- Asked 3/34
- 2070 Bhadra · 10 marks
- 2071 Bhadra · 6 marks
Drainage rate (l/s/ha) for bunded rice fields
Short answer
By trial, the drainage rate that satisfies the constraints (peak water level ≤400 mm for ≤1 day, depth above 250 mm ≤2 days) for a 3-day 400 mm rainfall starting from 50 mm initial depth is 46.5 mm/day, which equals 5.38 l/s/ha, adopted as 5.4 l/s/ha.
Determine the drainage rate in l/s/ha required to meet the following conditions for healthy growth of rice paddies in bunded field in Terai of Nepal. Initial water level in field = 50 mm; Maximum water level is 400 mm which may persist for up to one day; Depth in excess of 250 mm may persist for up to 2 days; No rain follows the design rainfall for several days; Neglect ET and deep percolation losses; Design 3 day rainfall is 400 mm.
Rice tolerates standing water only within limits of depth and duration, so the drainage rate is chosen such that the field water level during and after the design storm stays within these limits.
Given data and assumptions
- Initial depth = 50 mm; design 3-day rainfall = 400 mm, falling uniformly, so the rain rate = 133.3 mm/day
- Maximum depth 400 mm may persist for 1 day; depth above 250 mm may persist for 2 days
- ET and deep percolation neglected (safe side); drainage (mm/day) starts with the rain and is constant
Water level history
During the storm the level rises at per day, and after it the level falls at per day:
The duration condition above 250 mm governs. Trial values:
| D (mm/day) | Peak level (mm) | Time above limit (days) |
|---|---|---|
| 40 | 330 | 2.86 |
| 45 | 315 | 2.18 |
| 46.5 | 310 | 2.00 |
| 50 | 300 | 1.60 |
| 55 | 285 | 1.08 |
Solving = 2 days gives = 46.5 mm/day. Then:
- = 50 + 400 − 3 × 46.5 = 311 mm, which is below 400 mm, so the 400 mm level is never reached and the 1-day limit is satisfied
- = 2.30 days, = 1.30 days, = (3 − 2.30) + 1.30 = 2.00 days
Conversion: 1 mm/day = 10 m³/ha/day = 0.1157 l/s/ha, so
Answer: drainage rate ≈ 46.5 mm/day ≈ 5.4 l/s/ha (adopt about 5.4 l/s/ha).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Drainage rate (mm/day), initial 55 mm · Irrigation and Drainage Engineering, chapter 9 · asked 3×
- Surface drainage design, 40 ha Terai field · Irrigation and Drainage Engineering, chapter 9
- Drainage rate: 300 mm in 3 days, growth factor 1.5 · Irrigation and Drainage Engineering, chapter 9 · asked 2×
- Drainage canal for 5 ha paddy field · Irrigation and Drainage Engineering, chapter 9 · asked 2×
- Design discharge for surface drainage, bunded field · Irrigation and Drainage Engineering, chapter 9
- Water logging remedies and surface drainage in Terai · Irrigation and Drainage Engineering, chapter 9
- Internal/external drainage; water logging; Terai surface drainage · Irrigation and Drainage Engineering, chapter 9
- Reservoir level change, water balance, 1600 ha · Engineering Hydrology, chapter 1 · asked 2×
All Irrigation and Drainage Engineering chapter 9 questions →