- Asked 3/22
- 2079 Bhadra · 4 marks
- 2074 Chaitra
- 2066 Bhadra (old course) · 2 marks
Revised estimate: when and why
Short answer
A revised estimate is prepared to replace the original sanction when cost overruns exceed about 5% due to rate changes, design modifications, major quantity variations, or after a long delay. For example, a school building revised from Rs 20,000,000 to Rs 22,000,000 after deepening the foundation increased cost by 10%.
Why and when should a revised estimate be prepared? Explain with an example.
A revised estimate is a fresh estimate prepared to replace the original sanctioned estimate when it is found that the original will be exceeded.
Why it is prepared
- To bring the sanctioned amount in line with the actual probable cost, so that payment beyond the sanction does not occur.
- To obtain approval for the changed cost before further expenditure.
When it is prepared
- The cost is likely to exceed the sanctioned estimate by more than the permitted limit (about 5%, as per the rule of the agency).
- Changes in rates of material or labour, or a new District Rate.
- Design changes or changes in the specification required by the site.
- Major variation in quantities, such as deeper or rock foundation.
- Cost of the work already done and the balance work have to be re-estimated after a long delay.
Example
A school building was sanctioned for Rs 20,000,000. During excavation, the soil was found weak and the foundation had to be deepened, adding Rs 2,000,000 (10%). As the increase exceeds the limit, a revised estimate of Rs 22,000,000 is prepared, giving the original items, extra items and the reason for each change, and sent for fresh approval.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Revised vs supplementary estimate · Estimating and Costing, chapter 3
- Types of estimates and when prepared · Estimating and Costing, chapter 3 · asked 4×
- Approximate estimate: what and when · Estimating and Costing, chapter 3 · asked 6×
- Complete estimate: why and when · Estimating and Costing, chapter 3