- Asked 2/34
- 2069 Bhadra · 10 marks
Siphon aqueduct: Q 50, bed 32 m
Short answer
Siphon aqueduct. Drainage waterway: 12 spans of 8 m (96 m clear), overall 109.2 m. Canal flumed to a 15 m rectangular trough; transitions 22.4 m inlet and 33.6 m outlet. Trough bed levels 199.815 m and 199.764 m; downstream canal bed 199.835 m, FSL 201.635 m.
Design a syphon aqueduct (Drainage water way, Canal water way, Bed levels and Transitions) if the following data at the crossing of canal and drainage are given. Discharge of canal = 50 cumecs; Bed width of canal = 32 m; Full supply depth of canal = 1.80 m; Canal bed level = 200.0 m; Side slopes of canal = (1.5H:1V); High flood discharge of drainage = 400 cumecs; High flood level of drainage = 200.60 m; Bed level of drainage = 198.0 m; General ground level = 200.20 m.
The canal ( = 50 m³/s) crosses a drainage of = 400 m³/s. Design is done in four steps: type of work, drainage waterway, canal waterway (flumed trough) and bed/water levels of the trough.
Assumptions: Lacey's = 1; trough = 0.015; slab 0.6 m.
1. Type of structure
HFL of the drainage (200.60 m) is above the canal bed (200.00 m) by 0.60 m, so the trough cannot be kept above HFL without a very high, costly structure. The drainage is passed under the trough through barrels flowing under pressure (siphonic action). A siphon aqueduct is suitable. Drainage depth at HFL = 200.60 − 198.00 = 2.60 m.
2. Drainage waterway
Lacey's regime perimeter (for a natural stream):
Provide 12 spans of 8 m with piers 1.2 m thick: clear waterway = 12 × 8 = 96 m (> 95.0 m). Overall length = 96 + 11 × 1.2 = 109.2 m.
Check: mean velocity = Q/(L·d) = 400/(96 × 2.60) = 1.60 m/s. Lacey's regime depth = 3.46 m (with = 1); foundations of piers and abutments are taken about 1.5R = 5.2 m below HFL, with cut-offs and aprons for scour.
3. Canal waterway (flumed rectangular trough)
Normal canal: area = (32 + 1.5 × 1.8) × 1.8 = 62.46 m², = 50/62.46 = 0.801 m/s, = 0.0327 m. Top width = 37.40 m.
To save cost, the canal is flumed to a rectangular trough of width = 15 m, with the same full supply depth 1.8 m (the trough is as long as the drainage waterway, 109.2 m).
- Trough area = 15 × 1.8 = 27.00 m²; = 50/27.00 = 1.852 m/s (acceptable, < 2.5 m/s); = 0.1748 m
- Froude number = 0.44 < 1, flow is subcritical, so there is no hydraulic jump.
- Hydraulic radius = 27.00/18.60 = 1.452 m; friction slope = 0.000469 (Manning's n = 0.015); friction loss in trough = 0.000469 × 109.2 = 0.051 m
4. Transitions and levels
FSL ---. .--- FSL
'--.______________________.--'
bed ---. .--- bed
'--.______________________.--'
normal inlet flumed trough outlet normal
canal (2:1) (3:1) canal
Wing-wall (straight) transitions: inlet splay 2:1 (contraction) and outlet splay 3:1 (expansion), measured on each side:
- Inlet length = 2 × (T − B_t)/2 = 37.40 − 15 = 22.4 m
- Outlet length = 3 × (T − B_t)/2 = 33.6 m
Bernoulli's equation between sections (loss in contraction = 0.3 Δh_v, in expansion = 0.5 Δh_v; Δh_v = difference of velocity heads):
= 201.800 m, so = 201.615 m, = 201.564 m, = 201.635 m. Trough bed = water level − 1.8 m.
| Section | Location | Bed level (m) | FSL (m) |
|---|---|---|---|
| 1 | Normal canal, start of inlet transition | 200.000 | 201.800 |
| 2 | End of inlet transition = start of trough | 199.815 | 201.615 |
| 3 | End of trough = start of outlet transition | 199.764 | 201.564 |
| 4 | End of outlet transition = normal canal | 199.835 | 201.635 |
Total loss of head = 201.800 − 201.635 = 0.165 m, so the canal bed downstream of the work is 0.165 m lower than upstream.
Check: with trough slab 0.6 m thick, soffit of the barrels = 199.16 m, i.e. 1.16 m above the drainage bed; HFL stands 1.44 m above the soffit, which gives the siphonic head. Since the clear height is less than 1.5 m, the drainage bed is depressed under the barrels to RL 197.66 m (1.5 m clear height) with a 1 in 4 slope at both ends.
Answer: drainage waterway 96 m clear (12 × 8 m, overall 109.2 m); canal flumed to 15 m wide trough; bed/FSL at the four sections = 200.00/201.80, 199.82/201.62, 199.76/201.56, 199.84/201.64 m.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Siphon aqueduct: Q 60, bed 35 m · Irrigation and Drainage Engineering, chapter 8 · asked 2×
- Syphonic aqueduct canal waterway levels, Q 40 · Irrigation and Drainage Engineering, chapter 8
- Siphon aqueduct: Q 30, bed 24 m · Irrigation and Drainage Engineering, chapter 8
- Siphon aqueduct: Q 20, drainage 200 · Irrigation and Drainage Engineering, chapter 8
- Siphon aqueduct: Q 60, Manning 0.025 · Irrigation and Drainage Engineering, chapter 8
- Siphon: canal 50, FSL 201.80, RCC flumed · Irrigation and Drainage Engineering, chapter 8
- Siphon aqueduct: Q 30, drainage 800 · Irrigation and Drainage Engineering, chapter 8
All Irrigation and Drainage Engineering chapter 8 questions →