- 2066 Magh · 6 marks
Fixed overhead cost variance from standard card
Short answer
Standard fixed overhead Rs 30/unit (2 hrs at Rs 15/hr). Absorbed 24,000 vs actual 32,400: total variance Rs 8,400 A. Expenditure variance Rs 2,400 A, capacity Rs 3,000 A, efficiency Rs 3,000 A.
In the standard card, it is observed that one unit of product 'X' requires fixed overhead of 2 hrs at the rate of Rs. 15/hr. During the month of February, 800 units are produced at the actual fixed overhead of Rs. 18/hr in 1800 hours. Budgeted fixed overhead is Rs. 30,000. Perform cost variance analysis.
Standard data
- Standard: 2 hours per unit at Rs 15/h, so standard fixed overhead = Rs 30 per unit
- Budgeted fixed overhead = Rs 30,000, so budgeted hours = 30,000 / 15 = 2,000 h (budgeted output 1,000 units)
- Actual: 800 units, 1,800 hours, at Rs 18/h; actual fixed overhead = 1,800 × 18 = Rs 32,400
Standard hours for actual output = 800 × 2 = 1,600 h. Absorbed (recovered) overhead = 800 × 30 = Rs 24,000.
Variances
| Variance | Calculation | Rs |
|---|---|---|
| Total FOH cost variance | Absorbed 24,000 − actual 32,400 | 8,400 A |
| Expenditure (budget) variance | Budgeted 30,000 − actual 32,400 | 2,400 A |
| Volume variance | Absorbed 24,000 − budgeted 30,000 | 6,000 A |
| - Capacity variance | (AH − budgeted hours) × 15 = (1,800 − 2,000) × 15 | 3,000 A |
| - Efficiency variance | (SH for actual output − AH) × 15 = (1,600 − 1,800) × 15 | 3,000 A |
Check: 2,400 A + 3,000 A + 3,000 A = 8,400 A.
(Equivalent view: rate variance = (15 − 18) × 1,800 = 5,400 A and efficiency variance 3,000 A, total 8,400 A.)
Answer: Total fixed overhead variance = Rs 8,400 adverse (expenditure 2,400 A, capacity 3,000 A, efficiency 3,000 A). Output and efficiency were below standard and overhead spending exceeded the budget.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Cost variance analysis from standard and actual · Engineering Economics, chapter 1
- Variance analysis, 9,300 vs 10,500 units · Engineering Economics, chapter 1
- Standard costing variances, 3000 vs 2500 units · Engineering Economics, chapter 1
- Constant vs actual dollar; inflation-free rate on loan · Engineering Economics, chapter 8 · asked 2×
- Standard costing variances for a building company · Engineering Economics, chapter 1
- Overhead cost and opportunity cost · Engineering Economics, chapter 1
- Derive 4-hr UH from observed streamflow · Engineering Hydrology, chapter 5
- EVA; plantation 50 units, 3 weeks, Rs 2500 · Project Engineering, chapter 4 · asked 2×
- EVA; plantation 50 units, 4 weeks, Rs 200 · Project Engineering, chapter 4 · asked 2×
- Cost control; EVA 15 houses in 3 months · Project Engineering, chapter 4