- Practice · 8 marks
Assembly line balancing with cycle time
Short answer
Cycle time = 480/60 = 8 min. Total task time = 30 min, theoretical minimum stations = 4. Using ranked positional weight, 5 stations assigned; efficiency = 30/(5×8) = 75%, balance delay = 25%.
An assembly line must make 60 units in an 8-hour day (480 minutes). The tasks, their times and immediate predecessors are:
| Task | A | B | C | D | E | F | G | H |
|---|---|---|---|---|---|---|---|---|
| Time (min) | 4 | 3 | 5 | 4 | 3 | 6 | 2 | 3 |
| Predecessor | - | A | A | B | C | D, E | F | G |
Find (a) the cycle time, (b) the theoretical minimum number of stations, (c) a balanced assignment of tasks to stations using the ranked positional weight method, and (d) the efficiency of the line and balance delay.
(a) Cycle time
(b) Minimum number of stations
Total task time min.
(c) Ranked positional weight (RPW)
RPW of a task = its own time plus the times of all tasks that follow it.
| Task | A | B | C | D | E | F | G | H |
|---|---|---|---|---|---|---|---|---|
| RPW | 30 | 18 | 19 | 15 | 14 | 11 | 5 | 3 |
Order of rank: A, C, B, D, E, F, G, H. Assign to each station the highest-ranked available task that fits in the remaining cycle time.
| Station | Tasks | Time (min) | Idle (min) |
|---|---|---|---|
| 1 | A (4), B (3) | 7 | 1 |
| 2 | C (5), E (3) | 8 | 0 |
| 3 | D (4) | 4 | 4 |
| 4 | F (6), G (2) | 8 | 0 |
| 5 | H (3) | 3 | 5 |
Explanation: after A (4 min) only 4 min remain in the station. C (RPW 19) needs 5 min, which does not fit, so B (3 min) is taken. Task D cannot join station 2 because C+E already use 8 min, and F cannot start until D is finished, so D takes a station alone. F (6) and G (2) fill station 4 exactly.
(d) Efficiency and balance delay
The four-station minimum is not reachable because of the precedence limits, so five stations are needed.
Answer: Cycle time 8 min; minimum stations 4 (theoretical); 5 stations used; efficiency 75%; balance delay 25%.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- PERT expected time and completion probability · Industrial Engineering and Management, chapter 3
- TPM pillars and OEE calculation · Industrial Engineering and Management, chapter 7
- Safety stock and reorder level with lead time · Industrial Engineering and Management, chapter 4
- CPM schedule, critical path and float · Industrial Engineering and Management, chapter 3
- EOQ, total cost and reorder point numerical · Industrial Engineering and Management, chapter 4
- AC with COP 4 for hall: minimum theoretical power · Fundamental of Thermodynamics & Heat Transfer, chapter 5
- Balancing tank: village 80000 L/day, spring 0.8 lps · Water Supply Engineering, chapter 7
- Is balancing tank necessary: 20000 L/day spring · Water Supply Engineering, chapter 7
- Normal: machinery assembly time · Probability and Statistics, chapter 3
All Industrial Engineering and Management chapter 2 questions →