- 2077 Chaitra · 2+4+2 marks
Inventory planning and ABC classes from data
Short answer
Inventory for repetitive items is planned by ordering EOQ when stock hits reorder level. The ABC classification: A items are steel rebar and tiles (totaling 74% value), B is cement, rest are C. This directs management effort to high-value items, reduces holding costs, and prevents critical shortages.
How can inventory of construction materials be planned for repeatedly used items? Explain with suitable diagram. Consider a construction site acquired different materials given below, based on the data classify the materials in A, B and C classes. What are the significances of this classification?
| Materials | Quantity | Unit | Rate per unit |
|---|---|---|---|
| steel re-bar | 15 | ton | 110000 |
| cement | 600 | bag | 750 |
| tiles | 1500 | sqft | 350 |
| brick | 9000 | no | 12 |
| marbles | 450 | sqft | 250 |
| aggregate | 50 | cum | 1400 |
| sand | 25 | cum | 1200 |
Inventory planning for repetitive (regularly used) materials
Materials such as cement, sand and bricks are used continuously, so their stock is kept between a maximum and a minimum level by ordering a fixed economic quantity (EOQ) whenever the stock falls to the re-order level.
Stock
^
Max|\ |\ |\ maximum level
| \ | \ | \
| \ | \ | \
ROL|...\...|...\...|...\..... re-order level (order placed)
| \ | \ | \
| \ | \ | \
Min|......\|......\|......\.. minimum (safety) stock
| <-->| <-->|
| LT | LT |
+-----------------------------> Time
LT = lead time. Stock falls with use; the order placed at
ROL arrives after LT and raises the stock by EOQ (vertical line).
Quantities:
- Reorder level (ROL) = daily consumption x lead time + safety stock
- Maximum level = ROL + EOQ - (minimum consumption x minimum lead time)
- Minimum (safety) level = ROL - (normal consumption x normal lead time)
- Average stock = Minimum level + EOQ/2
- EOQ = , where is annual demand, ordering cost per order and carrying cost per unit per year.
Process: estimate consumption from the work schedule, fix the lead time and safety stock, compute the EOQ, place an order at the ROL, check the material on receipt, and review the levels when the rate of work changes.
ABC classification of the given materials
Value = quantity x rate.
| Material | Value (Rs) | % of total | Cumulative % | Class |
|---|---|---|---|---|
| Steel re-bar | 16,50,000 | 56.02 | 56.02 | A |
| Tiles | 5,25,000 | 17.82 | 73.84 | A |
| Cement | 4,50,000 | 15.28 | 89.12 | B |
| Marbles | 1,12,500 | 3.82 | 92.94 | C |
| Brick | 1,08,000 | 3.67 | 96.60 | C |
| Aggregate | 70,000 | 2.38 | 98.98 | C |
| Sand | 30,000 | 1.02 | 100.00 | C |
| Total | 29,45,500 | 100 |
Class limits are taken as A up to about 75%, B up to about 90%, and C the rest. Thus A: steel re-bar, tiles; B: cement; C: marbles, brick, aggregate, sand.
Significance of classification
- Management attention and control are concentrated on the few A items, which carry about 74% of the value.
- It reduces inventory carrying cost: A items are ordered often in small lots, C items in bulk.
- It helps in selecting suppliers and in negotiating for A items.
- It reduces the chance of a shortage of critical items.
- It saves time and effort in record keeping and purchasing.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- ABC classification and inventory planning · Construction Management, chapter 3 · asked 2×
- Planned maintenance, planning and scheduling · Construction Management, chapter 9 · asked 2×
- ABC graph and value engineering of materials · Construction Management, chapter 3
- ABC classification and material management · Construction Management, chapter 3 · asked 2×
- Material classification, EOQ, GiT and re-order level · Construction Management, chapter 3
- Job layout and site planning factors · Construction Management, chapter 6 · asked 2×
- INVENTORY file of items · Computer Programming, chapter 10
- ABC analysis from annual consumption data · Industrial Engineering and Management, chapter 4
- Salient pole generator phasor diagram in per unit · Electric Machines II, chapter 1
- Per unit circuit of three-generator system, 30 MVA base · Power System Analysis I, chapter 3