE (earliest)TL (latest)Slack
1000
2462
3660
4880
513130
616193
7891
813130
919190

Critical path and project duration

  • Critical activities (TF = 0): A, D, G, J
  • Critical path: A - D - G - J (= 6+2+5+6 = 19 days)

Answer: project duration = 19 days; critical path = A - D - G - J

Analysis of the project situation

  • Project completion time = 19 days.
  • Critical path = A - D - G - J (6 + 2 + 5 + 6 = 19 days); critical activities = A, D, G and J (zero float). A delay in any of them delays the road project by the same number of days.
  • Non-critical activities: B, C, E, F, H and I. E and I have only 1 day of float, so they are near-critical and must be watched; F (9 days) and H (3 days) have the most float.
  • Management should give priority in resources and supervision to the critical activities, and use the float of F, H, B and C to level labour and equipment.