- Practice · 4+4 marks
TPM pillars and OEE calculation
Short answer
TPM involves all employees in equipment care to achieve zero breakdowns, defects, and accidents. Pillars: autonomous and planned maintenance, focused improvement, quality maintenance, early equipment management, training, safety, office TPM. OEE: availability = 405/450 = 90.0%, performance = (1×340)/405 = 84.0%, quality = 328/340 = 96.5%, OEE = 0.900×0.8395×0.9647 = 72.9%.
(a) Explain Total Productive Maintenance (TPM) and its main pillars. (b) A machine runs 480 minutes in a shift with 30 minutes planned break. There is 45 minutes of breakdown downtime. The ideal cycle time is 1 minute per unit; the machine produced 340 units, of which 12 were defective. Calculate availability, performance, quality rate and OEE.
(a) TPM
Total Productive Maintenance (developed in Japan by Nippondenso and promoted by Seiichi Nakajima) is a company-wide approach in which all employees, from top management to operators, take part in keeping equipment in the best condition. Its aim is zero breakdowns, zero defects and zero accidents. The operator performs routine cleaning, lubricating and inspection (autonomous maintenance), while the maintenance staff do specialised work.
Main pillars (8 pillars)
- Autonomous maintenance (Jishu Hozen): operator cleans, inspects, lubricates.
- Planned maintenance: scheduled and predictive maintenance.
- Focused improvement (Kobetsu Kaizen): remove losses by small team projects.
- Quality maintenance: keep equipment conditions that give defect-free product.
- Early equipment management: new equipment designed for easy maintenance.
- Training and education.
- Safety, health and environment.
- Office TPM: remove waste in administration.
The base is 5S. The six big losses are breakdown, set-up and adjustment, idling and minor stops, reduced speed, process defects and start-up losses.
(b) Overall equipment effectiveness
Planned production time min. Operating time min.
Answer: Availability 90.0%, performance 84.0%, quality 96.5%, OEE = 72.9%.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Assembly line balancing with cycle time · Industrial Engineering and Management, chapter 2
- TPQM and quality-related maintenance · Industrial Engineering and Management, chapter 7
- Types of maintenance and their comparison · Industrial Engineering and Management, chapter 7
- Break-even cost comparison of three sites · Industrial Engineering and Management, chapter 2
- EOQ, total cost and reorder point numerical · Industrial Engineering and Management, chapter 4
- Ideal Brayton cycle with 30 MW heat input · Fundamental of Thermodynamics & Heat Transfer, chapter 6 · asked 2×
- Planned maintenance, planning and scheduling · Construction Management, chapter 9 · asked 2×
- Planned vs unplanned maintenance; maintenance plan · Construction Management, chapter 9
- Preventive, corrective and breakdown maintenance · Construction Management, chapter 9 · asked 3×
All Industrial Engineering and Management chapter 7 questions →