Short answer

Planning stages are: identification from maps/visits; pre-feasibility for quick screening; feasibility with detailed surveys, design, and economic analysis; detailed design and tender documents; then implementation and operation. This stepwise process ensures only viable projects proceed.

Describe in brief the stages (levels) of planning of irrigation projects.

Planning of an irrigation project is done step by step so that only viable projects proceed to costly design and construction.

  1. Identification (reconnaissance) stage: potential sites are identified from maps, field visits and existing data. Water source, command area, rough cost and benefits are assessed. Output: a list of possible projects.
  2. Pre-feasibility stage: a quick study of technical, economic, social and environmental aspects. Alternatives are compared, rough designs and cost estimates are prepared, and the project is screened.
  3. Feasibility stage: detailed surveys (topographic, hydrological, geological, soil, agro-economic), preliminary design, quantity and cost estimate, benefit-cost analysis (B/C ratio, IRR, NPV), environmental and social impact assessment, and institutional/financial plans. Decides whether to proceed.
  4. Detailed design and tender stage: final design of headworks, canals and structures, drawings, specifications, bill of quantities, tender documents.
  5. Implementation (construction) and operation stage: construction, commissioning, O&M and later monitoring and evaluation.

Planning is also viewed at levels: national/master plan, river-basin (regional) plan, and project plan.