- 2069 Bhadra (old course) · 8 marks
TCTO numerical: crashing critical path, Rs 30/day
Short answer
Lowest cost schedule: crash 1-2 by 1 day (slope Rs 25/day) and 3-5 by 3 days (slope Rs 26.67/day). Resulting duration 16 days, total cost Rs1,165 (direct Rs685 + overhead Rs480). No other crashing is economical against Rs30/day indirect saving.
For the activities lying on the critical path of a network, the normal duration and the crash duration along with their respective direct cost are given in the table.
| Activity | Normal duration | Normal cost (Rs) | Crash duration | Crash costs (Rs) |
|---|---|---|---|---|
| 1-2 | 2 days | 50 | 1 day | 75 |
| 2-3 | 4 days | 160 | 3 days | 225 |
| 3-5 | 9 days | 270 | 6 days | 350 |
| 5-6 | 5 days | 100 | 4 days | 250 |
The overhead indirect cost is Rs.30/- per day. Crashing is possible for 1 day for each of the activities 1-2, 2-3, and 5-6 and 3 days for activity 3-5. Find the lowest cost schedule by crashing step by step assuming no fresh critical path is developed on crashing a project.
Given data and method
Indirect cost = 30 Rs/day. Time-cost trade-off (TCTO) crashes the activities on the critical path, one time-unit at a time, always choosing the cheapest cost slope, as long as the saving in indirect cost is more than the extra direct cost.
The four activities lie in series on the critical path (normal duration 2 + 4 + 9 + 5 = 20 days). Crashing limits: 1-2, 2-3 and 5-6 by 1 day each; 3-5 by 3 days. No new critical path appears.
| Activity | Normal dur | Crash dur | Normal cost | Crash cost | Slope |
|---|---|---|---|---|---|
| 1-2 | 2 | 1 | 50 | 75 | 25 |
| 2-3 | 4 | 3 | 160 | 225 | 65 |
| 3-5 | 9 | 6 | 270 | 350 | 26.67 |
| 5-6 | 5 | 4 | 100 | 250 | 150 |
Paths at normal duration
- 1-2 + 2-3 + 3-5 + 5-6 = 20 days
Critical activities (on the longest path or paths): 1-2, 2-3, 3-5, 5-6; normal duration = 20 days; normal direct cost = 580 Rs.
Crashing, step by step
| Step | Crash (by 1 unit) | Slope/cost | Duration | Direct | Indirect | Total |
|---|---|---|---|---|---|---|
| 0 | - | - | 20 | 580 | 600 | 1,180 |
| 1 | 1-2 | 25 | 19 | 605 | 570 | 1,175 |
| 2 | 3-5 | 26.67 | 18 | 631.67 | 540 | 1,171.67 |
| 3 | 3-5 | 26.67 | 17 | 658.33 | 510 | 1,168.33 |
| 4 | 3-5 | 26.67 | 16 | 685 | 480 | 1,165 |
| 5 | 2-3 | 65 | 15 | 750 | 450 | 1,200 |
| 6 | 5-6 | 150 | 14 | 900 | 420 | 1,320 |
Result
- Optimum (minimum-cost) schedule: duration 16 days, direct cost 685 + indirect 480 = 1,165 Rs.
- Activities crashed at the optimum: 1-2 by 1, 3-5 by 3. Durations: 1-2=1, 2-3=4, 3-5=6, 5-6=5.
- Minimum possible duration: 14 days, with total cost 1,320 Rs (direct 900 + indirect 420).
Answer: the lowest-cost schedule is obtained by crashing 1-2 by 1 day and 3-5 by 3 days: duration 16 days, total cost Rs 1,165 (direct Rs 685 + overhead Rs 480), against Rs 1,180 at the normal duration. Crashing 2-3 (Rs 65/day) or 5-6 (Rs 150/day) costs more than the Rs 30/day saved.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- TCTO numerical: seven activities, Rs 225/day · Construction Management, chapter 2
- TCTO numerical: seven activities, Rs 2000/day · Construction Management, chapter 2
- TCTO numerical: seven activities, Rs 1000/day · Construction Management, chapter 2
- TCTO numerical: least cost schedule, Rs 2000/week · Construction Management, chapter 2
- TCTO numerical with time-cost chart (five activities) · Construction Management, chapter 2
- TCTO numerical: lowest cost schedule, Rs 400/week · Construction Management, chapter 2
- CPM network, road project (days) · Project Engineering, chapter 3
- Dummy activity; use of critical path in CPM · Project Engineering, chapter 3
- Critical path and dummy activity significance · Project Engineering, chapter 3
- EVA; 10 days, 50 labour days at Rs 1000 · Project Engineering, chapter 4 · asked 2×