Canal fall design, Q 12, drop 1.5 m
Short answer
Rectangular crest at 203.13 m, 8 m long, top width 0.80 m, base 2.00 m. Cistern 5.82 m long, 0.31 m deep, floor level 200.69 m. Total floor 12.16 m; d/s floor thickness 1.29 m reducing to 0.51 m.
Design a fall for a canal having a discharge of 12 cumecs for the data given below. Full supply level u/s and d/s = 204 and 202.5; Bed level u/s and d/s = 202.5 and 201; Bed width u/s and d/s = 8 m; Drop height = 1.5 m; Side Slope of canal = 1:1; Bligh's creep coefficient = 8.
Given data and assumptions
- m³/s, bed width m, side slope 1:1, u/s FSL m, u/s bed m, d/s bed m.
- Full supply depth u/s = d/s m (d/s FSL m); drop in water level m.
- Bligh's coefficient ; specific gravity of the masonry/concrete (assumed).
- The 1.5 m fall is designed as a Sarda-type vertical drop.
1. Upstream flow conditions
2. Crest
Since m³/s, a rectangular crest is used, with crest length equal to the bed width, m, and
where is the head over the crest (measured from the u/s FSL), is the top width of the crest and is the height of the crest above the d/s bed. Solving by trial:
Top width m. Base width of the crest wall:
3. Cistern
Energy head over the crest m. Using the UPIRI formulas:
Cistern floor level m.
4. Impervious floor (Bligh's theory)
Maximum seepage head occurs with no flow, water up to the crest on the u/s side and the d/s side dry: m. Required creep length m.
- Cut-offs: u/s m; d/s m.
- Horizontal floor length m.
- Minimum d/s floor (from the d/s face of the crest wall) m, which is more than ; adopt m.
- U/s floor 3.26 m.
- Total floor length m.
5. Floor thickness
Creep up to the d/s toe of the crest wall m, so the residual uplift head there is m (with m, the creep provided).
At the end of the cistern the creep is 13.28 m, m and m. Adopt a d/s floor 1.29 m thick near the crest wall, reducing to 0.51 m beyond the cistern (minimum 0.30 m); the u/s floor is given a nominal 0.30 m.
Summary
| Component | Value |
|---|---|
| Crest | rectangular, length 8 m, level 203.13 m, head = 0.867 m |
| Crest width (top / base) | 0.80 m / 2.00 m |
| Cistern (length / depth) | 5.82 m / 0.31 m, floor level 200.69 m |
| Floor (u/s / wall base / d/s) | 3.26 / 2.00 / 6.90 m, total 12.16 m |
| Cut-offs (u/s / d/s) | 1.10 m / 1.35 m |
| D/s floor thickness | 1.29 m, reducing to 0.51 m |
Answer: crest level 203.13 m (rectangular crest 8 m long, top width 0.80 m, base 2.00 m); cistern 5.82 m long and 0.31 m deep; impervious floor 12.16 m long (u/s 3.26 m, d/s 6.90 m) with cut-offs of 1.10 m (u/s) and 1.35 m (d/s); d/s floor thickness 1.29 m, reducing to 0.51 m.
Sketch:
FSL u/s ~~~~~~~~~~~|
| crest
u/s bed ___________|__ FSL d/s ~~~~
| u/s floor | \ drop ~~~~~
d1 | | \_____cistern________ d/s bed
| |<-Lc->| d/s floor | d2
|____ floor thickness __|
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Sarda fall: Q 12, bed level 103 m · Irrigation and Drainage Engineering, chapter 7
- Sarda fall: Q 12, U/S bed 103 m · Irrigation and Drainage Engineering, chapter 7
- Crest width, cistern length of vertical drop, Q 1.55 · Irrigation and Drainage Engineering, chapter 7 · asked 2×
- Vertical drop crest level and width, Q 30 · Irrigation and Drainage Engineering, chapter 7
- Vertical drop design, Q 1.8 m3/s (bed 205.05) · Irrigation and Drainage Engineering, chapter 7 · asked 4×
- Vertical drop design, Q 1.8 m3/s (drop 0.75 m) · Irrigation and Drainage Engineering, chapter 7 · asked 2×
- Irrigation canal earthwork with vertical drop · Estimating and Costing, chapter 6
- Canal earthwork, bed 3 m, free board 0.44 m · Estimating and Costing, chapter 6
All Irrigation and Drainage Engineering chapter 7 questions →