- 2070 Chaitra (old course) · 2+3+3 marks
Plan, importance, systematic planning process
Short answer
A plan is a predetermined course of action specifying what, how, who, and resources to meet objectives. Planning provides direction, reduces risk, optimizes resources, and serves as control baseline. The systematic process: define objectives, create WBS, sequence activities, estimate durations, schedule, assign responsibilities, and budget.
What is a plan? Why is planning important in a project? Write the systematic process of project planning.
What is a plan?
A plan is a pre-decided course of action that states what is to be done, how, by whom, when and with which resources, so that the project objectives are achieved within time, cost and quality limits. For a building project, the plan contains the scope, WBS, schedule, resource and cost estimates, and responsibilities.
Importance of project planning
- Gives direction. Everyone knows the objectives and the route to reach them.
- Reduces uncertainty and risk. Problems are foreseen and handled in advance.
- Uses resources economically. Manpower, machines and materials are arranged when needed, so idle time and waste fall.
- Basis for control. The plan is the baseline against which actual progress, cost and quality are compared.
- Improves coordination. Departments, contractors and suppliers work to one programme.
- Helps decisions and finance. Cash flow, loan drawdown and procurement are planned from it.
- Saves time and cost. Critical activities are identified and given attention.
- Motivation and accountability. Targets and responsibilities are clear.
Systematic process of project planning
- Define objectives and scope - fix what the project must deliver, with its time, cost and quality targets.
- Collect data and study constraints - site, market, law, funds, resources, weather.
- Prepare the Work Breakdown Structure (WBS) - divide the project into manageable work packages.
- List activities and fix their logical sequence - decide which activity precedes or follows which.
- Estimate duration, resources and cost of each activity (quantity x productivity, rates).
- Prepare the schedule - bar chart, milestone chart, CPM or PERT network; find the critical path.
- Assign responsibility - responsibility matrix, organisation structure, contract packages.
- Prepare resource, material, cash-flow and budget plans from the schedule.
- Plan quality, safety, risk and communication.
- Review, approve and issue the plan as the baseline; revise it when actual progress differs (feedback).
Objectives -> WBS -> Activities & logic
-> Estimates -> Schedule -> Resources
-> Budget -> Baseline plan -> Control
^ |
+------ feedback --------+
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Why schedule is important in planning · Project Engineering, chapter 3
- Why risk analysis is important in planning · Project Engineering, chapter 5
- Project planning and its importance · Project Engineering, chapter 3 · asked 3×
- Short note: Planning software, MS Project · Project Engineering, chapter 3 · asked 2×
- Importance of WBS for project planning · Project Engineering, chapter 3
- Step by step project appraisal process · Project Engineering, chapter 2
- Process of developing IS security plan · Information System, chapter 2
- Baseline management in project plan · ICT Project Management, chapter 7
- 300 MW reservoir project: planning to commissioning · Hydropower Engineering, chapter 2
- Project planning matrix (PPM) · ICT Project Management, chapter 7