Powerhouse plan and sections (Francis, 10 MW)

Short answer

For 10 MW with two 5 MW units at 80 m head, flow is about 7.24 m3/s per unit, runner diameter about 1.06 m. The powerhouse plan has two units plus erection bay, length about 22 m, breadth about 11 m, height about 14 m; section shows penstock, valve, spiral casing, runner, draft tube, generator, crane and control room.

Draw plan and sections of a powerhouse showing various components. Assume a Francis turbine is used in this powerhouse to generate electricity of 10 MW.

Assumptions

Total 10 MW with 2 units of 5 MW each, net head 80 m, vertical-shaft Francis turbines, ηo=0.88\eta_o = 0.88.

Q=50000.88×9.81×80=7.24 m3/s per unitQ = \frac{5000}{0.88 \times 9.81 \times 80} = 7.24\ \text{m}^3/\text{s per unit}

Rated speed 500 rpm (Ns≈148N_s \approx 148) and runner diameter D≈1.06D \approx 1.06 m.

Plan

  <-------------- 22 m --------------->
  +-----------------------------------+ ^
  | Unit 1     Unit 2     Erection   | |
  |  (G)        (G)         bay      | 11 m
  |  MIV        MIV      (loading)   | |
  +--||----------||-------------------+ v
   Penstock     Control + switchgear room
   -> Draft tubes -> tailrace

Section A-A (through one unit)

   roof truss  ========================
   crane rail  --- EOT crane ---
   |            GENERATOR             |  generator floor
   |__________  exciter  ____________|
   |      Turbine floor / governor    |
   |   Spiral casing ( runner )       |
 ~~|~~~~~~~~~~~ draft tube ~~~~~~~~~~~|~~ tailwater
   foundation raft
 penstock -> MIV -> spiral casing

Components shown

  • Penstock, main inlet valve, spiral casing, stay ring, guide vanes, runner and draft tube.
  • Generator, exciter and governor.
  • Overhead crane (about 30 t, lifting the rotor), erection bay and loading area.
  • Control room, switchgear, battery room, workshop and office; transformers outside.
  • Approximate dimensions: length about 22 m, breadth about 11 m, height about 14 m (draft tube floor to roof).