Siphon: canal 50, FSL 201.80, RCC flumed

Short answer

Siphon aqueduct. Drainage waterway: 11 spans of 10 m, 110 m clear, overall 125 m. Canal flumed to an 18 m rectangular trough; transitions 23.4 m inlet and 35.1 m outlet. Trough bed levels 199.876 m and 199.837 m; downstream canal bed 199.885 m, FSL 201.685 m, upstream bed 200.000 m.

Design syphon of a syphon aqueduct for the following data: Canal: Q = 50 m³/s; FSL = 201.80 m; CBL = 200.00 m; B = 36 m; z (side slope) = 1.5. Drainage: Qmax = 450 m³/s; HFL = 200.50 m; DBL = 198.00 m; GL = 200.00 m. Assume that the aqueduct will be made of RCC having flumed width of 18 m. Assume other data suitably, if necessary.

The canal (QQ = 50 m³/s) crosses a drainage of QQ = 450 m³/s. Design is done in four steps: type of work, drainage waterway, canal waterway (flumed trough) and bed/water levels of the trough.

Assumptions: Flumed (RCC) trough width 18 m as given; nn = 0.015 for RCC; Lacey's ff = 1; slab 0.6 m; barrel nn = 0.015 and barrel length ≈ trough width + walls ≈ 19 m. Depth of canal = 201.80 − 200.00 = 1.80 m.

1. Type of structure

HFL of the drainage (200.50 m) is above the canal bed (200.00 m) by 0.50 m, so the trough cannot be kept above HFL without a very high, costly structure. The drainage is passed under the trough through barrels flowing under pressure (siphonic action). A siphon aqueduct is suitable. Drainage depth at HFL = 200.50 − 198.00 = 2.50 m.

2. Drainage waterway

Lacey's regime perimeter (for a natural stream):

P=4.75Q=4.75450=100.8 mP = 4.75\sqrt{Q} = 4.75\sqrt{450} = 100.8\ \text{m}

Provide 11 spans of 10 m with piers 1.5 m thick: clear waterway = 11 × 10 = 110 m (> 100.8 m). Overall length = 110 + 10 × 1.5 = 125.0 m.

Check: mean velocity = Q/(L·d) = 450/(110 × 2.50) = 1.64 m/s. Lacey's regime depth R=0.47(Q/f)1/3R = 0.47(Q/f)^{1/3} = 3.60 m (with ff = 1); foundations of piers and abutments are taken about 1.5R = 5.4 m below HFL, with cut-offs and aprons for scour.

3. Canal waterway (flumed rectangular trough)

Normal canal: area A1=(B+zD)DA_1=(B+zD)D = (36 + 1.5 × 1.8) × 1.8 = 69.66 m², V1V_1 = 50/69.66 = 0.718 m/s, hv1=V12/2gh_{v1}=V_1^2/2g = 0.0263 m. Top width T=B+2zDT=B+2zD = 41.40 m.

To save cost, the canal is flumed to a rectangular trough of width BtB_t = 18 m, with the same full supply depth 1.8 m (the trough is as long as the drainage waterway, 125.0 m).

  • Trough area = 18 × 1.8 = 32.40 m²; VtV_t = 50/32.40 = 1.543 m/s (acceptable, < 2.5 m/s); hvth_{vt} = 0.1214 m
  • Froude number = 0.37 < 1, flow is subcritical, so there is no hydraulic jump.
  • Hydraulic radius R=A/PR=A/P = 32.40/21.60 = 1.500 m; friction slope S=(nV/R2/3)2S=(nV/R^{2/3})^2 = 0.000312 (Manning's n = 0.015); friction loss in trough hf=S Lh_f=S\,L = 0.000312 × 125.0 = 0.039 m

4. Transitions and levels

  FSL ---.                            .--- FSL
         '--.______________________.--'
  bed ---.                            .--- bed
         '--.______________________.--'
  normal  inlet     flumed trough     outlet  normal
  canal   (2:1)                      (3:1)   canal

Wing-wall (straight) transitions: inlet splay 2:1 (contraction) and outlet splay 3:1 (expansion), measured on each side:

  • Inlet length = 2 × (T − B_t)/2 = 41.40 − 18 = 23.4 m
  • Outlet length = 3 × (T − B_t)/2 = 35.1 m

Bernoulli's equation between sections (loss in contraction = 0.3 Δh_v, in expansion = 0.5 Δh_v; Δh_v = difference of velocity heads):

W2=W1+hv1−hvt−0.3(hvt−hv1)W3=W2−hfW4=W3+hvt−hv1−0.5(hvt−hv1)\begin{aligned} W_2 &= W_1 + h_{v1} - h_{vt} - 0.3(h_{vt}-h_{v1}) \\ W_3 &= W_2 - h_f \\ W_4 &= W_3 + h_{vt} - h_{v1} - 0.5(h_{vt}-h_{v1}) \end{aligned}

W1W_1 = 201.800 m, so W2W_2 = 201.676 m, W3W_3 = 201.637 m, W4W_4 = 201.685 m. Trough bed = water level − 1.8 m.

SectionLocationBed level (m)FSL (m)
1Normal canal, start of inlet transition200.000201.800
2End of inlet transition = start of trough199.876201.676
3End of trough = start of outlet transition199.837201.637
4End of outlet transition = normal canal199.885201.685

Total loss of head = 201.800 − 201.685 = 0.115 m, so the canal bed downstream of the work is 0.115 m lower than upstream.

Check: with trough slab 0.6 m thick, soffit of the barrels = 199.24 m, i.e. 1.24 m above the drainage bed; HFL stands 1.26 m above the soffit, which gives the siphonic head. Since the clear height is less than 1.5 m, the drainage bed is depressed under the barrels to RL 197.74 m (1.5 m clear height) with a 1 in 4 slope at both ends.

5. Design of the siphon (drainage barrels)

  • Barrels: 11 openings of 10 m clear width × 1.5 m clear height (drainage floor depressed to 197.74 m), area = 11 × 10 × 1.5 = 165 m².
  • Velocity in barrels VbV_b = 450/165 = 2.73 m/s (within the usual 2–3 m/s); hvbh_{vb} = 2.73²/19.62 = 0.379 m.
  • One barrel: RR = 15/23 = 0.652 m; friction loss hfb=n2Vb2L/R4/3=0.0152×2.732×19/0.6524/3h_{fb}=n^2V_b^2L/R^{4/3} = 0.015^2 \times 2.73^2 \times 19/0.652^{4/3} = 0.056 m.
  • Head loss through the siphon = entry (0.5hvb0.5h_{vb}) + exit (1.0hvb1.0h_{vb}) + friction = 0.190 + 0.379 + 0.056 = 0.625 m (approach velocity neglected).
  • Upstream HFL = 200.50 + 0.63 = 201.13 m, so the drainage banks and guide banks upstream are raised above this level, with free board.
  • Uplift on the roof (canal dry, drainage at HFL): the maximum is just inside the entry, with pressure head = 201.125 − 1.5 × 0.379 − 199.237 (soffit) = 1.32 m, so the uplift = 9.81 × 1.32 = 12.9 kN/m². This is less than the slab weight 24 × 0.6 = 14.4 kN/m², so the roof is safe against uplift.

Answer: drainage waterway 110 m clear (11 × 10 m, overall 125.0 m); canal flumed to 18 m wide trough; bed/FSL at the four sections = 200.00/201.80, 199.88/201.68, 199.84/201.64, 199.88/201.68 m; siphon barrels 11 × (10 m × 1.5 m), V = 2.73 m/s, head loss 0.63 m (upstream HFL 201.13 m), maximum uplift on the roof 12.9 kN/m².