- 2081 Shrawan · 4 marks
Power system security and reserve requirement
Short answer
Power system security is the ability to withstand sudden disturbances and continue supplying load, usually meeting the N-1 criterion. Reserve is capacity above peak demand, comprising spinning, non-spinning, and planning reserves; the reserve margin is typically 15-25%.
What is power system security? Also describe about reserve requirement in a power system.
Power system security is the ability of the power system to withstand sudden disturbances such as loss of a generator, line or transformer, or a short circuit, and continue supplying load without violating voltage, frequency and loading limits. The usual criterion is N-1: the system must remain secure after any single outage.
Reserve requirement
Reserve is the generating capacity kept above the forecast peak demand.
- Spinning reserve: unloaded capacity of synchronised units; at least equal to the largest running unit, for sudden outages and frequency control.
- Non-spinning (standby) reserve: quick-start units (hydro, gas turbine, diesel) that can come on line within 10–30 minutes.
- Planning (cold) reserve: extra installed capacity for maintenance, forced outages, load growth and dry-year hydrology.
Reserve margin
Typical values are 15–25%. It is fixed either deterministically (largest unit, fixed %) or probabilistically (LOLP/LOLE target). Interconnection with neighbouring grids reduces the reserve requirement.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Concept of power system security · Power Plant Design, chapter 2 · asked 3×
- Power system security assessment · Power Plant Design, chapter 2
- Accurate load forecasting and system security · Power Plant Design, chapter 2
- Spinning reserve versus reserve power · Power Plant Design, chapter 2
- Define reserve power · Power Plant Design, chapter 2
- Regional interconnection and reserve bottling · Power Plant Design, chapter 2
- Requirement elicitation and system behavior · Object Oriented Analysis and Design, chapter 2
- Fire fighting system in power station · Power Plant Equipment, chapter 4 · asked 5×
- BPT requirement; residual head at stand post · Water Supply Engineering, chapter 9
- SCADA in a power system · Power Plant Equipment, chapter 4 · asked 4×