Types of estimates and when prepared

Short answer

Estimate types include preliminary (before design for approval), detailed (after drawings for tender), revised (when sanctioned cost will be exceeded), supplementary (for extra work during construction), and complete (total project cost including non-construction components). Examples are a school plinth-area estimate, hospital detailed estimate, bridge revised estimate, added boundary wall, and hospital with equipment.

List the various types of estimates and describe the circumstances under which each (preliminary, detailed, revised, supplementary, complete) is prepared, with examples.

TypeMeaningCircumstances in which it is preparedExample
Preliminary (approximate) estimateRough cost from plinth area/unit rates, before designPlanning, feasibility and administrative approvalSchool of 600 students by plinth area rate
Detailed estimateItem-wise quantities with rates and abstractAfter design and drawings, for technical sanction and tenderDetailed estimate of a hospital building
Revised estimateNew estimate replacing the sanctioned oneThe sanctioned estimate is likely to be exceeded by more than the allowed limit (usually 5%) due to rate rise, design change or quantity changeEstimate of a bridge revised after a deeper foundation was needed
Supplementary estimateEstimate for additional work not included earlierExtra work is needed during construction on an already-sanctioned projectAdding a boundary wall to a building under construction
Complete estimateTotal cost of all components of a projectTo know the final overall cost including land, design, equipment and servicesComplete cost of a hospital with equipment
Annual repair and maintenance estimateYearly cost of repairsPreparing the yearly maintenance budgetMaintenance of a road section
Extension and improvement estimateCost of new additions and improvementWhen an existing structure is extendedExtra floor on a building

Circumstances (summary)

  • Preliminary: at the approval stage, when drawings are not ready.
  • Detailed: once drawings are available, before tendering; it is the basis of the contract.
  • Revised: when the original sanction will be exceeded; it replaces the old estimate.
  • Supplementary: for a new addition to a sanctioned work; the original remains valid.
  • Complete: where the project cost includes more than construction.