CPM network, hydropower project (months)
Short answer
CPM analysis gives project duration 17 months. Critical path is C-J, with only activities C and J having zero total float.
Draw a network diagram for a hydropower project having the information given below. Find out ES, EF, LS, LF, TF, FF, IntF, IndF and then analyse the situation of the project stating the critical path, project completion time and critical activities.
| Activity | Duration (month) | Predecessor |
|---|---|---|
| A | 3 | - |
| B | 5 | - |
| C | 8 | - |
| D | 4 | A |
| E | 7 | A |
| F | 2 | B |
| G | 1 | C |
| H | 7 | A |
| I | 4 | E, F, G |
| J | 9 | C |
Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.
Network diagram (activity-on-arrow)
Each activity is an arrow with its duration in brackets (months). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.
(1) --A(3)--> (2)
(1) --B(5)--> (3)
(1) --C(8)--> (4)
(2) --H(7)--> (5)
(2) --E(7)--> (6)
(2) --D(4)--> (7)
(3) --F(2)--> (6)
(4) --G(1)--> (6)
(4) --J(9)--> (7)
(5) - - dummy - -> (7)
(6) --I(4)--> (7)
The network has 7 events and 1 dummy activity. Start event is (1) and the end event is (7).
Forward pass (EST and EFT)
Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.
- A: EST = 0; EFT = 0 + 3 = 3
- B: EST = 0; EFT = 0 + 5 = 5
- C: EST = 0; EFT = 0 + 8 = 8
- D: EST = EFT of A = 3; EFT = 3 + 4 = 7
- E: EST = EFT of A = 3; EFT = 3 + 7 = 10
- H: EST = EFT of A = 3; EFT = 3 + 7 = 10
- F: EST = EFT of B = 5; EFT = 5 + 2 = 7
- G: EST = EFT of C = 8; EFT = 8 + 1 = 9
- J: EST = EFT of C = 8; EFT = 8 + 9 = 17
- I: EST = max(E:10, F:7, G:9) = 10; EFT = 10 + 4 = 14
Project duration = largest EFT = 17 months.
Backward pass (LFT and LST)
Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.
- I: LFT = project duration = 17; LST = 17 - 4 = 13
- J: LFT = project duration = 17; LST = 17 - 9 = 8
- G: LFT = LST of I = 13; LST = 13 - 1 = 12
- F: LFT = LST of I = 13; LST = 13 - 2 = 11
- H: LFT = project duration = 17; LST = 17 - 7 = 10
- E: LFT = LST of I = 13; LST = 13 - 7 = 6
- D: LFT = project duration = 17; LST = 17 - 4 = 13
- C: LFT = min(G:12, J:8) = 8; LST = 8 - 8 = 0
- B: LFT = LST of F = 11; LST = 11 - 5 = 6
- A: LFT = min(D:13, E:6, H:10) = 6; LST = 6 - 3 = 3
Floats
- Total float
- Free float
- Interfering float
- Independent float
Result table
| Activity | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F |
|---|---|---|---|---|---|---|---|---|---|
| A | 3 | 0 | 3 | 3 | 6 | 3 | 0 | 3 | 0 |
| B | 5 | 0 | 5 | 6 | 11 | 6 | 0 | 6 | 0 |
| C | 8 | 0 | 8 | 0 | 8 | 0 | 0 | 0 | 0 |
| D | 4 | 3 | 7 | 13 | 17 | 10 | 10 | 0 | 7 |
| E | 7 | 3 | 10 | 6 | 13 | 3 | 0 | 3 | 0 |
| F | 2 | 5 | 7 | 11 | 13 | 6 | 3 | 3 | 0 |
| G | 1 | 8 | 9 | 12 | 13 | 4 | 1 | 3 | 1 |
| H | 7 | 3 | 10 | 10 | 17 | 7 | 7 | 0 | 4 |
| I | 4 | 10 | 14 | 13 | 17 | 3 | 3 | 0 | 0 |
| J | 9 | 8 | 17 | 8 | 17 | 0 | 0 | 0 | 0 |
Event times (TE from the forward pass, TL from the backward pass):
| Event | TE (earliest) | TL (latest) | Slack |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 3 | 6 | 3 |
| 3 | 5 | 11 | 6 |
| 4 | 8 | 8 | 0 |
| 5 | 10 | 17 | 7 |
| 6 | 10 | 13 | 3 |
| 7 | 17 | 17 | 0 |
Critical path and project duration
- Critical activities (TF = 0): C, J
- Critical path: C - J (= 8+9 = 17 months)
Answer: project duration = 17 months; critical path = C - J
Analysis of the project situation
- Project completion time = 17 months.
- Critical path = C - J (8 + 9 = 17 months); critical activities = C and J (zero float).
- All other activities (A, B, D, E, F, G, H, I) are non-critical; they can be delayed by their floats (see table) without delaying the project, but a delay of C or J delays the hydropower project month for month.
- Management should give priority in resources, funds and supervision to C and J, and use the float of the other activities for levelling the resources.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM network, road project (days) · Project Engineering, chapter 3
- CPM precedence diagram, 9 activities · Project Engineering, chapter 3
- CPM network, 12 activities (A=1 to L=4) · Project Engineering, chapter 3 · asked 2×
- CPM network, building project (A to K) · Project Engineering, chapter 3
- CPM network, 10 activities with successors · Project Engineering, chapter 3
- CPM network, 9 activities (A=3 to I=1) · Project Engineering, chapter 3 · asked 5×
- CPM schedule, critical path and float · Industrial Engineering and Management, chapter 3