- 2072 Magh · 4 marks
Best substation location from load figure
Short answer
Compute load centre: x̄ = Σ(Si·xi)/ΣSi = 6050/244 = 24.80 m; ȳ = Σ(Si·yi)/ΣSi = 5600/244 = 22.95 m. Result near W1 at (25, 23) m. Locate substation here to minimise cable length, losses, and voltage drop, since W1 is 82% of load.
In the figure below, select the best option for setting the sub-station with suitable justifications. [Figure: a site plan on x-y coordinates (x axis marked 10, 80, 85, 100; y axis marked 10, 20, 28, 50, 60) with five loads: W1 = 200 kVA at (10, 20), W2 = 10 kVA at (80, 60), W3 = 12 kVA at (100, 50), W4 = 10 kVA at (85, 28), W5 = 12 kVA at (100, 10).]
The best site for a substation is at or near the load centre (centre of gravity of the loads), because it gives the least load × distance product, so LT cable cost, voltage drop and losses are minimum.
Load centre calculation
| Load | kVA | x | y | kVA·x | kVA·y |
|---|---|---|---|---|---|
| W1 | 200 | 10 | 20 | 2000 | 4000 |
| W2 | 10 | 80 | 60 | 800 | 600 |
| W3 | 12 | 100 | 50 | 1200 | 600 |
| W4 | 10 | 85 | 28 | 850 | 280 |
| W5 | 12 | 100 | 10 | 1200 | 120 |
| Total | 244 | 6050 | 5600 |
x̄ = Σ W·x / Σ W = 6050 / 244 = 24.80
ȳ = Σ W·y / Σ W = 5600 / 244 = 22.95
Selection and justification
- The load centre is at about (24.8, 23.0), very close to W1 (10, 20).
- W1 (200 kVA) is 82 % of the total load, so the substation should be placed next to W1, on the side facing the other loads.
- The heavy 200 kVA current then travels only a few metres, while only the small loads (10–12 kVA, low current) need long cables to the right side of the site, where voltage drop can be handled with modest cable sizes.
- Placing it at the geometric middle of the site (around x = 55) or near W2–W5 would make the large W1 feeder long and costly, with high losses.
Answer: locate the substation near W1, at about (25, 23) (or the option in the figure nearest to this point), subject to access, safety and HT line route.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Power/light sub-circuits and cable for 50 kW, 60 kW · Industrial Power Distribution and Illumination, chapter 5 · asked 4×
- Distribution substation site selection factors · Industrial Power Distribution and Illumination, chapter 4
- Substation site criteria and H-pole BOQ · Industrial Power Distribution and Illumination, chapter 4
- Cable size MDB to SDB1 (80 kW) and SDB2 (10 kW) · Industrial Power Distribution and Illumination, chapter 5 · asked 5×
- Substation capacity and diversity factor from load pattern · Industrial Power Distribution and Illumination, chapter 1
- Importance of distribution substation with SLD · Industrial Power Distribution and Illumination, chapter 4
- Sony-Samsung Markov, 80/85, 60% users · Simulation and Modeling, chapter 5
- Best financing option; EBIT Rs 350,000 · Project Engineering, chapter 6
- Capital structure; best option by EPS, three options · Project Engineering, chapter 6
- Coordinates of instrument station O and station A · Surveying II, chapter 5
All Industrial Power Distribution and Illumination chapter 4 questions →