- 2073 Magh · 4 marks
Tie-up between two national utilities
Short answer
A tie-up between national utilities is an agreement and cross-border interconnection for power exchange and reserve sharing. Nepal-India example: 400 kV Dhalkebar-Muzaffarpur line, Power Trade Agreement, export via IEX, long-term target 10,000 MW. Benefits include wet-season export, dry-season import, shared reserve, market for hydro; issues include approvals, pricing, transmission capacity.
Discuss the scenario of tie up between two national level electric utilities.
A tie-up between two national utilities is an agreement and physical interconnection (cross-border transmission lines) that allows two countries' electricity utilities to exchange power, share reserve and trade energy. The Nepal (NEA) – India tie-up is the main example for Nepal.
Present scenario (Nepal–India)
- Many 11, 33 and 132 kV cross-border links exist, plus the Dhalkebar–Muzaffarpur 400 kV line (first charged at 220 kV, operated at 400 kV since 2020).
- New 400 kV links (Butwal–Gorakhpur, Dhalkebar–Sitamarhi, Inaruwa–Purnea) are under construction or planned.
- The Power Exchange Agreement (since 1971) and the Power Trade Agreement (2014) allow trade; Nepal has sold power through the Indian Energy Exchange since 2021.
- A long-term agreement (2024) targets 10,000 MW of export to India within ten years; tripartite trade to Bangladesh (40 MW) started in 2024.
Benefits
- Nepal sells its wet-season surplus and imports in the dry season.
- Shared reserve and better reliability for both.
- India gets clean hydropower for its renewable targets.
- Investment in Nepal's large hydro becomes viable with an assured market.
Issues
Approval needed from Indian authorities for each project, pricing, transmission capacity, grid code compatibility and political dependence.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Nepal generation and consumption trends · Power Plant Design, chapter 1
- Hydropower versus solar PV in Nepal · Power Plant Design, chapter 1
- Power system expansion planning for a utility · Power Plant Design, chapter 2
- Power system planning and grid integration · Power Plant Design, chapter 2
- Unit generator-transformer schemes · Power Plant Design, chapter 4 · asked 3×
- Wind energy conversion options and characteristics · Power Plant Design, chapter 1
- Global and national energy scenario · Energy Environment and Society, chapter 2
- Surge tank area, up/downsurge, invert level · Hydropower Engineering, chapter 6
- Built-up column, two channels toe-to-toe, 1500 kN · Design of Steel and Timber Structure, chapter 6
- Bridge compression member, 1200 kN, tie bar lacing · Design of Steel and Timber Structure, chapter 6