- 2067 Mangsir · 4 marks
Overhead cost and opportunity cost
Short answer
Overhead cost is indirect cost (indirect material, labour, expenses) that cannot be traced to a single product, so it is allocated via an absorption base. Opportunity cost is the benefit lost when choosing one alternative over the next best, a non-cash economic cost relevant for decision-making.
Explain overhead cost and opportunity cost.
Overhead cost
Overhead cost (indirect cost) is the total of indirect material, indirect labour and indirect expenses. It cannot be traced to a single product or job, so it is distributed over products using an allocation base (labour hours, machine hours, % of direct labour).
- Types: factory overhead (factory rent, power, supervisor wages, machine depreciation), administration overhead (office salaries, stationery), and selling and distribution overhead (advertising, delivery).
- By behaviour: fixed, variable or semi-variable.
- Overhead absorption rate = budgeted overhead / budgeted base (e.g. Rs 600,000 / 20,000 labour hours = Rs 30 per hour).
Opportunity cost
Opportunity cost is the benefit lost by giving up the best alternative when a resource is used for one purpose. It is not a cash payment, but it is a real economic cost and must be included in decisions.
Example: A company owns a plot it could rent out for Rs 200,000 per year. If it builds a factory on it, the Rs 200,000 rent forgone is the opportunity cost of the land, even though no cash is paid. Similarly, if Rs 1 million is invested in a machine instead of a bank deposit earning 8%, the lost interest of Rs 80,000 per year is an opportunity cost.
This is also why the minimum attractive rate of return (MARR) is set at the return of the best investment opportunity forgone.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Fixed overhead cost variance from standard card · Engineering Economics, chapter 1
- Elements of cost; prime and overhead cost · Engineering Economics, chapter 1
- Cost variance analysis from standard and actual · Engineering Economics, chapter 1
- TCTO numerical: least cost schedule, Rs 2000/week · Construction Management, chapter 2
- Cost-plus pricing numerical · Entrepreneurship Development, chapter 3