Time-area method with histogram, drawbacks
Short answer
Used to compute direct runoff hydrograph from excess rainfall for ungauged catchments (basis of Clark IUH). Isochrones divide catchment into strips Aᵢ; discharge Qₙ = (2.78/Δt) Σ rᵢ A₍ₙ₋ᵢ₊₁₎. Drawbacks: neglects storage, assumes constant velocity and uniform rainfall, yields overly sharp peaks.
For what purpose is the time area method used? Explain the time area method using a time area histogram of a catchment and a set of effective rainfall hydrograph over it. Comment on its drawbacks.
Purpose
The time-area method is used to compute the direct runoff hydrograph at a catchment outlet for a known effective (excess) rainfall hyetograph, especially for ungauged catchments (it is also the base of Clark's IUH).
The method
Draw isochrones (lines of equal travel time to the outlet) at interval . Let the areas between them be (the last at ). The time-area histogram:
Area (km2)
A4 | ____
A3 | ___| |
A2 | __| | |___
A1 || | | | |
+-+--+---+----+---+--> t
0 Δt 2Δt 3Δt 4Δt
Let the effective rainfall be in blocks (cm) of duration .
- Rain falling on reaches the outlet in the first interval, on in the second interval, etc.
- The discharge at the end of each interval is the sum of the flows from all blocks:
So:
- and so on, until all rainfall blocks and strips have been used.
Here is in km², in cm and in h. Plotting against gives the direct runoff hydrograph (base flow is added to get the total flood).
Drawbacks
- It considers only translation and ignores storage in channels and on the catchment, so the computed peak is too high and the hydrograph too sharp.
- Constant velocity is assumed, so travel times do not change with discharge or rainfall intensity.
- Drawing isochrones accurately needs a good topographic map and field knowledge.
- Rainfall and losses are taken to be uniform over each strip.
✓ Answer checked by Claude Sonnet 5.5
Related questions
- Methods of average rainfall over catchment · Engineering Hydrology, chapter 2 · asked 3×
- Rainfall, lag time and time of concentration from hydrograph · Engineering Hydrology, chapter 5
- Time area method for runoff hydrograph · Engineering Hydrology, chapter 7
- Runoff and effective rainfall, 4-hr storm, 80 km2 · Engineering Hydrology, chapter 3 · asked 2×
- Thiessen polygon mean rainfall, pentagon catchment · Engineering Hydrology, chapter 2
- Flood hydrograph from 2-h UH, 5.2 cm rainfall · Engineering Hydrology, chapter 5
- Time and space switch drawbacks · Telecommunications, chapter 4
- Taper turning: set-over and compound angle · Workshop Technology, chapter 6
- Techniques for average depth of rainfall · Hydro Power, chapter 2
- Clay over sand, effective stress at depths · Soil Mechanics, chapter 6