Canal drop structure, Q 5, FSL 110.5

Short answer

A Sarda-type vertical fall with rectangular crest (length 3 m) yields crest level 109.59 m, head 0.910 m, top width 0.69 m. Cistern length 4.84 m, depth 0.24 m, floor level 107.76 m. Total impervious floor 9.07 m (u/s 1.0 m, d/s 6.40 m); cut-offs 1.10 m and 1.35 m; d/s floor thickness 1.11 m reducing to 0.52 m.

Design a canal drop structure for the data given below: Q = 5 m³/s; FSL, upstream = 110.5 m; FSL, downstream = 109.5 m; Normal Depth, u/s and d/s = 1.5 m; Bed width = 3.0 m; Bligh's coefficient, C = 7.

Given data and assumptions

  • Q=5Q = 5 m³/s, bed width B=3B = 3 m, side slope 1:1, u/s FSL =110.50= 110.50 m, u/s bed =109.00= 109.00 m, d/s bed =108.00= 108.00 m.
  • Full supply depth u/s = d/s D=1.5D = 1.5 m (d/s FSL =109.50= 109.50 m); drop in water level HL=1H_L = 1 m.
  • Bligh's coefficient C=7C = 7; specific gravity of the masonry/concrete G=2.24G = 2.24 (assumed).
  • Bed levels: u/s =110.5−1.5=109.0= 110.5 - 1.5 = 109.0 m, d/s =109.5−1.5=108.0= 109.5 - 1.5 = 108.0 m. Side slope 1:1 is assumed. The drop is designed as a Sarda-type vertical fall.

1. Upstream flow conditions

A=(B+mD)D=(3+1×1.5)(1.5)=6.750 m2Va=Q/A=0.741 m/s,ha=Va22g=0.028 m\begin{aligned} A &= (B + mD)D = (3 + 1\times1.5)(1.5) = 6.750\ \text{m}^2 \\ V_a &= Q/A = 0.741\ \text{m/s}, \qquad h_a = \frac{V_a^2}{2g} = 0.028\ \text{m} \end{aligned}

2. Crest

Since Q<14Q < 14 m³/s, a rectangular crest is used, with crest length equal to the bed width, L=3L = 3 m, and

Q=1.835 L H3/2(HBc)1/6,Bc=0.55dQ = 1.835\,L\,H^{3/2}\left(\frac{H}{B_c}\right)^{1/6}, \qquad B_c = 0.55\sqrt{d}

where HH is the head over the crest (measured from the u/s FSL), BcB_c is the top width of the crest and dd is the height of the crest above the d/s bed. Solving by trial:

H=0.910 m,crest level=110.50−0.910=109.59 m,d=109.59−108.00=1.59 mH = 0.910\ \text{m}, \qquad \text{crest level} = 110.50 - 0.910 = 109.59\ \text{m}, \qquad d = 109.59 - 108.00 = 1.59\ \text{m}

Top width Bc=0.551.59=0.69B_c = 0.55\sqrt{1.59} = 0.69 m. Base width of the crest wall:

Bw=H+dG=0.910+1.592.24=1.67 mB_w = \frac{H + d}{\sqrt{G}} = \frac{0.910 + 1.59}{\sqrt{2.24}} = 1.67\ \text{m}

3. Cistern

Energy head over the crest E=H+ha=0.910+0.028=0.938E = H + h_a = 0.910 + 0.028 = 0.938 m. Using the UPIRI formulas:

Lc=5E HL=50.938×1=4.84 mX=14 (E HL)2/3=14 (0.938)2/3=0.240 m\begin{aligned} L_c &= 5\sqrt{E\,H_L} = 5\sqrt{0.938\times1} = 4.84\ \text{m} \\ X &= \tfrac14\,(E\,H_L)^{2/3} = \tfrac14\,(0.938)^{2/3} = 0.240\ \text{m} \end{aligned}

Cistern floor level =108.00−0.240=107.76= 108.00 - 0.240 = 107.76 m.

4. Impervious floor (Bligh's theory)

Maximum seepage head occurs with no flow, water up to the crest on the u/s side and the d/s side dry: Hs=d=1.59H_s = d = 1.59 m. Required creep length L=C Hs=7×1.59=11.13L = C\,H_s = 7\times1.59 = 11.13 m.

  • Cut-offs: u/s d1=D/3+0.6=1.10d_1 = D/3 + 0.6 = 1.10 m; d/s d2=D/2+0.6=1.35d_2 = D/2 + 0.6 = 1.35 m.
  • Horizontal floor length b=L−2(d1+d2)=11.13−4.90=6.23b = L - 2(d_1 + d_2) = 11.13 - 4.90 = 6.23 m.
  • Minimum d/s floor (from the d/s face of the crest wall) =2(D+1.2)+HL=6.40= 2(D + 1.2) + H_L = 6.40 m, which is more than LcL_c; adopt Ld=6.40L_d = 6.40 m.
  • U/s floor =b−Ld−Bw=6.23−6.40−1.67=−1.84= b - L_d - B_w = 6.23 - 6.40 - 1.67 = -1.84 m, so a minimum u/s floor of 1.0 m is provided. Actual creep =13.97= 13.97 m ≥11.13\ge 11.13 m, safe.
  • Total floor length =1.00+1.67+6.40=9.07= 1.00 + 1.67 + 6.40 = 9.07 m.

5. Floor thickness

Creep up to the d/s toe of the crest wall =2d1+bu+Bw=4.87= 2d_1 + b_u + B_w = 4.87 m, so the residual uplift head there is h1=Hs L−4.87L=1.59×13.97−4.8713.97=1.036h_1 = H_s\,\dfrac{L - 4.87}{L} = 1.59\times\dfrac{13.97 - 4.87}{13.97} = 1.036 m (with L=13.97L = 13.97 m, the creep provided).

t1=43 h1G−1=43×1.0361.24=1.11 mt_1 = \frac{4}{3}\,\frac{h_1}{G - 1} = \frac{4}{3}\times\frac{1.036}{1.24} = 1.11\ \text{m}

At the end of the cistern the creep is 9.71 m, h2=0.485h_2 = 0.485 m and t2=0.52t_2 = 0.52 m. Adopt a d/s floor 1.11 m thick near the crest wall, reducing to 0.52 m beyond the cistern (minimum 0.30 m); the u/s floor is given a nominal 0.30 m.

Summary

ComponentValue
Crestrectangular, length 3 m, level 109.59 m, head HH = 0.910 m
Crest width (top / base)0.69 m / 1.67 m
Cistern (length / depth)4.84 m / 0.24 m, floor level 107.76 m
Floor (u/s / wall base / d/s)1.00 / 1.67 / 6.40 m, total 9.07 m
Cut-offs (u/s / d/s)1.10 m / 1.35 m
D/s floor thickness1.11 m, reducing to 0.52 m

Answer: crest level 109.59 m (rectangular crest 3 m long, top width 0.69 m, base 1.67 m); cistern 4.84 m long and 0.24 m deep; impervious floor 9.07 m long (u/s 1.00 m, d/s 6.40 m) with cut-offs of 1.10 m (u/s) and 1.35 m (d/s); d/s floor thickness 1.11 m, reducing to 0.52 m.

Sketch:

 FSL u/s ~~~~~~~~~~~|
                    |  crest
 u/s bed ___________|__          FSL d/s ~~~~
        |  u/s floor |  \  drop        ~~~~~
     d1 |            |   \_____cistern________ d/s bed
        |            |<-Lc->|   d/s floor   | d2
                     |____ floor thickness __|