WBS definition and importance

Short answer

Work Breakdown Structure (WBS) is a deliverable-oriented hierarchical decomposition of the total project scope into manageable work packages. It is crucial for defining the complete scope, creating schedules and budgets, assigning responsibilities, tracking progress, and facilitating communication. It helps ensure nothing is missed and supports cost, time, and risk management.

What is Work Breakdown Structure (WBS)? Discuss its importance (use) in project planning.

Work Breakdown Structure (WBS) is a hierarchical, deliverable-oriented decomposition of the total project scope into smaller manageable parts (work packages) down to the level at which cost, time and responsibility can be assigned.

Project
 +-- Major deliverable 1
 |     +-- Work package 1.1
 |     +-- Work package 1.2
 +-- Major deliverable 2
       +-- Work package 2.1

Importance (uses) in project planning

  • Defines the full scope, so nothing is missed (100% rule).
  • Makes a complex project manageable by dividing it.
  • Basis for schedule: activities are derived from work packages for bar chart, CPM and PERT.
  • Basis for cost estimate and budget at each level.
  • Assigns responsibility for each work package (responsibility matrix).
  • Helps resource planning and procurement.
  • Helps control: progress and cost are tracked package by package.
  • Improves communication and common understanding among team and client.
  • Helps risk identification at the work-package level.
  • Gives a coding system for reporting and accounting.