Design steps of side drain
Short answer
Design steps are: collect catchment data, find time of concentration and rainfall intensity, compute discharge by Q=CIA/360, choose drain shape and slope, size using Manning's equation, check non-silting and non-scouring velocities, add free board, and fix discharge points. The bed slope is at least 0.5%.
Write down the steps of design of side drain in road.
A side drain carries the runoff from the carriageway, shoulder and nearby catchment along the road. The design steps are:
- Collect data: catchment area (), slope, soil/ground cover, rainfall intensity for the chosen return period (5 to 10 years for side drains), and the longitudinal gradient of the road.
- Find the time of concentration and read the rainfall intensity for that duration.
- Compute the discharge with the rational formula:
with in mm/h and in hectares, and the runoff coefficient. 4. Select the shape and material: trapezoidal (side slope 1:1 to 1.5:1 in earth), rectangular (masonry or concrete, in hills) or V-shaped (small flows), and fix the bed slope, equal to road gradient but not less than 0.5%. 5. Size the drain by Manning's equation:
Assume dimensions, find , , , and revise until . 6. Check the velocity is more than the non-silting velocity (about 0.6 to 0.75 m/s) and less than the non-scouring limit of the soil/lining. 7. Add a free board (about 0.15 to 0.3 m) and provide lining or check dams where velocity is too high. 8. Fix the discharge points (mitre drains, cross drains) so that the length of drain does not exceed the capacity, and design the outfall protection.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Design steps of surface drainage · Transportation Engineering I, chapter 4 · asked 3×
- Special considerations in hill road design · Transportation Engineering I, chapter 5 · asked 5×
- Define hill road and design factors · Transportation Engineering I, chapter 5 · asked 2×
- Route location in hill road design · Transportation Engineering I, chapter 5
- Design steps of superelevation · Transportation Engineering I, chapter 3 · asked 3×
- Side-long ground hill road, 0-400 m · Estimating and Costing, chapter 6
- IC manufacturing steps; top-down F = xz + y · Embedded System, chapter 8
- Design of side intake with trashrack · Hydropower Engineering, chapter 5
- Column slab base: sketch and design steps · Design of Steel and Timber Structure, chapter 6 · asked 3×