- 2067 Asar (old course) · 4+4 marks
Project family tree and goal criteria
Short answer
The project family tree is a hierarchy from mission or goal down to objectives, sub-projects and tasks, showing how every lower level supports the level above. Example: goal to improve rural livelihood through electricity, objective to supply 2,000 households in 3 years, sub-projects micro-hydro, distribution and connections, then specific tasks. Goal setting applies SMART criteria: Specific, Measurable, Achievable, Realistic/Relevant and Time-bound.
Explain the project family tree with a suitable example. Explain also the criteria of goal setting in any project.
Project family tree
The project family tree is a hierarchy that breaks the project down from its broad purpose to individual tasks. It shows how each lower level supports the level above.
Mission / Goal
|
+-- Objective 1
| +-- Programme / Sub-project 1.1
| | +-- Activity / Task 1.1.1
| | +-- Activity / Task 1.1.2
| +-- Sub-project 1.2
+-- Objective 2
+-- Sub-project 2.1
Example (rural electrification):
- Goal: improve rural livelihood through electricity.
- Objective: supply power to 2,000 households within 3 years.
- Sub-projects: micro-hydro plant; distribution line; household connection.
- Tasks: civil works, turbine installation, pole erection, wiring, training.
The tree makes the link between goals and work clear and leads to the WBS.
Criteria of goal setting
A goal is turned into objectives, and each objective is tested against the SMART criteria:
| Letter | Criterion | Meaning |
|---|---|---|
| S | Specific | Clear and unambiguous; says what, where and for whom |
| M | Measurable | Quantity, quality or cost can be checked |
| A | Achievable | Possible with available resources and technology |
| R | Realistic / Relevant | Matches the need and the organisation's capacity |
| T | Time-bound | Has a deadline or time frame |
Example
Poor objective: "Improve the road to the village."
SMART objective: "Construct a 12 km, 5.5 m wide black-topped road from X to Y, within 24 months, at a cost not exceeding NRs 40 crore, meeting Department of Roads standards."
- Specific: 12 km black-topped road from X to Y.
- Measurable: length, width, cost and standard are given.
- Achievable: the equipment, contractor and budget are available.
- Realistic: the village needs year-round access.
- Time-bound: 24 months.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Project goal setting and criteria (SMART) · Project Engineering, chapter 1 · asked 5×
- Goal vs objective; goal setting criteria · Project Engineering, chapter 1
- Project, characteristics and SMART goal setting · Project Engineering, chapter 1
- Life cycle phases and goal setting example · Project Engineering, chapter 1
- Goal versus objective of a project · Project Engineering, chapter 1