Short answer

Risk is an uncertain event measured by probability × impact. Types: pure/speculative, internal/external; sources include technical, financial, management, political, natural, resource. A project manager rectifies by following risk management steps: planning, identification, qualitative and quantitative analysis, response planning (avoid, transfer, mitigate, accept), and monitoring/control.

Define risk, its types and sources. As a project manager, how would you rectify the possible risks on your project? Give your answer considering all possible steps that fall under risk management.

Risk

Risk is an uncertain event or condition which, if it occurs, has a positive or negative effect on the project objectives (scope, time, cost, quality). It is measured by the probability of the event and the size of its impact: Risk = Probability x Impact.

Types of risk

  • By nature: pure risk (only loss is possible, e.g. fire, accident, flood) and speculative / business risk (gain or loss is possible, e.g. price change, market demand).
  • By source: internal risk (within the control of the project team: estimate, design, management, labour, equipment) and external risk (outside its control: government policy, weather, inflation, market, law).
  • By effect: negative risk (threat) and positive risk (opportunity).
  • By knowledge: known risks (identified, so responses can be planned and covered by a contingency reserve) and unknown risks (cannot be foreseen, so they are covered by a management reserve).

Main categories: technical, schedule, cost, financial, management, legal, political, environmental, safety and market risk.

Sources of risk

  1. Technical sources: incomplete or wrong design and drawings, inadequate survey and investigation, difficult geology, new technology, quality of materials and workmanship.
  2. Estimating and planning sources: unrealistic cost estimate and schedule, missing activities, over-optimistic productivity, poor risk allowance.
  3. Management sources: weak project manager, poor coordination between client, consultant and contractor, lack of skilled manpower, poor monitoring and decision making.
  4. Financial sources: shortage of funds, delay in release of budget or payment, inflation, interest and exchange rate changes.
  5. Contractual and legal sources: vague contract documents, variation orders, claims and disputes, change in laws, land acquisition and compensation problems.
  6. Political and social sources: change of government and policy, bandh and strikes, local community demands, corruption, security situation.
  7. Natural and environmental sources: flood, landslide, earthquake, heavy rain, climate change, environmental impact and clearance requirements.
  8. Resource and market sources: shortage or price rise of material, fuel, labour and equipment; supplier delay; transport problems (especially in remote areas of Nepal).
  9. Human and safety sources: accidents, labour disputes, health problems, errors and negligence.

Rectifying the risks as project manager

I would apply the full risk management process:

  1. Risk management planning: decide the approach, team, roles, budget, tools, risk categories, probability-impact scales and reporting. The output is the risk management plan.
  2. Risk identification: find the risks which may affect the project and document them in a risk register (brainstorming, checklists, Delphi, SWOT, interviews, experience).
  3. Qualitative risk analysis: rank the risks by probability and impact using a probability-impact matrix (below) to find the priority risks.
  4. Quantitative risk analysis: estimate the numerical effect of the main risks on cost and time (expected monetary value, decision tree, sensitivity analysis, Monte Carlo simulation).
  5. Risk response planning: select the strategy for each risk (avoid, transfer, mitigate/reduce, accept) and prepare contingency plans and reserves.
  6. Risk monitoring and control: track the identified risks, watch for new risks, check that the responses are working, update the risk register and report.
 Probability-impact matrix

 Impact ->   Low      Medium     High
 Prob.
 High       Medium     High      High
 Medium      Low      Medium     High
 Low         Low       Low      Medium

Practical actions: keep a risk register with owners, take insurance and performance guarantees (transfer), do extra investigation and early procurement (reduce), change the design or site for severe risks (avoid), keep a contingency reserve of 5 to 10% (accept), and hold monthly risk meetings to update the register.