Time cost trade-off concept with example
Short answer
Time-cost trade-off balances direct and indirect costs to find the minimum total cost. Crashing critical activities with the lowest cost slope first, while the slope is less than indirect cost saved per day. For the example, crashing B (Rs 300/day) then A (Rs 500/day) yields an optimum duration of 10 days and total cost of Rs 9,300.
Explain the concept of time cost trade-off (and its use in determining the duration of a project) with an example.
Time-cost trade-off (TCTO) is the technique of shortening a project's duration by crashing (speeding up) selected activities while watching the total cost. Direct cost (labour, materials, machines) rises as an activity is crashed, while indirect cost (overheads, supervision, penalties) falls as the project becomes shorter. The sum of the two is lowest at an optimum duration.
Cost
^
|T T T = total cost
| T T D = direct cost
| T T I = indirect cost
| T T
| T * T * = minimum total cost
|D
| D I
| D I
| D I
| D I
| I D
| I D
| I D D
+-------------------------------------> Duration
crash optimum normal
Use in determining project duration
- Cost slope of an activity = (crash cost - normal cost) / (normal time - crash time).
- Only critical activities are crashed, cheapest slope first, until the slope exceeds the indirect cost saved per unit time or the crash limit is reached.
- The duration with the minimum total cost is the optimum duration; the shortest feasible duration is the crash duration.
Example
Two activities in series: A (normal 6 days, Rs 3,000; crash 4 days, Rs 4,000) and B (normal 5 days, Rs 2,000; crash 4 days, Rs 2,300). Indirect cost Rs 400/day.
Slope of A = (4000 - 3000)/(6 - 4) = Rs 500/day; slope of B = (2300 - 2000)/(5 - 4) = Rs 300/day.
| Step | Crash (by 1 unit) | Slope/cost | Duration | Direct | Indirect | Total |
|---|---|---|---|---|---|---|
| 0 | - | - | 11 | 5,000 | 4,400 | 9,400 |
| 1 | B | 300 | 10 | 5,300 | 4,000 | 9,300 |
| 2 | A | 500 | 9 | 5,800 | 3,600 | 9,400 |
| 3 | A | 500 | 8 | 6,300 | 3,200 | 9,500 |
Crashing B costs Rs 300 and saves Rs 400, so it is worthwhile. Crashing A (Rs 500) costs more than the Rs 400 saved. The optimum duration is 10 days with a total cost of Rs 9,300 (against Rs 9,400 at the normal duration).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Time cost trade-off and steps in planning · Construction Management, chapter 2
- TCTO, crashing and reducing project duration · Construction Management, chapter 2
- TCTO numerical with time-cost chart (five activities) · Construction Management, chapter 2
- Concept of project finance · Project Engineering, chapter 6
- Cut-off and time-current characteristics of fuse · Switchgear and Protection, chapter 3
- Prospective current, cut-off current, time delay fuse · Switchgear and Protection, chapter 3
- Project proposal; cost benefit analysis for road · Project Engineering, chapter 2