Skip to main content

Assembly line balancing with cycle time

Short answer

Cycle time = 480/60 = 8 min. Total task time = 30 min, theoretical minimum stations = 4. Using ranked positional weight, 5 stations assigned; efficiency = 30/(5×8) = 75%, balance delay = 25%.

An assembly line must make 60 units in an 8-hour day (480 minutes). The tasks, their times and immediate predecessors are:

TaskABCDEFGH
Time (min)43543623
Predecessor-AABCD, EFG

Find (a) the cycle time, (b) the theoretical minimum number of stations, (c) a balanced assignment of tasks to stations using the ranked positional weight method, and (d) the efficiency of the line and balance delay.

(a) Cycle time

C=available timerequired output=48060=8 minC = \frac{\text{available time}}{\text{required output}} = \frac{480}{60} = 8\ \text{min}

(b) Minimum number of stations

Total task time =4+3+5+4+3+6+2+3=30= 4+3+5+4+3+6+2+3 = 30 min.

Nmin=∑tC=308=3.75⇒4 stationsN_{min} = \frac{\sum t}{C} = \frac{30}{8} = 3.75 \Rightarrow 4\ \text{stations}

(c) Ranked positional weight (RPW)

RPW of a task = its own time plus the times of all tasks that follow it.

TaskABCDEFGH
RPW30181915141153

Order of rank: A, C, B, D, E, F, G, H. Assign to each station the highest-ranked available task that fits in the remaining cycle time.

StationTasksTime (min)Idle (min)
1A (4), B (3)71
2C (5), E (3)80
3D (4)44
4F (6), G (2)80
5H (3)35

Explanation: after A (4 min) only 4 min remain in the station. C (RPW 19) needs 5 min, which does not fit, so B (3 min) is taken. Task D cannot join station 2 because C+E already use 8 min, and F cannot start until D is finished, so D takes a station alone. F (6) and G (2) fill station 4 exactly.

(d) Efficiency and balance delay

Efficiency=∑tN C×100=305×8×100=75%\text{Efficiency} = \frac{\sum t}{N\,C} \times 100 = \frac{30}{5 \times 8} \times 100 = 75\% Balance delay=100−75=25%\text{Balance delay} = 100 - 75 = 25\%

The four-station minimum is not reachable because of the precedence limits, so five stations are needed.

Answer: Cycle time 8 min; minimum stations 4 (theoretical); 5 stations used; efficiency 75%; balance delay 25%.

✓ Answer checked by Claude Opus 5.5 (high effort)

All Industrial Engineering and Management chapter 2 questions →