- Asked 2/26
- 2070 Chaitra (old course) · 4+6 marks
CPM network, 9 activities (old course)
Short answer
Duration 15 time units; critical path B-E-H-I. EST/EFT/LST/LFT/TF/FF: A 0,2,1,3,1,0; B 0,4,0,4,0,0; C 2,7,3,8,1,0; D 4,9,5,10,1,0; E 4,7,4,7,0,0; F 7,11,8,12,1,1; G 9,11,10,12,1,1; H 7,12,7,12,0,0; I 12,15,12,15,0,0.
Draw a CPM network. Find EST, EFT, LST, LFT, TF, FF.
| Activity | Duration | Predecessor |
|---|---|---|
| A | 2 | - |
| B | 4 | - |
| C | 5 | A |
| D | 5 | B |
| E | 3 | B |
| F | 4 | B, C |
| G | 2 | D |
| H | 5 | E |
| I | 3 | F, G, H |
Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.
Network diagram (activity-on-arrow)
Each activity is an arrow with its duration in brackets (time units). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.
(1) --A(2)--> (2)
(1) --B(4)--> (3)
(2) --C(5)--> (6)
(3) --D(5)--> (4)
(3) --E(3)--> (5)
(3) - - dummy - -> (6)
(4) --G(2)--> (7)
(5) --H(5)--> (7)
(6) --F(4)--> (7)
(7) --I(3)--> (8)
The network has 8 events and 1 dummy activity. Start event is (1) and the end event is (8).
Forward pass (EST and EFT)
Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.
- A: EST = 0; EFT = 0 + 2 = 2
- B: EST = 0; EFT = 0 + 4 = 4
- C: EST = EFT of A = 2; EFT = 2 + 5 = 7
- D: EST = EFT of B = 4; EFT = 4 + 5 = 9
- E: EST = EFT of B = 4; EFT = 4 + 3 = 7
- F: EST = max(B:4, C:7) = 7; EFT = 7 + 4 = 11
- H: EST = EFT of E = 7; EFT = 7 + 5 = 12
- G: EST = EFT of D = 9; EFT = 9 + 2 = 11
- I: EST = max(F:11, G:11, H:12) = 12; EFT = 12 + 3 = 15
Project duration = largest EFT = 15 time units.
Backward pass (LFT and LST)
Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.
- I: LFT = project duration = 15; LST = 15 - 3 = 12
- G: LFT = LST of I = 12; LST = 12 - 2 = 10
- H: LFT = LST of I = 12; LST = 12 - 5 = 7
- F: LFT = LST of I = 12; LST = 12 - 4 = 8
- E: LFT = LST of H = 7; LST = 7 - 3 = 4
- D: LFT = LST of G = 10; LST = 10 - 5 = 5
- C: LFT = LST of F = 8; LST = 8 - 5 = 3
- B: LFT = min(D:5, E:4, F:8) = 4; LST = 4 - 4 = 0
- A: LFT = LST of C = 3; LST = 3 - 2 = 1
Floats
- Total float
- Free float
- Interfering float
- Independent float
Result table
| Activity | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F |
|---|---|---|---|---|---|---|---|---|---|
| A | 2 | 0 | 2 | 1 | 3 | 1 | 0 | 1 | 0 |
| B | 4 | 0 | 4 | 0 | 4 | 0 | 0 | 0 | 0 |
| C | 5 | 2 | 7 | 3 | 8 | 1 | 0 | 1 | 0 |
| D | 5 | 4 | 9 | 5 | 10 | 1 | 0 | 1 | 0 |
| E | 3 | 4 | 7 | 4 | 7 | 0 | 0 | 0 | 0 |
| F | 4 | 7 | 11 | 8 | 12 | 1 | 1 | 0 | 0 |
| G | 2 | 9 | 11 | 10 | 12 | 1 | 1 | 0 | 0 |
| H | 5 | 7 | 12 | 7 | 12 | 0 | 0 | 0 | 0 |
| I | 3 | 12 | 15 | 12 | 15 | 0 | 0 | 0 | 0 |
Event times (TE from the forward pass, TL from the backward pass):
| Event | TE (earliest) | TL (latest) | Slack |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 2 | 3 | 1 |
| 3 | 4 | 4 | 0 |
| 4 | 9 | 10 | 1 |
| 5 | 7 | 7 | 0 |
| 6 | 7 | 8 | 1 |
| 7 | 12 | 12 | 0 |
| 8 | 15 | 15 | 0 |
Critical path and project duration
- Critical activities (TF = 0): B, E, H, I
- Critical path: B - E - H - I (= 4+3+5+3 = 15 time units)
Answer: project duration = 15 time units; critical path = B - E - H - I
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM network, 9 activities with successors · Project Engineering, chapter 3 · asked 2×
- CPM network, 9 activities (A=3 to I=1) · Project Engineering, chapter 3 · asked 5×
- CPM network, 9 activities (A=5 to I=2) · Project Engineering, chapter 3 · asked 5×
- CPM network, 13 activities (A to M) · Project Engineering, chapter 3 · asked 5×
- CPM network, 13 activities (A=2 to M=7) · Project Engineering, chapter 3 · asked 5×
- CPM network, 10 activities (A=4 to J=9) · Project Engineering, chapter 3
- CPM network, 10 activities with successors · Project Engineering, chapter 3