Short answer

Types: preliminary, detailed, revised, supplementary, complete, annual repair, extension/improvement. A revised estimate replaces the original sanction when costs exceed the permitted limit (e.g., design change), covering the whole work; a supplementary estimate adds new work not in the original scope, leaving the original estimate valid.

List the various types of estimates. Differentiate between revised estimate and supplementary estimate for a project.

Types of estimates

  1. Preliminary (approximate) estimate
  2. Detailed estimate
  3. Revised estimate
  4. Supplementary estimate
  5. Complete estimate
  6. Annual repair and maintenance estimate
  7. Extension and improvement estimate

Revised versus supplementary estimate

BasisRevised estimateSupplementary estimate
MeaningNew estimate that replaces the original sanctioned estimateAn additional estimate for extra work over the sanctioned one
ReasonOriginal cost will be exceeded (rate rise, design or quantity change)New work not in the original estimate is needed during construction
Effect on originalOriginal is cancelled and replacedOriginal remains valid; the new one is added to it
ScopeCovers the whole work (changed items and unchanged)Covers only the additional items
LimitUsually when cost exceeds the sanction by about 5%Prepared whenever extra work is required
ExampleFoundation deepened, cost rises, whole estimate redoneBoundary wall added to a building project