For kinematic wave routing, maximum time step from Courant condition Δt≤Δx/c. Normal depth y=0.684 m, velocity V=3.66 m/s, celerity c=5/3 V=6.096 m/s, so Δt_max=246 s (≈4.1 min).
A channel with a width of 40 m, bed slope 2% and Manning's carries a discharge of 100 m/s through a section. If is taken as 1500 meters, recommend the maximum time step for kinematic wave routing in this condition. Assume hydraulic radius equal to flow depth.
For an explicit kinematic wave scheme the time step is limited by the Courant condition:
where is the kinematic wave celerity.
Step 1: Normal depth
With and , Manning's equation gives
Step 2: Velocity and celerity
Since , .
Step 3: Maximum time step
Answer: the time step should not exceed about 246 s (about 4.1 minutes); a practical choice is slightly less, e.g. 4 minutes (240 s).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Non-linear kinematic wave discharge at 1 km · Computational Techniques in Civil Engineering, chapter 5
- Linear kinematic wave, 200 ft channel · Computational Techniques in Civil Engineering, chapter 5
- Linear kinematic wave, 30 m channel · Computational Techniques in Civil Engineering, chapter 5
- Non-linear kinematic wave, trapezoidal river · Computational Techniques in Civil Engineering, chapter 5
- First-order kinematic wave, flood peak at community · Computational Techniques in Civil Engineering, chapter 5
- Second-order scheme, linear kinematic wave · Computational Techniques in Civil Engineering, chapter 5
- Economical rectangular condition and trapezoidal bed slope · Hydro Power, chapter 1
- Direct step, 16 m wide channel, 40 m³/s · Hydraulics, chapter 8
- Lacey and Kennedy bed width, Q 40 · Irrigation and Drainage Engineering, chapter 4
- Slope break: jump depth and jump length by step · Hydraulics, chapter 9
All Computational Techniques in Civil Engineering chapter 5 questions →