CPM network, hydropower project (months)

Short answer

CPM analysis gives project duration 17 months. Critical path is C-J, with only activities C and J having zero total float.

Draw a network diagram for a hydropower project having the information given below. Find out ES, EF, LS, LF, TF, FF, IntF, IndF and then analyse the situation of the project stating the critical path, project completion time and critical activities.

ActivityDuration (month)Predecessor
A3-
B5-
C8-
D4A
E7A
F2B
G1C
H7A
I4E, F, G
J9C

Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.

Network diagram (activity-on-arrow)

Each activity is an arrow with its duration in brackets (months). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.

(1) --A(3)--> (2)
(1) --B(5)--> (3)
(1) --C(8)--> (4)
(2) --H(7)--> (5)
(2) --E(7)--> (6)
(2) --D(4)--> (7)
(3) --F(2)--> (6)
(4) --G(1)--> (6)
(4) --J(9)--> (7)
(5) - - dummy - -> (7)
(6) --I(4)--> (7)

The network has 7 events and 1 dummy activity. Start event is (1) and the end event is (7).

Forward pass (EST and EFT)

Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.

  • A: EST = 0; EFT = 0 + 3 = 3
  • B: EST = 0; EFT = 0 + 5 = 5
  • C: EST = 0; EFT = 0 + 8 = 8
  • D: EST = EFT of A = 3; EFT = 3 + 4 = 7
  • E: EST = EFT of A = 3; EFT = 3 + 7 = 10
  • H: EST = EFT of A = 3; EFT = 3 + 7 = 10
  • F: EST = EFT of B = 5; EFT = 5 + 2 = 7
  • G: EST = EFT of C = 8; EFT = 8 + 1 = 9
  • J: EST = EFT of C = 8; EFT = 8 + 9 = 17
  • I: EST = max(E:10, F:7, G:9) = 10; EFT = 10 + 4 = 14

Project duration = largest EFT = 17 months.

Backward pass (LFT and LST)

Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.

  • I: LFT = project duration = 17; LST = 17 - 4 = 13
  • J: LFT = project duration = 17; LST = 17 - 9 = 8
  • G: LFT = LST of I = 13; LST = 13 - 1 = 12
  • F: LFT = LST of I = 13; LST = 13 - 2 = 11
  • H: LFT = project duration = 17; LST = 17 - 7 = 10
  • E: LFT = LST of I = 13; LST = 13 - 7 = 6
  • D: LFT = project duration = 17; LST = 17 - 4 = 13
  • C: LFT = min(G:12, J:8) = 8; LST = 8 - 8 = 0
  • B: LFT = LST of F = 11; LST = 11 - 5 = 6
  • A: LFT = min(D:13, E:6, H:10) = 6; LST = 6 - 3 = 3

Floats

  • Total float TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT
  • Free float FF=min⁡(EST of successors)−EFTFF = \min(\text{EST of successors}) - EFT
  • Interfering float IntF=TF−FFIntF = TF - FF
  • Independent float IndF=max⁡(0, min⁡(EST of successors)−max⁡(LFT of predecessors)−D)IndF = \max\left(0,\ \min(\text{EST of successors}) - \max(\text{LFT of predecessors}) - D\right)

Result table

ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A303363030
B5056116060
C808080000
D4371317101007
E73106133030
F25711136330
G18912134131
H731010177704
I4101413173300
J98178170000

Event times (TE from the forward pass, TL from the backward pass):

EventTE (earliest)TL (latest)Slack
1000
2363
35116
4880
510177
610133
717170

Critical path and project duration

  • Critical activities (TF = 0): C, J
  • Critical path: C - J (= 8+9 = 17 months)

Answer: project duration = 17 months; critical path = C - J

Analysis of the project situation

  • Project completion time = 17 months.
  • Critical path = C - J (8 + 9 = 17 months); critical activities = C and J (zero float).
  • All other activities (A, B, D, E, F, G, H, I) are non-critical; they can be delayed by their floats (see table) without delaying the project, but a delay of C or J delays the hydropower project month for month.
  • Management should give priority in resources, funds and supervision to C and J, and use the float of the other activities for levelling the resources.