Cost budgeting
Short answer
Cost budgeting aggregates activity cost estimates to establish an authorized time-phased cost baseline. It adds contingency reserves for known risks and management reserves for unknown risks, producing a cumulative S-curve for performance measurement.
What do you mean by cost budgeting?
Cost budgeting (Determine Budget) is the process of aggregating the estimated costs of individual activities or work packages to establish an authorised cost baseline. It allocates the overall cost estimate to individual work items over time, so that the project's performance can be measured against it.
Inputs, tools and outputs
| Inputs | Tools | Outputs |
|---|---|---|
| Activity cost estimates, basis of estimates | Cost aggregation | Cost performance baseline (S-curve) |
| Scope baseline (WBS) | Reserve analysis | Project funding requirements |
| Project schedule | Expert judgment | Updates to project documents |
| Resource calendars, contracts | Historical relationships | |
| OPA | Funding limit reconciliation |
Steps
- Estimate cost of each work package.
- Aggregate upward to control accounts and project total.
- Add contingency reserve (for identified risks) to get the cost baseline.
- Add management reserve (for unknown risks) to get the project budget (not part of baseline).
- Time-phase the budget by schedule: cost per period.
- Reconcile with the funding limits of the organisation.
- Approve the cost baseline.
Work package estimates
-> Control accounts -> Cost baseline (+ contingency)
-> + Management reserve -> Project budget
Cumulative cost curve
Cost
| ___--- Budget
| __--
| __-- (S-curve)
+---------------------- time
Importance
- Gives a standard to measure and control cost (earned value).
- Shows when funds are needed.
- Supports approval and funding decisions.
Example: A 10-month web project costs Rs 20 lakh. Budget by month shows heavy spending in months 4-8 during development; a 10% contingency (Rs 2 lakh) is added.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Project cost versus product cost · ICT Project Management, chapter 9
- Cost estimating and types of estimates · ICT Project Management, chapter 9
- Cost of quality · ICT Project Management, chapter 10
- Capital budgeting; ARR numerical, Rs 100000 · Project Engineering, chapter 6
- Case study: new system vs existing (cost, manpower) · Instrumentation II, chapter 10 · asked 4×
- Proposal for computer lab: title, technical, cost · Communication English, chapter 6 · asked 2×
- Proposal for computer lab: background, technical, cost · Communication English, chapter 6 · asked 2×