Risk response planning strategies

Short answer

Risk response planning develops options and actions to reduce threats and enhance opportunities, assigning an owner and budget. It is important because it gives planned action before risks occur, reduces probability and impact, sets responsibility, and protects cost, schedule and quality. Strategies for negative risks are avoid, transfer, mitigate and accept.

What are the strategies for risk response planning? Why is risk response planning important in a project? What are the response strategies for negative risk?

Risk response planning

Risk response planning is the process of developing options and actions to improve opportunities and reduce threats to the project objectives, after the risks have been identified and analysed. It assigns an owner to each response and puts its cost and time into the plan.

Strategies for risk response planning

  • For negative risks (threats): avoid, transfer, mitigate (reduce), accept.
  • For positive risks (opportunities): exploit, share, enhance, accept.
  • Contingent response: a plan used only if a trigger event occurs.

Why it is important

  1. It gives a planned action before the risk happens, so the loss is smaller.
  2. It reduces the probability and impact of threats and increases opportunities.
  3. It sets responsibility (risk owner), time and budget (contingency reserve).
  4. It protects the cost, schedule and quality objectives.
  5. It helps decisions on insurance, contract type and reserves.
  6. It gives confidence to the client, lenders and the team.

Response strategies for negative risks

StrategyMeaningExample
AvoidChange the plan so the risk cannot occur or its impact is removedShift a bridge site away from an unstable slope; change to a proven design
TransferShift the impact and ownership of the risk to a third party (the risk is not removed)Insurance (CAR policy), performance bond, fixed-price contract, subcontract
Mitigate (reduce)Reduce the probability and/or the impact to an acceptable levelExtra soil tests, early procurement, quality control, training, safety measures
AcceptDo nothing now (passive) or keep a contingency reserve (active)A minor price change accepted with a 5% contingency

The best strategy is chosen by comparing the cost of the response with the expected loss. High-probability, high-impact risks are avoided or reduced; low-probability, high-impact risks are transferred (insurance); small risks are accepted.