CPM network, 9 activities with successors

Short answer

Draw the activity-on-arrow network with one dummy, then compute EST/EFT forward and LST/LFT backward. Total, free, interfering and independent floats follow from the event times. Project duration is 13 days; critical path is A-D-G-I.

Draw the network. Find EST, EFT, LST, LFT, TF, FF and IF.

SNActivityDurationPredecessorSuccessor
1A5-B, C, D
2B4AE
3C2AF, H
4D3AG
5E2BH
6F1CI
7G3DI
8H1C, E-
9I2F, G-

IF is taken as independent float.

Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.

Network diagram (activity-on-arrow)

Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.

(1) --A(5)--> (2)
(2) --B(4)--> (3)
(2) --C(2)--> (4)
(2) --D(3)--> (5)
(3) --E(2)--> (6)
(4) - - dummy - -> (6)
(4) --F(1)--> (7)
(5) --G(3)--> (7)
(6) --H(1)--> (8)
(7) --I(2)--> (8)

The network has 8 events and 1 dummy activity. Start event is (1) and the end event is (8).

Forward pass (EST and EFT)

Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.

  • A: EST = 0; EFT = 0 + 5 = 5
  • B: EST = EFT of A = 5; EFT = 5 + 4 = 9
  • C: EST = EFT of A = 5; EFT = 5 + 2 = 7
  • D: EST = EFT of A = 5; EFT = 5 + 3 = 8
  • F: EST = EFT of C = 7; EFT = 7 + 1 = 8
  • G: EST = EFT of D = 8; EFT = 8 + 3 = 11
  • E: EST = EFT of B = 9; EFT = 9 + 2 = 11
  • H: EST = max(C:7, E:11) = 11; EFT = 11 + 1 = 12
  • I: EST = max(F:8, G:11) = 11; EFT = 11 + 2 = 13

Project duration = largest EFT = 13 days.

Backward pass (LFT and LST)

Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.

  • I: LFT = project duration = 13; LST = 13 - 2 = 11
  • H: LFT = project duration = 13; LST = 13 - 1 = 12
  • E: LFT = LST of H = 12; LST = 12 - 2 = 10
  • G: LFT = LST of I = 11; LST = 11 - 3 = 8
  • F: LFT = LST of I = 11; LST = 11 - 1 = 10
  • D: LFT = LST of G = 8; LST = 8 - 3 = 5
  • C: LFT = min(F:10, H:12) = 10; LST = 10 - 2 = 8
  • B: LFT = LST of E = 10; LST = 10 - 4 = 6
  • A: LFT = min(B:6, C:8, D:5) = 5; LST = 5 - 5 = 0

Floats

  • Total float TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT
  • Free float FF=min⁡(EST of successors)−EFTFF = \min(\text{EST of successors}) - EFT
  • Interfering float IntF=TF−FFIntF = TF - FF
  • Independent float IndF=max⁡(0, min⁡(EST of successors)−max⁡(LFT of predecessors)−D)IndF = \max\left(0,\ \min(\text{EST of successors}) - \max(\text{LFT of predecessors}) - D\right)

Result table

ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A505050000
B4596101010
C2578103030
D358580000
E291110121010
F17810113300
G38118110000
H1111212131100
I2111311130000

Event times (TE from the forward pass, TL from the backward pass):

EventTE (earliest)TL (latest)Slack
1000
2550
39101
47103
5880
611121
711110
813130

Critical path and project duration

  • Critical activities (TF = 0): A, D, G, I
  • Critical path: A - D - G - I (= 5+3+3+2 = 13 days)

Answer: project duration = 13 days; critical path = A - D - G - I