Tidal power generation and output: 3 km × 3 km
Short answer
Tides create a head between sea and basin; water flows through low-head bulbs turbines during ebb, driving generators. Energy per tide is 0.5 rho g A h^2. With area 9e6 m^2, range 10 m, density 1025 kg/m^3, two tides daily, and 30% efficiency, average power output is about 31.4 MW.
How electric power is generated from a Tidal Power Project? Estimate the power output from a tidal project that has tidal range of approximately 10 m. The surface area of tidal harnessing plant is 3 km × 3 km. Consider that there are two high tides every day. Assume power conversion efficiency as 30%. Density of sea water is about 1025 kg/m³.
Generation of electric power from a tidal project
Tides are the periodic rise and fall of sea level caused by the moon and sun's gravity; most coasts have two high and two low tides a day. A tidal power plant uses the head between the sea and a basin.
SEA BARRAGE BASIN
high tide ~~~~~ +-----------+
| sluice | ~~~~~ stored
low tide ~~~~ | turbine | water
+-----------+
<--- flow through turbine on ebb (basin -> sea)
- A barrage (dam) is built across a bay or estuary, with sluice gates and low-head bulb (Kaplan type) turbines.
- Filling: at rising tide the gates open and the basin fills.
- Holding: at high tide the gates close and water is held.
- Generation (ebb): when the sea falls, a head forms; water flows from basin to sea through the turbines, driving generators.
- In double-effect schemes, power is also generated on the flood tide (sea to basin).
Examples: La Rance (France, 240 MW), Sihwa (South Korea, 254 MW).
Power estimation
Energy of water in the basin per tide (centre of gravity at ):
Given: m², m, kg/m³, m/s², 2 tides per day, .
Answer: Average power output MW (about 275 GWh per year).
Assumption: one basin emptying per high tide, averaged over 24 hours.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Tidal power output: 3 km × 5.5 km barrage · Power Plant Design, chapter 1
- Tidal versus wind power plant · Power Plant Design, chapter 1
- Design: 230 m head plant, 20 km line · Power Plant Design, chapter 4 · asked 14×
- Design: 230 m head plant, 55 km line · Power Plant Design, chapter 4 · asked 12×
- Design: 250 m head plant, 35 km line · Power Plant Design, chapter 4 · asked 12×
- Design: 230 m head plant, 45 km line · Power Plant Design, chapter 4 · asked 12×
- Pondage surface area and weekly output · Hydropower Engineering, chapter 3
- Slope-area discharge, 10 km reach · Engineering Hydrology, chapter 4
- Slope-area discharge, 10 km reach, 104.77 m · Engineering Hydrology, chapter 4
- Every RE has NFA; ε-NFA for bb(a∪b)*ab · Theory of Computation, chapter 2