- Asked 2/26
- 2065 Shrawan (old course) · 11 marks
CPM network, 9 activities with successors
Short answer
Draw the activity-on-arrow network with one dummy, then compute EST/EFT forward and LST/LFT backward. Total, free, interfering and independent floats follow from the event times. Project duration is 13 days; critical path is A-D-G-I.
Draw the network. Find EST, EFT, LST, LFT, TF, FF and IF.
| SN | Activity | Duration | Predecessor | Successor |
|---|---|---|---|---|
| 1 | A | 5 | - | B, C, D |
| 2 | B | 4 | A | E |
| 3 | C | 2 | A | F, H |
| 4 | D | 3 | A | G |
| 5 | E | 2 | B | H |
| 6 | F | 1 | C | I |
| 7 | G | 3 | D | I |
| 8 | H | 1 | C, E | - |
| 9 | I | 2 | F, G | - |
IF is taken as independent float.
Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.
Network diagram (activity-on-arrow)
Each activity is an arrow with its duration in brackets (days). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.
(1) --A(5)--> (2)
(2) --B(4)--> (3)
(2) --C(2)--> (4)
(2) --D(3)--> (5)
(3) --E(2)--> (6)
(4) - - dummy - -> (6)
(4) --F(1)--> (7)
(5) --G(3)--> (7)
(6) --H(1)--> (8)
(7) --I(2)--> (8)
The network has 8 events and 1 dummy activity. Start event is (1) and the end event is (8).
Forward pass (EST and EFT)
Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.
- A: EST = 0; EFT = 0 + 5 = 5
- B: EST = EFT of A = 5; EFT = 5 + 4 = 9
- C: EST = EFT of A = 5; EFT = 5 + 2 = 7
- D: EST = EFT of A = 5; EFT = 5 + 3 = 8
- F: EST = EFT of C = 7; EFT = 7 + 1 = 8
- G: EST = EFT of D = 8; EFT = 8 + 3 = 11
- E: EST = EFT of B = 9; EFT = 9 + 2 = 11
- H: EST = max(C:7, E:11) = 11; EFT = 11 + 1 = 12
- I: EST = max(F:8, G:11) = 11; EFT = 11 + 2 = 13
Project duration = largest EFT = 13 days.
Backward pass (LFT and LST)
Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.
- I: LFT = project duration = 13; LST = 13 - 2 = 11
- H: LFT = project duration = 13; LST = 13 - 1 = 12
- E: LFT = LST of H = 12; LST = 12 - 2 = 10
- G: LFT = LST of I = 11; LST = 11 - 3 = 8
- F: LFT = LST of I = 11; LST = 11 - 1 = 10
- D: LFT = LST of G = 8; LST = 8 - 3 = 5
- C: LFT = min(F:10, H:12) = 10; LST = 10 - 2 = 8
- B: LFT = LST of E = 10; LST = 10 - 4 = 6
- A: LFT = min(B:6, C:8, D:5) = 5; LST = 5 - 5 = 0
Floats
- Total float
- Free float
- Interfering float
- Independent float
Result table
| Activity | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F |
|---|---|---|---|---|---|---|---|---|---|
| A | 5 | 0 | 5 | 0 | 5 | 0 | 0 | 0 | 0 |
| B | 4 | 5 | 9 | 6 | 10 | 1 | 0 | 1 | 0 |
| C | 2 | 5 | 7 | 8 | 10 | 3 | 0 | 3 | 0 |
| D | 3 | 5 | 8 | 5 | 8 | 0 | 0 | 0 | 0 |
| E | 2 | 9 | 11 | 10 | 12 | 1 | 0 | 1 | 0 |
| F | 1 | 7 | 8 | 10 | 11 | 3 | 3 | 0 | 0 |
| G | 3 | 8 | 11 | 8 | 11 | 0 | 0 | 0 | 0 |
| H | 1 | 11 | 12 | 12 | 13 | 1 | 1 | 0 | 0 |
| I | 2 | 11 | 13 | 11 | 13 | 0 | 0 | 0 | 0 |
Event times (TE from the forward pass, TL from the backward pass):
| Event | TE (earliest) | TL (latest) | Slack |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 5 | 5 | 0 |
| 3 | 9 | 10 | 1 |
| 4 | 7 | 10 | 3 |
| 5 | 8 | 8 | 0 |
| 6 | 11 | 12 | 1 |
| 7 | 11 | 11 | 0 |
| 8 | 13 | 13 | 0 |
Critical path and project duration
- Critical activities (TF = 0): A, D, G, I
- Critical path: A - D - G - I (= 5+3+3+2 = 13 days)
Answer: project duration = 13 days; critical path = A - D - G - I
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM network, 9 activities (old course) · Project Engineering, chapter 3 · asked 2×
- CPM network, 10 activities with successors · Project Engineering, chapter 3
- CPM network, 9 activities with successors · Project Engineering, chapter 3
- CPM network, 9 activities (A=3 to I=1) · Project Engineering, chapter 3 · asked 5×
- CPM network, 9 activities (A=5 to I=2) · Project Engineering, chapter 3 · asked 5×
- CPM network, 13 activities (A to M) · Project Engineering, chapter 3 · asked 5×
- CPM network, 13 activities (A=2 to M=7) · Project Engineering, chapter 3 · asked 5×