- 2068 Baisakh (old course) · 16 marks
CPM network, 10 activities (A=5 to J=5)
Short answer
Duration 19 time units; critical path A-E-J. EST/EFT/LST/LFT/TF/FF: A 0,5,0,5,0,0; B 0,6,1,7,1,0; C 0,7,2,9,2,0; D 0,8,3,11,3,0; E 5,14,5,14,0,0; F 6,13,7,14,1,1; G 7,12,9,14,2,2; H 8,11,11,14,3,3; I 14,18,15,19,1,1; J 14,19,14,19,0,0.
For a project, the following durations are given. Find EST, EFT, LST, LFT, TF, FF. Show the critical path and find the duration.
| SN | Activity | Duration | Precedence | Successor |
|---|---|---|---|---|
| 1 | A | 5 | - | E |
| 2 | B | 6 | - | F |
| 3 | C | 7 | - | G |
| 4 | D | 8 | - | H |
| 5 | E | 9 | A | I, J |
| 6 | F | 7 | B | I, J |
| 7 | G | 5 | C | I, J |
| 8 | H | 3 | D | I, J |
| 9 | I | 4 | E, F, G, H | - |
| 10 | J | 5 | E, F, G, H | - |
Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.
Network diagram (activity-on-arrow)
Each activity is an arrow with its duration in brackets (time units). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.
(1) --A(5)--> (2)
(1) --B(6)--> (3)
(1) --C(7)--> (4)
(1) --D(8)--> (5)
(2) --E(9)--> (6)
(3) --F(7)--> (6)
(4) --G(5)--> (6)
(5) --H(3)--> (6)
(6) --J(5)--> (7)
(6) --I(4)--> (8)
(7) - - dummy - -> (8)
The network has 8 events and 1 dummy activity. Start event is (1) and the end event is (8).
Forward pass (EST and EFT)
Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.
- A: EST = 0; EFT = 0 + 5 = 5
- B: EST = 0; EFT = 0 + 6 = 6
- C: EST = 0; EFT = 0 + 7 = 7
- D: EST = 0; EFT = 0 + 8 = 8
- E: EST = EFT of A = 5; EFT = 5 + 9 = 14
- F: EST = EFT of B = 6; EFT = 6 + 7 = 13
- G: EST = EFT of C = 7; EFT = 7 + 5 = 12
- H: EST = EFT of D = 8; EFT = 8 + 3 = 11
- I: EST = max(E:14, F:13, G:12, H:11) = 14; EFT = 14 + 4 = 18
- J: EST = max(E:14, F:13, G:12, H:11) = 14; EFT = 14 + 5 = 19
Project duration = largest EFT = 19 time units.
Backward pass (LFT and LST)
Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.
- J: LFT = project duration = 19; LST = 19 - 5 = 14
- I: LFT = project duration = 19; LST = 19 - 4 = 15
- H: LFT = min(I:15, J:14) = 14; LST = 14 - 3 = 11
- G: LFT = min(I:15, J:14) = 14; LST = 14 - 5 = 9
- F: LFT = min(I:15, J:14) = 14; LST = 14 - 7 = 7
- E: LFT = min(I:15, J:14) = 14; LST = 14 - 9 = 5
- D: LFT = LST of H = 11; LST = 11 - 8 = 3
- C: LFT = LST of G = 9; LST = 9 - 7 = 2
- B: LFT = LST of F = 7; LST = 7 - 6 = 1
- A: LFT = LST of E = 5; LST = 5 - 5 = 0
Floats
- Total float
- Free float
- Interfering float
- Independent float
Result table
| Activity | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F |
|---|---|---|---|---|---|---|---|---|---|
| A | 5 | 0 | 5 | 0 | 5 | 0 | 0 | 0 | 0 |
| B | 6 | 0 | 6 | 1 | 7 | 1 | 0 | 1 | 0 |
| C | 7 | 0 | 7 | 2 | 9 | 2 | 0 | 2 | 0 |
| D | 8 | 0 | 8 | 3 | 11 | 3 | 0 | 3 | 0 |
| E | 9 | 5 | 14 | 5 | 14 | 0 | 0 | 0 | 0 |
| F | 7 | 6 | 13 | 7 | 14 | 1 | 1 | 0 | 0 |
| G | 5 | 7 | 12 | 9 | 14 | 2 | 2 | 0 | 0 |
| H | 3 | 8 | 11 | 11 | 14 | 3 | 3 | 0 | 0 |
| I | 4 | 14 | 18 | 15 | 19 | 1 | 1 | 0 | 1 |
| J | 5 | 14 | 19 | 14 | 19 | 0 | 0 | 0 | 0 |
Event times (TE from the forward pass, TL from the backward pass):
| Event | TE (earliest) | TL (latest) | Slack |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 5 | 5 | 0 |
| 3 | 6 | 7 | 1 |
| 4 | 7 | 9 | 2 |
| 5 | 8 | 11 | 3 |
| 6 | 14 | 14 | 0 |
| 7 | 19 | 19 | 0 |
| 8 | 19 | 19 | 0 |
Critical path and project duration
- Critical activities (TF = 0): A, E, J
- Critical path: A - E - J (= 5+9+5 = 19 time units)
Answer: project duration = 19 time units; critical path = A - E - J
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM network, 10 activities with successors · Project Engineering, chapter 3
- CPM network, 12 activities (A=10 to L=8) · Project Engineering, chapter 3
- CPM network, 10 activities (A=10 to J=4) · Project Engineering, chapter 3
- CPM network, 10 activities (A=4 to J=9) · Project Engineering, chapter 3
- CPM precedence diagram, 9 activities · Project Engineering, chapter 3
- CPM network, 9 activities (A=3 to I=1) · Project Engineering, chapter 3 · asked 5×
- CPM schedule, critical path and float · Industrial Engineering and Management, chapter 3
- TCTO numerical: crashing critical path, Rs 30/day · Construction Management, chapter 2