Rate analysis: premix asphalt carpeting
Short answer
For 100 m², aggregate 5.43 m³, bitumen 531 kg, labour, fuel and roller give sub-total Rs 102,315; add 15% overhead/profit gives Rs 117,662.25, so the rate is Rs 1,176.62 per m² excluding VAT.
Prepare an analysis of rate for providing, laying and consolidation of 40 mm thick premix asphalt carpeting per m².
Basis
Rate for providing, laying and consolidating 40 mm thick premix asphalt carpeting, worked out for 100 m² and then divided to give the rate per m². Quantities follow the usual DUDBC / DoR (Department of Roads) practice; rates are illustrative.
Assumptions:
- Density of compacted mix = 2,300 kg/m³, so mass per m² = 0.04 x 2,300 = 92 kg.
- Bitumen content 5.5% of the mix = 5.06 kg/m² (plus 0.25 kg/m² for the tack coat on the base); aggregate = 86.94 kg/m², and a bulk density of loose aggregate of 1,600 kg/m³ gives 0.0543 m³/m².
Analysis (per 100 m²)
| Description | Qty | Unit | Rate (Rs) | Amount (Rs) |
|---|---|---|---|---|
| Aggregate (20 mm and 12 mm graded), loose | 5.43 | m³ | 3,500.00 | 19,005.00 |
| Bitumen 60/70 (5.06 kg/m² in the mix + 0.25 kg/m² tack coat) | 531 | kg | 110.00 | 58,410.00 |
| Labour: skilled (mixing, rakers) | 2 | md | 1,200.00 | 2,400.00 |
| Labour: unskilled | 15 | md | 900.00 | 13,500.00 |
| Fuel for heating and boiler | 1 | L.S. | 6,000.00 | 6,000.00 |
| Tools and equipment: 8-10 t roller (1 hr) | 1 | hr | 3,000.00 | 3,000.00 |
| Sub-total | 102,315.00 | |||
| Contractor's overhead and profit | 15% | 15,347.25 | ||
| Total per 100 m² | 117,662.25 |
Answer: Rate = 117,662.25 / 100 = Rs 1,176.62 per m² (excluding VAT).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Rate analysis: 25 mm premix carpeting · Estimating and Costing, chapter 4
- Rate analysis: 40 mm asphalt wearing coat · Estimating and Costing, chapter 4
- Rate analysis: 40 mm PCC 1:2:4 floor · Estimating and Costing, chapter 4
- Rate analysis: 12.5 mm plaster 1:5, per m² · Estimating and Costing, chapter 4 · asked 3×
- Rate analysis: 20 mm plaster 1:4 per 100 m² · Estimating and Costing, chapter 4 · asked 3×
- Rate analysis: 12.5 mm plaster 1:3, per 100 m² · Estimating and Costing, chapter 4