- 2070 Asar · 3+4 marks
Cost control; EVA 15 houses in 3 months
Short answer
PV = 125 lakh, EV = 100 lakh, AC = 96 lakh; SV = -25 lakh, CV = 4 lakh, SPI = 0.800, CPI = 1.042. The project is behind schedule but under budget.
Why is cost control important in a project? 15 houses were to be completed in three months with a per unit cost of Rs 25,00,000. In one month 4 houses were completed with a total expenditure of Rs 96,00,000. Use earned value analysis to find the status of the project.
Importance of cost control
- It keeps the actual cost within the budget and avoids overrun.
- It shows variances early, so that corrective action can be taken.
- It helps to forecast the final cost and the cash needed.
- It increases profit, efficiency and the client's confidence.
Earned value analysis
Money is in Rs lakh (Rs 25,00,000 = Rs 25 lakh per house).
- BAC = 15 x 25 = Rs 375 lakh (Rs 3.75 crore)
- After 1 month: planned = 1/3 of the work (5 houses); completed = 4 houses; actual cost = Rs 96 lakh
Calculation
Comment
- Schedule: SV is negative and SPI = 0.800, so the project is behind schedule. Only 80 % of the planned work is done. At this rate the work will take about 3.75 months instead of the planned 3 months.
- Cost: CV is positive and CPI = 1.042, so the project is under budget. Each Rs 1 spent gives Rs 1.04 of work.
- Forecast: if the present cost trend continues, the final cost will be Rs 360 lakh against the budget of Rs 375 lakh (variance at completion = Rs 15 lakh saving).
Answer: SV = -Rs 25 lakh, CV = Rs 4 lakh, SPI = 0.800, CPI = 1.042; the project is behind schedule and under budget.
Cost is favourable but progress is slow. Controlling statements: add resources or work extra shifts to recover the delay, remove bottlenecks (material, equipment, approvals), and keep the present cost discipline.
Five houses were planned in the first month, but only 4 were finished. The project is behind schedule (it needs about 3.75 months instead of 3), but the cost is slightly under budget.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- EVA; 60 days, 25% work, Rs 12,00,000 · Project Engineering, chapter 4
- EVA and S-curve; Rs 30,00,000, 24 months · Project Engineering, chapter 4
- Cost control need; earned value; EVA approach · Project Engineering, chapter 4
- EPS and book value; ABC project Rs 6,00,000 · Project Engineering, chapter 6
- EVA application; 35 days, Rs 8,00,000 spent · Project Engineering, chapter 4
- EPS; total capital Rs 15,00,000 · Project Engineering, chapter 6
- Capitalised value from Rs 20,000 monthly rent · Construction Management, chapter 13
- Earned value analysis for performance control · Construction Management, chapter 7 · asked 6×
- Earned value management · ICT Project Management, chapter 9
- Valuation of a cinema hall (land Rs 15 lakh) · Construction Management, chapter 13 · asked 2×