- Asked 2/26
- 2081 Baisakh · 10 marks
- 2072 Chaitra · 2+5+6 marks
CPM network, 12 activities (A=1 to L=4)
Short answer
Network analysis gives project duration 21 weeks. Critical activities: B, D, H, I, K, L; path B-D-H-I-K-L.
Draw a network diagram from the following data. (i) Find critical path and critical activities. (ii) Find ES, EF, LS, LF, TF, FF, Ind.F and Int.F.
| Activity | Duration (weeks) | Predecessor |
|---|---|---|
| A | 1 | None |
| B | 3 | None |
| C | 2 | A |
| D | 4 | A, B |
| E | 3 | B |
| F | 5 | C, D |
| G | 1 | D |
| H | 2 | D |
| I | 6 | E, H |
| J | 3 | E, H |
| K | 2 | F, G, I |
| L | 4 | K, J |
Network diagram (activity on node)
Each node is: activity (duration). Arrows show precedence.
A(1) --+--> C(2) -----------------> F(5) --------+
| ^ |
+--> D(4) --+-----------------+ |
^ | v
B(3) --+----+ +--> G(1) -----------------> K(2) ---> L(4)
| | ^ ^
| +--> H(2) --+--> I(6) --------+ |
| | |
+--> E(3) --------------+--> J(3) ------------------+
Links: A and B start; C after A; D after A and B; E after B; F after C and D; G and H after D; I and J after E and H; K after F, G and I; L after K and J.
Forward and backward passes
= largest of predecessors; = smallest of successors. Project duration weeks. ; ; ; .
| Act | D | ES | EF | LS | LF | TF | FF | Int.F | Ind.F | Critical |
|---|---|---|---|---|---|---|---|---|---|---|
| A | 1 | 0 | 1 | 2 | 3 | 2 | 0 | 2 | 0 | No |
| B | 3 | 0 | 3 | 0 | 3 | 0 | 0 | 0 | 0 | Yes |
| C | 2 | 1 | 3 | 8 | 10 | 7 | 4 | 3 | 2 | No |
| D | 4 | 3 | 7 | 3 | 7 | 0 | 0 | 0 | 0 | Yes |
| E | 3 | 3 | 6 | 6 | 9 | 3 | 3 | 0 | 3 | No |
| F | 5 | 7 | 12 | 10 | 15 | 3 | 3 | 0 | 0 | No |
| G | 1 | 7 | 8 | 14 | 15 | 7 | 7 | 0 | 7 | No |
| H | 2 | 7 | 9 | 7 | 9 | 0 | 0 | 0 | 0 | Yes |
| I | 6 | 9 | 15 | 9 | 15 | 0 | 0 | 0 | 0 | Yes |
| J | 3 | 9 | 12 | 14 | 17 | 5 | 5 | 0 | 5 | No |
| K | 2 | 15 | 17 | 15 | 17 | 0 | 0 | 0 | 0 | Yes |
| L | 4 | 17 | 21 | 17 | 21 | 0 | 0 | 0 | 0 | Yes |
Sample check, activity C: ; ; ; ; ; ; ; (using ).
(i) Critical path
The activities with form the critical path B - D - H - I - K - L: weeks.
Answer: Critical activities: B, D, H, I, K, L. Project duration = 21 weeks.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM precedence diagram, 9 activities · Project Engineering, chapter 3
- CPM network, road project (days) · Project Engineering, chapter 3
- CPM network, 9 activities (A=3 to I=1) · Project Engineering, chapter 3 · asked 5×
- CPM network, 9 activities (A=5 to I=2) · Project Engineering, chapter 3 · asked 5×
- CPM network, 13 activities (A to M) · Project Engineering, chapter 3 · asked 5×
- CPM network, 13 activities (A=2 to M=7) · Project Engineering, chapter 3 · asked 5×
- CPM schedule, critical path and float · Industrial Engineering and Management, chapter 3
- TCTO numerical: crashing critical path, Rs 30/day · Construction Management, chapter 2