- 2072 Asoj · 8 marks
Critical DO deficit, 300 l/s into river
Short answer
Critical DO deficit is 18.56 mg/l at 1.88 days (90.2 km downstream). Mixed BOD5=78.25 mg/l, ultimate BOD=114.4 mg/l, initial deficit=3.21 mg/l. Minimum DO negative, stream would become anaerobic without treatment.
A town is discharging sewage of 300 liters/second in the river having discharge of 1300 liters/second and a velocity of 48 km/day. The BOD5 of sewage and river water are 400 mg/l and 4 mg/l respectively. The DO of sewage sample is nil. D.O. in the river water is 80% of the saturation value. The temperature of both sewage and river water is 20°C. The saturation DO at 20°C is 9.17 mg/l. Assume K1 = 0.1/day and K2 = 0.4/day (both with base 10). Calculate the critical DO deficit.
River DO mg/l. Both temperatures are 20°C, so no correction is needed. , (base 10), . Flows are in l/s.
Step 1: Conditions just after mixing
Step 2: Ultimate BOD and self-purification constant
Step 3: Critical time and critical deficit
Answer: critical DO deficit mg/l, reached after days (about 90.2 km downstream at 48 km/day). Minimum DO mg/l.
Note: the computed deficit is larger than the saturation DO (9.17 mg/l). In reality DO cannot fall below zero, so the stream would go anaerobic near the critical point and the effluent needs treatment before discharge. The negative value is simply what the formula gives for these data.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Time of critical DO deficit, 50 l/s city · Sanitary Engineering, chapter 6 · asked 2×
- Critical DO deficit, city 100 l/s · Sanitary Engineering, chapter 6 · asked 2×
- Critical DO deficit, location, sag curve · Sanitary Engineering, chapter 6
- Is treatment necessary? Town wastewater 300 l/s · Sanitary Engineering, chapter 6
- 1-day BOD 300 mg/l to 5-day at 30°C · Sanitary Engineering, chapter 5
- DO deficit 50 km downstream, 1.9 m³/s stream · Sanitary Engineering, chapter 6 · asked 2×
- Critical DO deficit and location downstream · Environment and Pollution Control, chapter 4
- Ca and Mg concentration, alkalinity (300 mg/l hardness) · Water Supply Engineering, chapter 4 · asked 2×
- Rural area 22000 L/day river supply (question text cut) · Water Supply Engineering, chapter 7
- Impounded reservoir, 400 m3/day demand · Water Supply Engineering, chapter 2