- 2075 Chaitra · 3 marks
Why schedule is important in planning
Short answer
The schedule provides a time-table of activities, fixing the completion date and critical path. It enables resource planning, cash flow forecasting, progress monitoring, and forms the basis for contract claims and communication.
Why is schedule important in planning a project?
A schedule converts the plan into a time-table: it gives the start and finish time of every activity and the project completion date. It is important because:
- Fixes the completion date. The project duration and the critical activities are known.
- Co-ordinates work. Each party knows when its work starts and what must be finished before it.
- Resource planning. Labour, equipment and material are arranged in time from the schedule, avoiding idle time and shortage.
- Cash flow and finance. Payments, loan withdrawals and bills depend on when the work is done.
- Basis for control. Actual progress is compared with the schedule; delay is detected early and corrective action taken.
- Float is known. Non-critical activities can be shifted to level resources.
- Contract and claims. The approved schedule is used to assess delay, extension of time and liquidated damages.
- Communication. Gives clients and management a clear picture of progress.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Why risk analysis is important in planning · Project Engineering, chapter 5
- Project planning and its importance · Project Engineering, chapter 3 · asked 3×
- Short note: Planning software, MS Project · Project Engineering, chapter 3 · asked 2×
- Importance of WBS for project planning · Project Engineering, chapter 3
- Risk response planning strategies · Project Engineering, chapter 5 · asked 3×
- Plan, importance, systematic planning process · Project Engineering, chapter 3
- 300 MW reservoir project: planning to commissioning · Hydropower Engineering, chapter 2
- Project planning matrix (PPM) · ICT Project Management, chapter 7
- Importance of risk response planning · ICT Project Management, chapter 12
- TCTO numerical: lowest cost schedule, Rs 400/week · Construction Management, chapter 2