Schedule development and control
Short answer
Schedule development creates the project schedule by analyzing sequences, durations, resources, and constraints using CPM and compression. Schedule control monitors actual progress, compares to baseline, analyzes variances, and implements corrective actions like crashing or fast-tracking to manage changes.
What do you mean by schedule development and control?
Schedule development is the process of analysing activity sequences, durations, resource requirements and schedule constraints to create the project schedule model. Schedule control is monitoring the status of the project to update progress and managing changes to the schedule baseline. Both belong to the Project Time Management knowledge area.
Schedule development
Inputs: activity list, sequence, resource requirements, duration estimates, constraints, calendars.
Tools and techniques:
- Network diagram analysis and Critical Path Method: forward and backward pass to find ES, EF, LS, LF, float.
- Critical chain method: add buffers for resource constraints.
- Resource levelling and smoothing.
- What-if analysis and simulation (Monte Carlo).
- Schedule compression: crashing (add resources, more cost) and fast tracking (do activities in parallel, more risk).
- Leads and lags, scheduling software.
Outputs: project schedule (Gantt chart, milestone chart, network diagram), schedule baseline, schedule data, updated calendars.
Schedule control
Concerned with determining current status, influencing factors that cause change, determining that the schedule has changed and managing the changes. Tools: performance reviews, variance analysis, trend analysis, earned value (SPI = EV/PV), what-if analysis, resource levelling, schedule compression, progress reports. Outputs: work performance measures, change requests, updates to the schedule baseline and plan.
Activities + durations + resources
-> CPM / Gantt -> Baseline schedule
-> Track actuals -> Variance -> Corrective action
Control steps
- Measure actual progress.
- Compare with baseline.
- Analyse variances.
- Decide on corrective actions (crash, fast track, re-sequence).
- Process changes through change control and update the schedule.
Example: If testing slips by 5 days, the manager fast-tracks documentation in parallel and adds one tester to recover.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Project development life cycle phases · ICT Project Management, chapter 1
- System development methodologies · ICT Project Management, chapter 4
- System development life cycle · ICT Project Management, chapter 4
- Integrated change control · ICT Project Management, chapter 7
- Project scope control · ICT Project Management, chapter 7
- Control charts · ICT Project Management, chapter 10
- Monitoring and quality, cost, schedule control · Project Engineering, chapter 4
- Schedule control and schedule control cycle · Project Engineering, chapter 4
- Crest, average and schedule speed; speed-time curve · Utilization of Electrical Energy, chapter 4
- Biogas plants under Clean Development Mechanism · Power Plant Design, chapter 1 · asked 2×